Community Program  Advisory Committee Tuesday, May 17, 2005
Today’s Meeting <ul><li>Program Update </li></ul><ul><li>$161 million in contracts awarded </li></ul><ul><ul><li>Bay View ...
BVWWTP – EQ Basin <ul><li>Construction begins in June </li></ul><ul><li>Completed by December 2006 </li></ul><ul><li>Low b...
BVWWTP – Grit Facility <ul><li>Construction began in April </li></ul><ul><li>Completed by Fall 2006 </li></ul><ul><li>$13....
BVWWTP – Grit Facility
BVWWTP – Grit Facility
BVWWTP – Grit Facility
BVWWTP –  Wet Weather/ Ballasted Flocculation <ul><li>Construction begins in May </li></ul><ul><li>Completed by Fall 2006 ...
290 th  Street Pump Station <ul><li>Substantially complete </li></ul><ul><li>Landscaping underway </li></ul><ul><li>Contra...
290 th  Street Pump Station
290 th  Street Pump Station
290 th  Street Pump Station
290 th  Street Pump Station
Edgewater Pump Station <ul><li>Working on startup, plan to start testing in a few weeks </li></ul><ul><li>Completed by ear...
Edgewater Pump Station
Edgewater Pump Station
Edgewater Construction <ul><li>Currently testing 24-inch force main, then will test 8-inch force main </li></ul><ul><li>Co...
Edgewater Construction
Edgewater Construction
River Road Park <ul><li>Construction underway </li></ul><ul><li>Completed by Fall 2007 </li></ul><ul><li>$3.6 million (pum...
River Road Park
River Road Park
River Road <ul><li>Water line nearly complete </li></ul><ul><li>Sewer line will be completed by Fall 2005 </li></ul><ul><l...
River Road
River Road
LTCP/EPA update <ul><li>LTCP </li></ul><ul><li>EPA </li></ul>
Next meeting <ul><li>Other issues </li></ul><ul><li>Next meeting date, time </li></ul>
Upcoming SlideShare
Loading in...5
×

CPAC Meeting 5-17-05

347

Published on

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
347
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
1
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Transcript of "CPAC Meeting 5-17-05"

  1. 1. Community Program Advisory Committee Tuesday, May 17, 2005
  2. 2. Today’s Meeting <ul><li>Program Update </li></ul><ul><li>$161 million in contracts awarded </li></ul><ul><ul><li>Bay View Wastewater Treatment Plant </li></ul></ul><ul><ul><li>Point Place </li></ul></ul><ul><ul><li>River Road </li></ul></ul><ul><li>LTCP/EPA Update </li></ul><ul><li>Next Meeting </li></ul>
  3. 3. BVWWTP – EQ Basin <ul><li>Construction begins in June </li></ul><ul><li>Completed by December 2006 </li></ul><ul><li>Low bid was $28 million </li></ul><ul><li>Contract with Rudolph Libbe being finalized </li></ul>
  4. 4. BVWWTP – Grit Facility <ul><li>Construction began in April </li></ul><ul><li>Completed by Fall 2006 </li></ul><ul><li>$13.9 million </li></ul><ul><li>Contractor is Rudolph Libbe </li></ul>
  5. 5. BVWWTP – Grit Facility
  6. 6. BVWWTP – Grit Facility
  7. 7. BVWWTP – Grit Facility
  8. 8. BVWWTP – Wet Weather/ Ballasted Flocculation <ul><li>Construction begins in May </li></ul><ul><li>Completed by Fall 2006 </li></ul><ul><li>$40 million </li></ul><ul><li>Contractor is Mosser Construction </li></ul>
  9. 9. 290 th Street Pump Station <ul><li>Substantially complete </li></ul><ul><li>Landscaping underway </li></ul><ul><li>Contractor was Gardner Mechanical </li></ul>
  10. 10. 290 th Street Pump Station
  11. 11. 290 th Street Pump Station
  12. 12. 290 th Street Pump Station
  13. 13. 290 th Street Pump Station
  14. 14. Edgewater Pump Station <ul><li>Working on startup, plan to start testing in a few weeks </li></ul><ul><li>Completed by early Summer </li></ul><ul><li>$4 million </li></ul><ul><li>Contractor is Walbridge Aldinger </li></ul>
  15. 15. Edgewater Pump Station
  16. 16. Edgewater Pump Station
  17. 17. Edgewater Construction <ul><li>Currently testing 24-inch force main, then will test 8-inch force main </li></ul><ul><li>Completed this Summer; resumes Winter 2005 </li></ul><ul><li>$2.5 million </li></ul><ul><li>Contractor is Crestline Paving </li></ul>
  18. 18. Edgewater Construction
  19. 19. Edgewater Construction
  20. 20. River Road Park <ul><li>Construction underway </li></ul><ul><li>Completed by Fall 2007 </li></ul><ul><li>$3.6 million (pump station and basin) </li></ul><ul><li>Contractor is E.S. Wagner </li></ul>
  21. 21. River Road Park
  22. 22. River Road Park
  23. 23. River Road <ul><li>Water line nearly complete </li></ul><ul><li>Sewer line will be completed by Fall 2005 </li></ul><ul><li>$1.8 million </li></ul><ul><li>Contractor is Anderzack Pitzen </li></ul>
  24. 24. River Road
  25. 25. River Road
  26. 26. LTCP/EPA update <ul><li>LTCP </li></ul><ul><li>EPA </li></ul>
  27. 27. Next meeting <ul><li>Other issues </li></ul><ul><li>Next meeting date, time </li></ul>
  1. A particular slide catching your eye?

    Clipping is a handy way to collect important slides you want to go back to later.

×