  1. 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 4/14/2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 4/12/2010 Current Activities this Week: Mass Excavation: Remaining Mass Excavation Activities are ongoing and are nearling completion. Removal of the Haul Road to Area C is complete and restoration of the Speedway Property is ongoing. Site Utilities: Speedway Property – Sod and seeding Installation of the new electrical ductbank is ongoing. installation has commenced. Approximately 150 linear feet is installed. Awaiting BPU resolution on manhole tie-in. Boring of the service line and Sanitary Main Line D is complete, installation of the steel casing is ongoing. Foundations: Area 1 Field Level – Column Pad placement in Area 1 is nearly complete. Installation of Field Walls has started. Concourse Level Area 2 – Waterline relocation piping is nearly complete and Area 1 Mezzanine Level – E-Line Footing installation backfill of line has started. is complete. E-Line Wall installation is ongoing. Area 1 Concourse Level – E-Line Footing installation Has started at Column Line 23.2. Area 2 Field Level – Excavation for the footings has started. Field Level Area 2 – Soil nail wall installation on remaining section (east of Column Line 14) has commenced. Building the Future
  2. 2. Soil Nail Wall: Area 2 – Shotcrete installation on the remaining sections has begun. Structural Steel Erection: Field Bowl – 300 Ton Crane has been mobilized and assembled (230’ Boom Length). Projected Activities occurring next Week: Field Level Area 2 – Excavation for A-Line footing has started. Mass Excavation: Removal of the ledges for soil nail wall installation will continue to be removed. Site Utilities: Waterline relocation will be complete. Installation of the Sanitary Manhole at the North end of Area 1 will begin. Field Level Bowl – Crane assembly Installation of the Storm Line on the East Side (France underway. Family Drive) of the site will begin. Deep Underground Sanitary in Area 1/2 will continue. Foundations: Area 2 Field Level – Placement of footings around stage will begin. Area 1 Mezzanine Level – Drilled Pier installation at D-Line will begin. Field Level Area 1 – Shot looking north from Area 1 Concourse Level – E-Line footing will be completed. Concourse Level showing column pads and deep underground sanitary line installation. Soil Nail Wall: Area 2 – Shotcrete wall installation east of Column 13 will continue. Structural Steel Erection: Erection of Structural Steel Sequence 1-1 will begin. Building the Future
  3. 3. Additional Photos: Field Level Area 1 – Field Wall installation is ongoing at the base of the north section of Field Level Area 1 – Placement of Elevator on-grade seating. F1 Pit Walls. Mezzanine Level Area 1 – Placement of concrete for D-Line Wall and Rebar set in Concourse Level Area 1 – E-Line Footing place for E-Line Wall at VIP Entrance. Placement at Column Line 23.2 Mezzanine Level Area 1 – Steel Casing installation under Village West Parkway for Field Level Area 1/2 – Making the turn from Sanitary Main Line. Area 1 into Area 2 with Foundations. Building the Future

×