SlideShare a Scribd company logo
1 of 5
Download to read offline
MAINTAINABILITY
ENGINEERING
Maintainability Analysis
Purpose

The purpose of this task is to translate data from contractor’s studies,
engineering reports and information which is available from the Contracting
Activity (CA) into a detailed design approach and to provide inputs to the
detailed maintenance and support plan, which is part of the Logistics Support
Analysis (LSA). The four main goals are:
• To establish design criteria that will provide the desired system features
• To allow for design decisions to be made through the evaluation of

alternatives and through the use of trade-off studies
• To contribute toward establishing maintenance, repair and servicing

policies and support maintainability achievement
• To verify that the design complies with maintainability design
requirements

Scope

The following Table reproduced from MIL-STD-470B (Maintainability
Program For Systems And Equipment) contains identification to show when
the Maintainability Analysis (Task 205) is used in different Program Phases.
In the Contract Data Requirements List (CDRL), the Task 205 is referred as
DI-R-7109 and the recommended delivery date to the customer is 30 days
prior to PDR & CDR
TASK

TITLE

TASK
TYPE

PROGRAM PHASE

OSD

Concept

205

Maintainability
Analysis

ENG

Validatio
n

FSD

Production

S(3)

G(3)

G(1)

C(1)

ENG - Maintainability Engineering
OSD - Operational System Developments (Modifications)
G - Generally Applicable
S - Selectively Applicable
C - Generally Applicable to design changes only
(1) - Requires considerable interpretation of intent to be cost effective
(3) - Appropriate for those task elements suitable to definition during phase

http://www.linkedin.com/in/hilaireperera
Hilaire Ananda Perera PEng
Long Term Quality Assurance

S
MAINTAINABILITY
ENGINEERING
Maintainability Analysis, Continued
Definitions

CDRL = Contract Data Requirements List
PDR = Preliminary Design Review
CDR = Critical Design Review
FSD = Full Scale Development
MTTR = Mean Time To Repair
Mmax(φ) = Maximum Time To Repair for the φ percentile
BIT = Built - In - Test

Responsibilitie
s

It is the responsibility of the maintainability engineer assigned to the particular
project to do the Analysis. The Analysis should be reviewed and approved by
the Maintainability Group Leader and the Project Manager.

Procedure

The maintainability analysis integrates data from contractor’s studies with
engineering reports and information which is available from the CA into a
detailed design approach. Outputs from Tasks 201 and 202 of MIL-STD2165, if called out should form the basis for testability and diagnostic
analysis.
The elements specified in the Statement Of Work and to be considered in the
maintainability analysis should include:
•

Mean Time To Repair (MTTR) and Maximum Time To Repair for the
φ percentile (Mmax(φ)) for all levels (organizational, intermediate, depot)
of maintenance. MIL-HDBK-472 Notice 1, Procedure V is an easy
method for this task. If repair times cannot be synthesized from data
books, time and motion studies should be performed and data
statistically corrected to obtain times for analysis.

•

Maintenance man-hours and maintenance time expended/maintenance
task/flight hour/operating hour for all appropriate levels of maintenance

•

False Alarm Rates (FAR), Cannot Duplicate (CND) Rates, Retest OK
(RTOK) Rates associated with all levels of maintenance

http://www.linkedin.com/in/hilaireperera
Hilaire Ananda Perera PEng
Long Term Quality Assurance
MAINTAINABILITY
ENGINEERING
Maintainability Analysis, Continued
Procedure
(Continued)

• Proportion of faults detectable (all levels of maintenance, including

system/equipment/unit built-in detection, and external fault detection
subsystems)
• Level(s) of isolation or ambiguity (for example, does the built-in-test or

external test system or tester identify N possible units or assemblies etc.,
only one of which is failed) for the system, equipment, unit, assembly,
subassembly, etc., for each level of maintenance.
• Identification of the required mix of automatic, semiautomatic, built-in and

manual test capability, plus the maintenance aids and manual diagnostic
procedures required at all levels of repair and their associated software and
technical costs, skill levels required and manpower requirements, as well as
acquisition costs if available.
• Levels of repair associated with each equipment design and each test system

alternative as derived from the LSA.
• Development of unique external test systems and testers versus use of

existing units (stock listed or commercial)
• Producibility considerations relating to the realization of each test system

alternative.
• Determination of system/subsystem/equipment parameters that are

monitored and not monitored by BIT or other diagnostic/test systems.
•

Impact of scheduled and preventive maintenance workload:
• Mean time between scheduled and preventive maintenance at each

required level of maintenance
• Mean preventive maintenance time

http://www.linkedin.com/in/hilaireperera
Hilaire Ananda Perera PEng
Long Term Quality Assurance
MAINTAINABILITY
ENGINEERING
Maintainability Analysis, Continued
Procedure
(Continued)

•

Maintainability mathematical models, life cycle cost models, and
acquisition cost estimates if specified in the Statement Of Work should be
developed from the inputs and considerations described above to:
• Show the impacts on cost, maintainability and on system readiness

parameters of the germane maintainability elements
•

Allocate quantitative maintainability requirements to all significant item
levels of the system/subsystem/equipment. (details are in Task 202 of
MIL-STD-470B)

• Develop the most cost effective maintainability design and test system

configuration which meets support and personnel constraints as well as
system readiness and mission performance objectives
• Performance Design Trade-offs.

