SlideShare a Scribd company logo
1 of 23
International Competitive BiddingIntroduction Guidelines Procurement underIBRD Loans and IDA Credits
Table of Contents Introduction Type and Size of Contracts Two-Stage Bidding Notification and Advertising Prequalification of Bidders
Introduction Guidelines Procurement under IBRD Loans and IDA Credits
Introduction Para 2.1 The objective of International Competitive Bidding (ICB), as described in these Guidelines, is to provide all eligible prospective bidders with timely and adequate notification of a Borrower’s requirements and an equal opportunity to bid for the required goods and works.
Type and Size of Contracts Guidelines Procurement under IBRD Loans and IDA Credits
Type and Size of Contracts Para 2.2 The bidding documents shall clearly state the type of contract to be entered into and contain the proposed contract provisions appropriate therefore.  The most common types of contracts provide for payments on the basis of  a lump sum,  unit prices,  reimbursable  cost plus fees, or  combinations thereof.
Type and Size of Contracts Reimbursable cost contracts are acceptable to the Bank only in exceptional circumstances such as conditions of high risk or where costs cannot be determined in advance with sufficient accuracy. Such contracts shall include appropriate incentives to limit costs.
Type and Size of Contracts The size and scope of individual contracts will depend on the  magnitude,  nature, and  location of the project.  For projects requiring a variety of goods and works, separate contracts generally are awarded for the supply and/or installation of different items of equipment and plant and for the works. For purposes of these Guidelines, “plant” refers to installed equipment, as in a production facility.
Type and Size of Contracts For a project requiring similar but separate items of equipment or works, bids may be invited under alternative contract options that would attract the interest of both small and large firms, which could be allowed, at their option, to bid for individual contracts (slices) or for a group of similar contracts (package).  All bids and combinations of bids shall be received by the same deadline and opened and evaluated simultaneously so as to determine the bid or combination of bids offering the lowest evaluated cost to the Borrower.
Type and Size of Contracts In certain cases the Bank may accept or require a turnkey contract under which the design and engineering, the supply and installation of equipment, and the construction of a complete facility or works are provided under one contract.  Alternatively, the Borrower may remain responsible for the design and engineering, and invite bids for a single responsibility contract for the supply and installation of all goods and works required for the project component.  Design and build, and management contracting contracts are also acceptable where appropriate.
Two-Stage Bidding Guidelines Procurement under IBRD Loans and IDA Credits
Two-Stage Bidding Para 2.6 In the case of turnkey contracts or contracts for large complex facilities or works of a special nature or complex information and communication technology, it may be undesirable or impractical to prepare complete technical specifications in advance.  In such a case, a two-stage bidding procedure may be used, under which first unpriced technical proposals on the basis of a conceptual design or performance specifications are invited, subject to technical as well as commercial clarifications and adjustments, to be followed by amended bidding documents and the submission of final technical proposals and priced bids in the second stage.
Notification and Advertising Guidelines Procurement under IBRD Loans and IDA Credits
Notification and Advertising Para 2.7 Timely notification of bidding opportunities is essential in competitive bidding. For projects that include ICB the Borrower is required to prepare and submit to the Bank a draft General Procurement Notice. The Bank will arrange for its publication in UN Development Business online(UNDB online) and in the Development Gateway’s  dgMarket).
Notification and Advertising Para 2.7 The Notice shall contain information concerning  the Borrower (or prospective Borrower),  amount and purpose of the loan,  scope of procurement under ICB, and  the name, telephone (or fax) number, and address of the Borrower’s agency responsible for procurement and the address of the Website where specific procurement notices will be posted.
Notification and Advertising Para 2.7 If known, the scheduled date for availability of prequalification or bidding documents should be indicated. The related prequalification or bidding documents, as the case may be, shall not be released to the public earlier than the date of publication of the General Procurement Notice.
Notification and Advertising Para 2.8 Invitations to prequalify or to bid, as the case may be, shall be advertised asSpecific Procurement Notices in at least one newspaper of national circulation in the Borrower’s country (or in the official gazette, or in an electronic portal with free access).  Such invitations shall also be published in UNDB online and in dgMarket.  Notification shall be given in sufficient time to enable prospective bidders to obtain prequalification or bidding documents and prepare and submit their responses.See para. 2.44.
Prequalification of Bidders Guidelines Procurement under IBRD Loans and IDA Credits
Prequalification of Bidders Para 2.9 Prequalification is usually necessary for large or complex works, or in any other circumstances in which the high costs of preparing detailed bids could discourage competition, such as custom-designed equipment, industrial plant, specialized services, some complex information and technology and contracts to be let under turnkey, design and build, or management contracting.  This also ensures that invitations to bid are extended only to those who have adequate capabilities and resources.
Prequalification of Bidders Para 2.9 Prequalification shall be based entirely upon the capability and resources of prospective bidders to perform the particular contract satisfactorily, taking into account their  experience and past performance on similar contracts,  capabilities with respect to personnel, equipment, and construction or manufacturing facilities, and  financial position.The Bank has prepared a Standard Prequalification Document for use by its Borrowers, where appropriate.
Prequalification of Bidders Para 2.10 The invitation to prequalify for bidding on specific contracts or groups of similar contracts shall be advertised and notified as described in paragraphs 2.7 and 2.8 above.  The scope of the contract and a clear statement of the requirements for qualification shall be sent to those who responded to the invitation.  All such applicants that meet the specified criteria shall be allowed to bid.  Borrowers shall inform all applicants of the results of prequalification.
Prequalification of Bidders Para 2.10 As soon as prequalification is completed, the bidding documents shall be made available to the qualified prospective bidders.  For prequalification for groups of contracts to be awarded over a period of time, a limit for the number or total value of awards to any one bidder may be made on the basis of the bidder’s resources.  The list of prequalified firms in such instances shall be updated periodically.  Verification of the information provided in the submission for prequalification shall be confirmed at the time of award of contract, and award may be denied to a bidder that is judged to no longer have the capability or resources to successfully perform the contract.
Wb procurement icb a

