S ecure  T raffic-light  E mergency  M anagement  S ystem   ( STEMS) Team GT Ambulance Chasers: Dan Boland Brandon Harring...
Overview <ul><li>Review of Our Concept </li></ul><ul><li>Progress Update </li></ul><ul><li>Preliminary Results </li></ul><...
Our Concept <ul><li>STEMS is an emergency traffic light bypass solution </li></ul><ul><li>STEMS reduces response time of e...
Timeline Update
Design Update
Design Update (cont’d)
Preliminary Results <ul><li>AES Encryption scheme progress </li></ul><ul><li>Ebox configuration progress </li></ul><ul><li...
Preliminary Results (cont’d)
Parts Status and Order Update <ul><li>Received: 1 eBox, 3 TLUs </li></ul><ul><li>Ordered and waiting on: 1 eBox, 1 Digital...
Outstanding Issues <ul><li>Unexpected interfacing issues  </li></ul><ul><li>Need to receive parts to begin prototyping and...
In Summary… <ul><li>Due to lack of parts, we have been unable to work on several major components of our design </li></ul>...
Questions?
Upcoming SlideShare
Loading in...5
×

GT Ambulance Chasers - Midterm Presentation_final2.ppt

307

Published on

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
307
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
1
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

GT Ambulance Chasers - Midterm Presentation_final2.ppt

  1. 1. S ecure T raffic-light E mergency M anagement S ystem ( STEMS) Team GT Ambulance Chasers: Dan Boland Brandon Harrington Brian Liu Kevin Wright
  2. 2. Overview <ul><li>Review of Our Concept </li></ul><ul><li>Progress Update </li></ul><ul><li>Preliminary Results </li></ul><ul><li>Parts Status and Orders Update </li></ul><ul><li>Outstanding Issues </li></ul><ul><li>Summary and Questions </li></ul>
  3. 3. Our Concept <ul><li>STEMS is an emergency traffic light bypass solution </li></ul><ul><li>STEMS reduces response time of emergency response crews, and increases overall safety on the roads </li></ul><ul><li>STEMS is a low cost and highly scalable solution </li></ul>
  4. 4. Timeline Update
  5. 5. Design Update
  6. 6. Design Update (cont’d)
  7. 7. Preliminary Results <ul><li>AES Encryption scheme progress </li></ul><ul><li>Ebox configuration progress </li></ul><ul><li>TLU progress </li></ul>
  8. 8. Preliminary Results (cont’d)
  9. 9. Parts Status and Order Update <ul><li>Received: 1 eBox, 3 TLUs </li></ul><ul><li>Ordered and waiting on: 1 eBox, 1 Digital Compass, 1 OOPIC, 2 Wireless-B USB Adapters, and 3 TLUs </li></ul>
  10. 10. Outstanding Issues <ul><li>Unexpected interfacing issues </li></ul><ul><li>Need to receive parts to begin prototyping and testing </li></ul><ul><li>Solidify demonstration concepts (i.e. use laptop to control/simulate 5 TLUs) </li></ul>
  11. 11. In Summary… <ul><li>Due to lack of parts, we have been unable to work on several major components of our design </li></ul><ul><li>Nevertheless we have made significant progress in other sectors of our design </li></ul><ul><li>Necessary reprioritizations and deviations from original Gantt chart should allow adequate time for successful completion of our project </li></ul>
  12. 12. Questions?