Construction Update 07-21-2010

  1. 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 7.21.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 7.19.2010 Current Activities this Week: Mass Excavation: Backfilling of on-grade seating is ongoing in Area 2 and Area 3. Site Utilities: Storm Sewer Installation (Line 6000) is ongoing Area 3 – Installation of Storm Line 6000 is on the east side of France Family Drive. ongoing on the east side of France Family Drive. Foundations: Area 3 Field Level – Foundation installation continues on the east side of the site. Concrete Flatwork: Area 1 – North Mezzanine concrete placement is Complete at VIP Entrance. Prep work is ongoing for Next Slab-on-Grade pour (Column Line 26-24). Prep work is ongoing for Main Club topping slab placement. Field Level Area 1 – Cast-in-place concrete Structural Steel Erection: riser installation is ongoing. Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-7) Area 2 - Structural Steel Erection Sequence 2-1 is ongoing. Area 3 – Structural Steel Erection Sequence 3-1 has started. Underground MEP: Electrical Secondary Distribution is ongoing in Areas 2. Mezzanine Level Area 1 – Concrete for slab- on-grade at VIP Entrance is placed at North Mezzanine. Building the Future
  2. 2. MEP Rough-in: Area 1 – Shallow electrical and plumbing rough-in is ongoing. Ductwork installation on Suite Level is ongoing. Metal Stud Framing: Area 1 – Metal stud framing for Suite and Press Levels are ongoing. Field Level Area 1/2 – Steel Erection ongoing Projected Activities occurring next Week: in both Sequence 2-1 (right side of picture) and 3-1 (left side of picture). Mass Excavation: Backfilling of on-grade seating areas will continue in Area 3. Grading in Area 3 (east of A-Line) will continue. Site Utilities: Installation of the Storm Line 6000 on the East Side (France Family Drive) of the site will be complete. Deep Underground MEP: Deep Electrical Distribution installation will start again in Area 3. Foundations: Area 1 – Shot of the West Building from the Area 3 Field Level – Foundation installation will continue. south concourse area. Concrete Flatwork: Area 1 Field Level – Concrete placement for Slab-on-Grade will be completed to 24 Line. Area 1 Field Level – Installation of on-grade seating risers will continue. Structural Steel Erection: Erection of Structural Steel in Sequence 2-1 will continue. Erection of Structural Steel Sequence 3-1 will continue. Suite Level Area 1 – Shot at the front of the Erection of the Canopy Trusses will begin in Sequence 1-8. Suites of metal stud framing progress. Building the Future
  3. 3. Underground MEP: Electrical Secondary will continue in Area 3. MEP Rough-in: Plumbing and Electrical rough-in for Area 1 Field Level slab on grade will continue. MEP Rough-in at Suite Level will continue. Metal Stud Framing: Area 1 – Metal stud framing for Suite and Press Levels will Area 1 – Shot from Roof Level showing the continue. installation of the Canopy Roof Trusses. Suite Level Area 1 – Ductwork installation is ongoing. Building the Future
  4. 4. Additional Photos: Roof Level Area 1 – Shot looking between Area 1 – Shot of the West Building showing Canopy Trusses at 29 and 30 showing the Canopy Trusses, Stadium Suite and Suites bridging trusses, purlins and chevron braces. metal stud framing. Concourse Level Area 1 – Main Club slab-on- Field Level Area 1 – Shot looking north of grade is placed. on-grade seating. Area 1 – Metal decking installation is Field Level Area 1 – Shot of Supporter’s Club ongoing at Terrace Seating Area. Seating Area and Cauldron Club entrances. Building the Future

×