More Related Content

What's hot

Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Mauricio Portugal Ribeiro
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Joy Irman
 
Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation servicesabenyeung1
 
Wb consultant 2a
Wb consultant 2aWb consultant 2a
Wb consultant 2aJoy Irman
 
Tender and Bidding in Construction Projects
Tender and Bidding in Construction ProjectsTender and Bidding in Construction Projects
Tender and Bidding in Construction ProjectsIJERA Editor
 
Wb procurement other method-2
Wb procurement other method-2Wb procurement other method-2
Wb procurement other method-2Joy Irman
 
FREQUENTLY ASKED QUESTIONS(FAQs) RELATED TO PROCUREMENT
FREQUENTLY ASKED  QUESTIONS(FAQs) RELATED TO  PROCUREMENT FREQUENTLY ASKED  QUESTIONS(FAQs) RELATED TO  PROCUREMENT
FREQUENTLY ASKED QUESTIONS(FAQs) RELATED TO PROCUREMENT Nadeem Khan
 
REFORM ROADMAP OF PUBLIC PROCUREMENT SYSTEM & PROCUREMENT OF CONSULTANCY SE...
REFORM ROADMAP OF PUBLIC PROCUREMENT SYSTEM & PROCUREMENT OF  CONSULTANCY  SE...REFORM ROADMAP OF PUBLIC PROCUREMENT SYSTEM & PROCUREMENT OF  CONSULTANCY  SE...
REFORM ROADMAP OF PUBLIC PROCUREMENT SYSTEM & PROCUREMENT OF CONSULTANCY SE...Nadeem Khan
 
Roumen GALABINOV_presentation_final
Roumen GALABINOV_presentation_finalRoumen GALABINOV_presentation_final
Roumen GALABINOV_presentation_finalRoumen Galabinov
 
Bot(build operate transfer)
Bot(build operate transfer)Bot(build operate transfer)
Bot(build operate transfer)Satish Kambaliya
 

What's hot (11)

Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...Summary of the main features and rational of the hospital do suburbio bidding...
Summary of the main features and rational of the hospital do suburbio bidding...
 
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
Guidelines on The Use of Consultants by Asian Development Bank and Its Borrow...
 
