3. Part of the Potential Housing Opportunities Program
Currently Wilton is a small village (1,890 people and 590
homes)
A new town is planned in Wilton Junction Precinct
Residential (about 12,000 dwellings)
Employment (11,000 jobs)
Retail (at a new town centre)
School and other facilities.
http://www.planning.nsw.gov.au/wiltonjunction
Project background – Wilton Junction Precinct
3
4. Hume Highway
Interstate highway linking Sydney and Melboune
Main north-south corridor accessing Wilton
Two lanes in each direction and speed of 110 km
B-double route
Picton Road
State road travelling between Picton and Mount
Ousley Road
Main west-east corridor accessing Wilton
one lanes in each direction
freight route to Port Kembla and a commuter traffic
route on weekdays
Other key roads including Remembrance Drive and
Appin Road/Wilton Road
Road network
4
5. Transport management and accessibility plan
5
TMAP
Support the application for the rezoning of Wilton
Junction Precinct
Travel requirements of the Precinct by road, public
transport, walking and cycling
3-Tier Transport modelling
identify the transport impacts of the Wilton Junction
Precinct
assess the provision and staging of the required
traffic and transport infrastructureone lanes in each
direction
Macro/Meso/Micro
6. Strategic modelling
6
Sydney Strategic Travel Model (STM)
Maintained by BTS and Sydney GMA
provide origin-destination (OD) demand and
patterns for the existing year
determine the future year trip generation, trip
distribution and mode split for development
Subarea matrices were extracted from STM for
study area to consider impact on wider regional
network
7. Mesoscopic modelling
7
Select modelling platform
Relatively recent development and has been gaining
popularity in NSW
Intermediate level of detail between Macroscopic
and Microsimulation
Quickly assign traffic to alternative routes at wider
regional area
Test initial intersection design option for the
development area with acceptable level of accuracy
AIMSUN software was selected
Model network development
Cover Bargo to Campbelltown (about 35 km in
distance) and Picton to the Illawarra Escarpment
(about 36 km in distance)
Zone aggregation and disaggreation
8. Mesoscopic modelling
8
OD demand estimation
Initial cordon subarea matrices extracted from STM
Restructure matrices to fit Meso zone system
Furness matrix estimation
Adjust matrices with static traffic assignment
Fine-tune at dynamic traffic assignment
Traffic assignment
Considering the rural environment of the study area,
stochastic dynamic assignment method
Traffic proportionally assigned to alternative travel
routes with preference over shortest routes
9. Mesoscopic modelling
9
Calibration and validation
Network coding
Routing
Traffic flows
Travel time
Model stability
Existing road conditions
Heavy congestion on Narellan Road
Long delays for the turning traffic at the Hume
Highway/Picton Road intersection
Heavy but moving flows along Hume Highway and
Picton Road
10. Hybrid modelling
10
Micro pocket created for Wilton Junction Precint
Wider road network modelled at Meso level
Model network, zone system and database
common to both level
Parameters only applied to Micro level were
calibrated
Detailed analysis of intersection design at Micro
level
Transport infrastructure requirement and staging
plan were determined with Hybrid model results
11. Discussion
11
Global parameter in AIMSUN Meso
Time reaction is most influencing parameter
Difficult to calibrate it for the existing condition
TSS research indicated lower value leads to aggressive and unrealistic
driver behaviour
SIDRA model was used to cross check Meso model results
Our model review experience showed this parameter was commonly
changed to make model calibration results look right and no appropriate
justification was provided
Intersection Meso SIDRA
Picton Road/Pembroke
Parade
LOS B LOS C
Picton Road/Almond Street LOS B LOSC
12. Discussion
12
Sensitivity test for different traffic assignment method
Model was reviewed by RMS and found to be fit for purpose
Dynamic User Equilibrium (DUE) was suggested to test to check robustness of
model
Base model was recalibrated and validated using DUE to conduct like with like
comparison for future year scenario
DUE tended to assign more traffic to route with higher hierarchy and speed
Propose infrastructure upgrades would be able to accommodate the increased
demand on key routes
Confidence in our proposed infrastructure requirement was enhanced.
13. Conclusion
13
First application of Hybrid modelling for large-scale development in NSW
3-tier modelling framework is suitable for capturing development impact in wider regional
context and local envrionment
AIMSUN Mesoscopic modelling is able to quickly assess route choice in large network and
test initial intersection design with acceptable level of detail
Microsimulation pocket can be created to conduct detailed analysis of core study area
Road network, zone system and database are common to both Meso and Micro areas of
network can avoid manual interfacing between different Meso and Micro software packages
Time reaction is one of the most influencing parameters in AIMSUN Meso. Caution should
be taken when calibrating parameter value. Low parameter value tends to underestimate
traffic delays
Sensitivity test for DUE and DTA can be useful to build confidence in model robustness and
proposed upgrade scheme