NOTE: This task has significant
possibilities for overlap with LSA efforts, and should therefore be
coordinated closely with the LSA community and LSA Statement Of Work,
to ensure consistency and prevent duplication.

• Trade-offs between maintainability design alternatives and equipment

design parameters should be made to provide an economical design
which best satisfies systems or equipment requirements
• Trade-offs involving impacts on maintainability attributed to changes in

areas such as packaging, fault detection and isolation portions of the
design or to external test equipment or testers should be incorporated in
status reports submitted
.

http://www.linkedin.com/in/hilaireperera
Hilaire Ananda Perera PEng
Long Term Quality Assurance
MAINTAINABILITY
ENGINEERING
Maintainability Analysis, Continued

Associated
Documents

Customer provided Statement Of Work and the Equipment Specifications
ISO 9001 Level II Document: Design Control - The Product Assurance
Process
MIL-STD-470: Maintainability Program For Systems And Equipment
MIL-HDBK-472: Maintainability Prediction
MIL-STD-2165: Testability Program For Electronic Systems And Equipment
MIL-STD-721: Definitions Of Terms For Reliability And Maintainability

http://www.linkedin.com/in/hilaireperera
Hilaire Ananda Perera PEng
Long Term Quality Assurance

More Related Content

What's hot

Maintenance module1 ppt number 3
Maintenance module1 ppt number 3Maintenance module1 ppt number 3
Maintenance module1 ppt number 3Dhanesh S
 
Solid modeling
Solid modelingSolid modeling
Solid modelingDhruv Shah
 
Reliability engineering chapter-2 reliability of systems
Reliability engineering chapter-2 reliability of systemsReliability engineering chapter-2 reliability of systems
Reliability engineering chapter-2 reliability of systemsCharlton Inao
 
Introduction to maintenance
Introduction to maintenanceIntroduction to maintenance
Introduction to maintenanceHashim V tkmce
 
7 TRADITIONAL TOOLS OF QUALITY
7 TRADITIONAL TOOLS OF QUALITY7 TRADITIONAL TOOLS OF QUALITY
7 TRADITIONAL TOOLS OF QUALITYJustin Dhiraviam
 
7 QC and New 7 QC Comparison & Applicability
7 QC and New 7 QC Comparison & Applicability7 QC and New 7 QC Comparison & Applicability
7 QC and New 7 QC Comparison & Applicabilityaksahu4u
 
Image sampling and quantization
Image sampling and quantizationImage sampling and quantization
Image sampling and quantizationBCET, Balasore
 
Real time operating-systems
Real time operating-systemsReal time operating-systems
Real time operating-systemskasi963
 
COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)KRUNAL RAVAL
 
Maintenance strategy
Maintenance strategyMaintenance strategy
Maintenance strategygumma alsgier
 
NG BB 06 Project Charter
NG BB 06 Project CharterNG BB 06 Project Charter
NG BB 06 Project CharterLeanleaders.org
 
Reliability engineering chapter-1csi
Reliability engineering chapter-1csiReliability engineering chapter-1csi
Reliability engineering chapter-1csiCharlton Inao
 
Computer aided process planning
Computer aided process planningComputer aided process planning
Computer aided process planningjashid41
 

What's hot (20)

Maintenance module1 ppt number 3
Maintenance module1 ppt number 3Maintenance module1 ppt number 3
Maintenance module1 ppt number 3
 
Solid modeling
Solid modelingSolid modeling
Solid modeling
 
Reliability engineering chapter-2 reliability of systems
Reliability engineering chapter-2 reliability of systemsReliability engineering chapter-2 reliability of systems
Reliability engineering chapter-2 reliability of systems
 
Introduction to maintenance
Introduction to maintenanceIntroduction to maintenance
Introduction to maintenance
 
7 TRADITIONAL TOOLS OF QUALITY
7 TRADITIONAL TOOLS OF QUALITY7 TRADITIONAL TOOLS OF QUALITY
7 TRADITIONAL TOOLS OF QUALITY
 
Capp
CappCapp
Capp
 
Maintenance engineering- Unit- 3
Maintenance engineering- Unit- 3Maintenance engineering- Unit- 3
Maintenance engineering- Unit- 3
 
Maintenance strategies
Maintenance strategiesMaintenance strategies
Maintenance strategies
 