Itt provision of wi fi network design and implementation services
Itt   provision of wi fi network design and implementation servicesItt   provision of wi fi network design and implementation services
Itt provision of wi fi network design and implementation services
 
Wb consultant 2a
Wb consultant 2aWb consultant 2a
Wb consultant 2a
 
Tender and Bidding in Construction Projects
Tender and Bidding in Construction ProjectsTender and Bidding in Construction Projects
Tender and Bidding in Construction Projects
 
Wb procurement other method-2
Wb procurement other method-2Wb procurement other method-2
Wb procurement other method-2
 
FREQUENTLY ASKED QUESTIONS(FAQs) RELATED TO PROCUREMENT
FREQUENTLY ASKED  QUESTIONS(FAQs) RELATED TO  PROCUREMENT FREQUENTLY ASKED  QUESTIONS(FAQs) RELATED TO  PROCUREMENT
FREQUENTLY ASKED QUESTIONS(FAQs) RELATED TO PROCUREMENT
 
Surety Bonds
Surety BondsSurety Bonds
Surety Bonds
 
REFORM ROADMAP OF PUBLIC PROCUREMENT SYSTEM & PROCUREMENT OF CONSULTANCY SE...
REFORM ROADMAP OF PUBLIC PROCUREMENT SYSTEM & PROCUREMENT OF  CONSULTANCY  SE...REFORM ROADMAP OF PUBLIC PROCUREMENT SYSTEM & PROCUREMENT OF  CONSULTANCY  SE...
REFORM ROADMAP OF PUBLIC PROCUREMENT SYSTEM & PROCUREMENT OF CONSULTANCY SE...
 
Roumen GALABINOV_presentation_final
Roumen GALABINOV_presentation_finalRoumen GALABINOV_presentation_final
Roumen GALABINOV_presentation_final
 
Bot(build operate transfer)
Bot(build operate transfer)Bot(build operate transfer)
Bot(build operate transfer)
 

Similar to Wb procurement icb a

Topic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxTopic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxVanJasperCastillo
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03ypinada
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptxssuser4ae21a
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qumes manandhar
 
Wb procurement icb c2
Wb procurement icb c2Wb procurement icb c2
Wb procurement icb c2Joy Irman
 
Adb procurement guidelines icb-b3
Adb procurement guidelines   icb-b3Adb procurement guidelines   icb-b3
Adb procurement guidelines icb-b3Joy Irman
 
Wb procurement other method-1
Wb procurement other method-1Wb procurement other method-1
Wb procurement other method-1Joy Irman
 
Adb procurement guidelines icb-b2
Adb procurement guidelines   icb-b2Adb procurement guidelines   icb-b2
Adb procurement guidelines icb-b2Joy Irman
 
Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”RCREEE
 
Wb procurement icb d
Wb procurement icb dWb procurement icb d
Wb procurement icb dJoy Irman
 
Bid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal PradeshBid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal PradeshHeadway Solar
 
Adb procurement guidelines icb-c1
Adb procurement guidelines   icb-c1Adb procurement guidelines   icb-c1
Adb procurement guidelines icb-c1Joy Irman
 
1658466483_Supply_of_Stationery_Items_English.pdf
1658466483_Supply_of_Stationery_Items_English.pdf1658466483_Supply_of_Stationery_Items_English.pdf
1658466483_Supply_of_Stationery_Items_English.pdfAMITTRIPATHI182
 
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)Gensol Engineering Limited
 
Procurement of infrastructure projects
Procurement of infrastructure projectsProcurement of infrastructure projects
Procurement of infrastructure projectswil_mia
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.pptssuser32da691
 
VIETNAM – The World Bank is asking Duane Morris about Doing Business and Gove...
VIETNAM – The World Bank is asking Duane Morris about Doing Business and Gove...VIETNAM – The World Bank is asking Duane Morris about Doing Business and Gove...
VIETNAM – The World Bank is asking Duane Morris about Doing Business and Gove...Dr. Oliver Massmann
 

Similar to Wb procurement icb a (20)

Topic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxTopic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptx
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03
 
Final standard tender doc
Final standard tender docFinal standard tender doc
Final standard tender doc
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Wb procurement icb c2
Wb procurement icb c2Wb procurement icb c2
Wb procurement icb c2
 
