I-74 Bettendorf Local Roads Meeting
Upcoming SlideShare
Loading in...5
×
 

I-74 Bettendorf Local Roads Meeting

on

  • 2,694 views

November 7, 2012 Bettendorf Local Roads Presentation

November 7, 2012 Bettendorf Local Roads Presentation

Statistics

Views

Total Views
2,694
Views on SlideShare
593
Embed Views
2,101

Actions

Likes
1
Downloads
12
Comments
0

3 Embeds 2,101

http://www.iowadot.gov 2073
http://accessibility_checker.siteimprove.com 17
http://testiowadot 11

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

I-74 Bettendorf Local Roads Meeting I-74 Bettendorf Local Roads Meeting Presentation Transcript

  • 1I-74 Bettendorf Local RoadsMeetingNovember 7, 2012Bettendorf City Hall1609 State StreetBettendorf, Iowa
  • 2Funding Update Bettendorf, IowaMoline, Illinois Davenport, Iowa
  • 3Funding Update• Projected Funding ▫ Federal Transportation Bill passed on 7/7/12
  • 4Funding Update• Projected Funding ▫ Iowa DOT 2013 -2017 ProgramDRAFT 2013 - 2017 IOWA HIGHWAY PROGRAMRTE ADT LOCATION MILES TYPE OF WORK 2013 2014 2015 2016 201774 20300 53RD ST EROSION 250 INTERCHANGE IN CONTROL DAVENPORT74 34800 IN BETTENDORF 2.5 RIGHT OF WAY 4208 4715 4201 3734 AND DAVENPORT GRADE AND 13700 PAVE ▫ Illinois DOT 2013 -2018 Program ▫ $73 Million
  • 5Funding Update
  • 6Funding Update
  • 7Funding Update
  • 8Bettendorf Local Roads – Advance Work Bettendorf, Iowa Moline, Illinois Davenport, Iowa
  • 9Bettendorf Local Roads – Advance Work • The letting date is September 16, 2014. • Potential changes were possible due to the advancement of the local roads.
  • 10Bettendorf Local Roads – Advance Work
  • 11Bettendorf Local Roads – Advance Work • Eliminate the State Street to Gilbert Street Diagonal Connection ▫ Original design closed State Street for the new I-74 piers ▫ New piers not constructed, so State Street can stay open ▫ Diagonal connection is no longer needed for staging ▫ Land occupied by the connection could become developable ▫ State Street will need patching and/or resurfacing ▫ Ownership of State Street will transfer to the City
  • 12Bettendorf Local Roads – Advance Work
  • 13Bettendorf Local Roads – Advance Work • Geometry Existing State Street & Proposed US 67 ▫ Sharp skew angle was not desirable ▫ Eliminate the connection  Access to the area between 11th and 12th Streets would be via new US 67, south on 12th Street and west on State Street - Rejected ▫ Modify the connection  State Street one way between 11th and 12th Street  QCA Spas and Adel would have right-in/right-out entrances as they do today.
  • 14Bettendorf Local Roads – Advance Work
  • 15Bettendorf Local Roads – Initial
  • 16Bettendorf Local Roads – Current
  • 17Bettendorf Local Roads – Key Issues • WB I-74 Exit Ramp to State Street/US 67 ▫ To be maintained at all times ▫ Temporary connection in the interim condition • Intersection of State Street and 12th Street ▫ May experience capacity issues in the interim condition ▫ Kimberly and State Street accessing the EB entrance ramp ▫ Intersection often experiences delays now
  • 18Bettendorf Local Roads – Current
  • 19Bettendorf Local Roads – Key Issues • Calvert Drive to Remain Open Until I-74 Built ▫ If closed, traffic exiting businesses north of Mississippi Blvd on 14th Street would need to detour north to Central then back on 15th Street to access the downtown ▫ Existing traffic on Calvert Drive is light, however a detour may cause confusion for drivers • Parking ▫ Some parking lot spaces will be lost ▫ There is the potential to gain some spaces along State Street.
  • 20Bettendorf Local Roads – Parking
  • 21Bettendorf Local Roads – Properties
  • 22Bettendorf Local Roads – Properties • Total Acquistion (Blue Shaded Lots) ▫ Largely, existing building have been removed ▫ Contract to remove six buildings (320, 327, 335, 359, 361, 368) ▫ Purchased but not possesed (341, BP Station 402 State St) • Parcel 365 ▫ 412 -16th St should be marked with red cross hashes. This is a parcel that is possibly a total acquisition
  • 23Bettendorf Local Roads – Properties
  • 24Bettendorf Local Roads – Properties • Properties Acquisition ▫ The goal is to acquire all properties by the end of 2013 ▫ All of the properties will need to be cleared prior to the September 2014 letting
  • 25Bettendorf Local Roads – Properties
  • 26Bettendorf Local Roads – Properties • Potential Excess Property ▫ Property outside the red dashed “need line” ▫ Proposed ROW lines not finalized until after the local road project is fully designed ▫ Not likely dispose of any excess property along the I-74 mainline and ramps until this work is completed ▫ Lots needed for mainline construction are all lots between 13th Street and 15th Street
  • 27Bettendorf Local Roads – Properties
  • 28Plan Development Update Bettendorf, IowaMoline, Illinois Davenport, Iowa
  • 29Iowa Plans - 100% Unapproved Plans• Roadway Plans ▫ Contract A (161) – Completed ▫ Contract B (205) – Completed ▫ Contract C (206) – Completed ▫ Contract D (207) – Completed ▫ Contract E (226) – Will be Completed in December• Signing Plans ▫ Being prepared by the Iowa DOT• ROW plans and plats (partial takes) ▫ Work to begin in March 2013• Iowa Utility Process ▫ Utilities to owners in December 2012
  • 30Iowa Plans - 100% Unapproved Plans• Bridge Plans ▫ Iowa Ramps A, B, C and D – Completed ▫ WB Iowa Viaduct – Completed ▫ EB Iowa Viaduct – Completed ▫ WB North Approach – Completed ▫ WB South Approach – Completed ▫ EB North Approach – Completed ▫ EB South Approach – Completed ▫ 100% Arch Substructure Plans – Completed ▫ 100% Arch Superstructure Plans – Completed• Bridge Demolition Plans ▫ Suspension Spans – Completed ▫ Truss Spans – Completed
  • 31Illinois Plans• Roadway Plans: 90% Complete Submittal ▫ Contract A – Completed ▫ Contract B – Completed ▫ Contract C – Completed ▫ Contract D – Will be Completed in January• Structure Plans ▫ Pre-Final Plans Completed by February 15 2012• ROW plans and plats (partial takes) ▫ Work began in March 2012• Illinois Utility Process ▫ 90% Plans sent to utilities/agencies in late August ▫ Utility owners response due December 31st
  • 32 Typology E – Landscape Design – Bettendorf, Iowa1/22/2013
  • 33 Typology E- Typical Landscape Design1/22/2013
  • 34 I-74 Corridor Landscape • Assume mow edge along roadway entire mainline at interchange/ramps • Plans show plant material areas with idea that some earthwork can occur to enhance character and conditions (i.e. aesthetics, slopes & drainage) • Possibility of Right of Way fence enhancement • Possibility of selective thinning of existing tree species/understory plant material1/22/2013
  • 35I-74 Bettendorf Local RoadsMeeting THANK YOU!