Adb procurement guidelines icb-b3
Adb procurement guidelines   icb-b3Adb procurement guidelines   icb-b3
Adb procurement guidelines icb-b3
 
Wb procurement other method-1
Wb procurement other method-1Wb procurement other method-1
Wb procurement other method-1
 
Adb procurement guidelines icb-b2
Adb procurement guidelines   icb-b2Adb procurement guidelines   icb-b2
Adb procurement guidelines icb-b2
 
Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”
 
Wb procurement icb d
Wb procurement icb dWb procurement icb d
Wb procurement icb d
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
 
Bid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal PradeshBid document for Solar in Himachal Pradesh
Bid document for Solar in Himachal Pradesh
 
Chapter -Two (2).pdf
Chapter -Two (2).pdfChapter -Two (2).pdf
Chapter -Two (2).pdf
 
Adb procurement guidelines icb-c1
Adb procurement guidelines   icb-c1Adb procurement guidelines   icb-c1
Adb procurement guidelines icb-c1
 
1658466483_Supply_of_Stationery_Items_English.pdf
1658466483_Supply_of_Stationery_Items_English.pdf1658466483_Supply_of_Stationery_Items_English.pdf
1658466483_Supply_of_Stationery_Items_English.pdf
 
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
 
Procurement of infrastructure projects
Procurement of infrastructure projectsProcurement of infrastructure projects
Procurement of infrastructure projects
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 
VIETNAM – The World Bank is asking Duane Morris about Doing Business and Gove...
VIETNAM – The World Bank is asking Duane Morris about Doing Business and Gove...VIETNAM – The World Bank is asking Duane Morris about Doing Business and Gove...
VIETNAM – The World Bank is asking Duane Morris about Doing Business and Gove...
 

More from Joy Irman

Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Joy Irman
 
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Joy Irman
 
Lampiran iv b jasa konsultansi - perorangan
Lampiran iv b   jasa konsultansi - peroranganLampiran iv b   jasa konsultansi - perorangan
Lampiran iv b jasa konsultansi - peroranganJoy Irman
 
Lampiran iv a jasa konsultansi - badan usaha
Lampiran iv a   jasa konsultansi - badan usahaLampiran iv a   jasa konsultansi - badan usaha
Lampiran iv a jasa konsultansi - badan usahaJoy Irman
 
Consulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development BankConsulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development BankJoy Irman
 
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingGuidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingJoy Irman
 
Guidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA LoansGuidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA LoansJoy Irman
 
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...Joy Irman
 
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeriJoy Irman
 
12 konsep ramah lingkungan
12 konsep ramah lingkungan12 konsep ramah lingkungan
12 konsep ramah lingkunganJoy Irman
 
13 pengadaan secara elektronik
13 pengadaan secara elektronik13 pengadaan secara elektronik
13 pengadaan secara elektronikJoy Irman
 
6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaanJoy Irman
 
3 1 organisasi pengadaan
3 1 organisasi pengadaan3 1 organisasi pengadaan
3 1 organisasi pengadaanJoy Irman
 
4 rencana umum pengadaan barang
4 rencana umum pengadaan barang4 rencana umum pengadaan barang
4 rencana umum pengadaan barangJoy Irman
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelolaJoy Irman
 
5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelolaJoy Irman
 
3 7 penyedia barang jasa
3 7 penyedia barang jasa3 7 penyedia barang jasa
3 7 penyedia barang jasaJoy Irman
 
3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaanJoy Irman
 
3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaanJoy Irman
 
3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmenJoy Irman
 

More from Joy Irman (20)

Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
 
Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010Penjelasan atas peraturan presiden nomor 54 tahun 2010
Penjelasan atas peraturan presiden nomor 54 tahun 2010
 
Lampiran iv b jasa konsultansi - perorangan
Lampiran iv b   jasa konsultansi - peroranganLampiran iv b   jasa konsultansi - perorangan
Lampiran iv b jasa konsultansi - perorangan
 
Lampiran iv a jasa konsultansi - badan usaha
Lampiran iv a   jasa konsultansi - badan usahaLampiran iv a   jasa konsultansi - badan usaha
Lampiran iv a jasa konsultansi - badan usaha
 
Consulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development BankConsulting Services Operation Manual, Asian Development Bank
Consulting Services Operation Manual, Asian Development Bank
 
Guidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank FinancingGuidelines for the Use of Consultants under Islamic Development Bank Financing
Guidelines for the Use of Consultants under Islamic Development Bank Financing
 
Guidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA LoansGuidelines for the Employment of Consultants under Japanese ODA Loans
Guidelines for the Employment of Consultants under Japanese ODA Loans
 
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
Guidelines Selection and Employment of Consultants under IBRD Loans and IDA C...
 
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
10 pengadaan barang jasa yang dibiayai dengan dana pinjaman hibah luar negeri
 
12 konsep ramah lingkungan
12 konsep ramah lingkungan12 konsep ramah lingkungan
12 konsep ramah lingkungan
 
13 pengadaan secara elektronik
13 pengadaan secara elektronik13 pengadaan secara elektronik
13 pengadaan secara elektronik
 
6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan6 1 persiapan dan perencanaan pengadaan
6 1 persiapan dan perencanaan pengadaan
 
3 1 organisasi pengadaan
3 1 organisasi pengadaan3 1 organisasi pengadaan
3 1 organisasi pengadaan
 
4 rencana umum pengadaan barang
4 rencana umum pengadaan barang4 rencana umum pengadaan barang
4 rencana umum pengadaan barang
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola
 
5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola5 1 ketentuan umum swakelola
5 1 ketentuan umum swakelola
 
3 7 penyedia barang jasa
3 7 penyedia barang jasa3 7 penyedia barang jasa
3 7 penyedia barang jasa
 
3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan3 6 pejabat penerima hasil pekerjaan
3 6 pejabat penerima hasil pekerjaan
 
3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan3 5 ulp pejabat pengadaan
3 5 ulp pejabat pengadaan
 
3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen3 4 pejabat pembuat komitmen
3 4 pejabat pembuat komitmen
 

Recently uploaded

Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandSharisaBethune
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 

Recently uploaded (20)

Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal Brand
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 

Wb procurement icb a

  • 1. International Competitive BiddingIntroduction Guidelines Procurement underIBRD Loans and IDA Credits
  • 2. Table of Contents Introduction Type and Size of Contracts Two-Stage Bidding Notification and Advertising Prequalification of Bidders
  • 3. Introduction Guidelines Procurement under IBRD Loans and IDA Credits
  • 4. Introduction Para 2.1 The objective of International Competitive Bidding (ICB), as described in these Guidelines, is to provide all eligible prospective bidders with timely and adequate notification of a Borrower’s requirements and an equal opportunity to bid for the required goods and works.
  • 5. Type and Size of Contracts Guidelines Procurement under IBRD Loans and IDA Credits
  • 6. Type and Size of Contracts Para 2.2 The bidding documents shall clearly state the type of contract to be entered into and contain the proposed contract provisions appropriate therefore. The most common types of contracts provide for payments on the basis of a lump sum, unit prices, reimbursable cost plus fees, or combinations thereof.
  • 7. Type and Size of Contracts Reimbursable cost contracts are acceptable to the Bank only in exceptional circumstances such as conditions of high risk or where costs cannot be determined in advance with sufficient accuracy. Such contracts shall include appropriate incentives to limit costs.
  • 8. Type and Size of Contracts The size and scope of individual contracts will depend on the magnitude, nature, and location of the project. For projects requiring a variety of goods and works, separate contracts generally are awarded for the supply and/or installation of different items of equipment and plant and for the works. For purposes of these Guidelines, “plant” refers to installed equipment, as in a production facility.
  • 9. Type and Size of Contracts For a project requiring similar but separate items of equipment or works, bids may be invited under alternative contract options that would attract the interest of both small and large firms, which could be allowed, at their option, to bid for individual contracts (slices) or for a group of similar contracts (package). All bids and combinations of bids shall be received by the same deadline and opened and evaluated simultaneously so as to determine the bid or combination of bids offering the lowest evaluated cost to the Borrower.
  • 10. Type and Size of Contracts In certain cases the Bank may accept or require a turnkey contract under which the design and engineering, the supply and installation of equipment, and the construction of a complete facility or works are provided under one contract. Alternatively, the Borrower may remain responsible for the design and engineering, and invite bids for a single responsibility contract for the supply and installation of all goods and works required for the project component. Design and build, and management contracting contracts are also acceptable where appropriate.
  • 11. Two-Stage Bidding Guidelines Procurement under IBRD Loans and IDA Credits
  • 12. Two-Stage Bidding Para 2.6 In the case of turnkey contracts or contracts for large complex facilities or works of a special nature or complex information and communication technology, it may be undesirable or impractical to prepare complete technical specifications in advance. In such a case, a two-stage bidding procedure may be used, under which first unpriced technical proposals on the basis of a conceptual design or performance specifications are invited, subject to technical as well as commercial clarifications and adjustments, to be followed by amended bidding documents and the submission of final technical proposals and priced bids in the second stage.
  • 13. Notification and Advertising Guidelines Procurement under IBRD Loans and IDA Credits
  • 14. Notification and Advertising Para 2.7 Timely notification of bidding opportunities is essential in competitive bidding. For projects that include ICB the Borrower is required to prepare and submit to the Bank a draft General Procurement Notice. The Bank will arrange for its publication in UN Development Business online(UNDB online) and in the Development Gateway’s dgMarket).
  • 15. Notification and Advertising Para 2.7 The Notice shall contain information concerning the Borrower (or prospective Borrower), amount and purpose of the loan, scope of procurement under ICB, and the name, telephone (or fax) number, and address of the Borrower’s agency responsible for procurement and the address of the Website where specific procurement notices will be posted.
  • 16. Notification and Advertising Para 2.7 If known, the scheduled date for availability of prequalification or bidding documents should be indicated. The related prequalification or bidding documents, as the case may be, shall not be released to the public earlier than the date of publication of the General Procurement Notice.
  • 17. Notification and Advertising Para 2.8 Invitations to prequalify or to bid, as the case may be, shall be advertised asSpecific Procurement Notices in at least one newspaper of national circulation in the Borrower’s country (or in the official gazette, or in an electronic portal with free access). Such invitations shall also be published in UNDB online and in dgMarket. Notification shall be given in sufficient time to enable prospective bidders to obtain prequalification or bidding documents and prepare and submit their responses.See para. 2.44.
  • 18. Prequalification of Bidders Guidelines Procurement under IBRD Loans and IDA Credits
  • 19. Prequalification of Bidders Para 2.9 Prequalification is usually necessary for large or complex works, or in any other circumstances in which the high costs of preparing detailed bids could discourage competition, such as custom-designed equipment, industrial plant, specialized services, some complex information and technology and contracts to be let under turnkey, design and build, or management contracting. This also ensures that invitations to bid are extended only to those who have adequate capabilities and resources.
  • 20. Prequalification of Bidders Para 2.9 Prequalification shall be based entirely upon the capability and resources of prospective bidders to perform the particular contract satisfactorily, taking into account their experience and past performance on similar contracts, capabilities with respect to personnel, equipment, and construction or manufacturing facilities, and financial position.The Bank has prepared a Standard Prequalification Document for use by its Borrowers, where appropriate.
  • 21. Prequalification of Bidders Para 2.10 The invitation to prequalify for bidding on specific contracts or groups of similar contracts shall be advertised and notified as described in paragraphs 2.7 and 2.8 above. The scope of the contract and a clear statement of the requirements for qualification shall be sent to those who responded to the invitation. All such applicants that meet the specified criteria shall be allowed to bid. Borrowers shall inform all applicants of the results of prequalification.
  • 22. Prequalification of Bidders Para 2.10 As soon as prequalification is completed, the bidding documents shall be made available to the qualified prospective bidders. For prequalification for groups of contracts to be awarded over a period of time, a limit for the number or total value of awards to any one bidder may be made on the basis of the bidder’s resources. The list of prequalified firms in such instances shall be updated periodically. Verification of the information provided in the submission for prequalification shall be confirmed at the time of award of contract, and award may be denied to a bidder that is judged to no longer have the capability or resources to successfully perform the contract.