7 QC and New 7 QC Comparison & Applicability
7 QC and New 7 QC Comparison & Applicability7 QC and New 7 QC Comparison & Applicability
7 QC and New 7 QC Comparison & Applicability
 
Image sampling and quantization
Image sampling and quantizationImage sampling and quantization
Image sampling and quantization
 
Unit vi (1)
Unit vi (1)Unit vi (1)
Unit vi (1)
 
Plant maintenance
Plant maintenancePlant maintenance
Plant maintenance
 
Real time operating-systems
Real time operating-systemsReal time operating-systems
Real time operating-systems
 
COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)
 
Maintenance strategy
Maintenance strategyMaintenance strategy
Maintenance strategy
 
NG BB 06 Project Charter
NG BB 06 Project CharterNG BB 06 Project Charter
NG BB 06 Project Charter
 
Pic full note
Pic full notePic full note
Pic full note
 
Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)
 
Reliability engineering chapter-1csi
Reliability engineering chapter-1csiReliability engineering chapter-1csi
Reliability engineering chapter-1csi
 
Computer aided process planning
Computer aided process planningComputer aided process planning
Computer aided process planning
 

Viewers also liked

Reliability engineering chapter-4 fmea
Reliability engineering chapter-4 fmeaReliability engineering chapter-4 fmea
Reliability engineering chapter-4 fmeaCharlton Inao
 
Maintainability SFJS Sept 4 2014
Maintainability SFJS Sept 4 2014 Maintainability SFJS Sept 4 2014
Maintainability SFJS Sept 4 2014 Jarrod Overson
 
Reducing Product Development Risk with Reliability Engineering Methods
Reducing Product Development Risk with Reliability Engineering MethodsReducing Product Development Risk with Reliability Engineering Methods
Reducing Product Development Risk with Reliability Engineering MethodsWilde Analysis Ltd.
 
Reliability Maintenance Engineering 2 - 3 Measuring Maintainability
Reliability Maintenance Engineering 2 - 3 Measuring MaintainabilityReliability Maintenance Engineering 2 - 3 Measuring Maintainability
Reliability Maintenance Engineering 2 - 3 Measuring MaintainabilityAccendo Reliability
 
Interpretive structural modeling
Interpretive structural modelingInterpretive structural modeling
Interpretive structural modelingUjjwal 'Shanu'
 
Maintainance of farm machinery
Maintainance of farm machineryMaintainance of farm machinery
Maintainance of farm machineryRione Drevale
 
Leontief input output models.ppt final
Leontief input output models.ppt finalLeontief input output models.ppt final
Leontief input output models.ppt finalKinnar Majithia
 
basic concepts of reliability
basic concepts of reliabilitybasic concepts of reliability
basic concepts of reliabilitydennis gookyi
 
System engineering
System engineeringSystem engineering
System engineeringSlideshare
 
Reverse engineering
Reverse engineeringReverse engineering
Reverse engineeringananya0122
 
Introduction to Simulation
Introduction to SimulationIntroduction to Simulation
Introduction to Simulationchimco.net
 

Viewers also liked (13)

Reliability engineering chapter-4 fmea
Reliability engineering chapter-4 fmeaReliability engineering chapter-4 fmea
Reliability engineering chapter-4 fmea
 
Reliability engineering ppt-Internship
Reliability engineering ppt-InternshipReliability engineering ppt-Internship
Reliability engineering ppt-Internship
 
Maintainability SFJS Sept 4 2014
Maintainability SFJS Sept 4 2014 Maintainability SFJS Sept 4 2014
Maintainability SFJS Sept 4 2014
 
Reducing Product Development Risk with Reliability Engineering Methods
Reducing Product Development Risk with Reliability Engineering MethodsReducing Product Development Risk with Reliability Engineering Methods
Reducing Product Development Risk with Reliability Engineering Methods
 
Reliability Maintenance Engineering 2 - 3 Measuring Maintainability
Reliability Maintenance Engineering 2 - 3 Measuring MaintainabilityReliability Maintenance Engineering 2 - 3 Measuring Maintainability
Reliability Maintenance Engineering 2 - 3 Measuring Maintainability
 
Interpretive structural modeling
Interpretive structural modelingInterpretive structural modeling
Interpretive structural modeling
 
Maintainance of farm machinery
Maintainance of farm machineryMaintainance of farm machinery
Maintainance of farm machinery
 
Leontief input output models.ppt final
Leontief input output models.ppt finalLeontief input output models.ppt final
Leontief input output models.ppt final
 
basic concepts of reliability
basic concepts of reliabilitybasic concepts of reliability
basic concepts of reliability
 
System engineering
System engineeringSystem engineering
System engineering
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
Reverse engineering
Reverse engineeringReverse engineering
Reverse engineering
 
Introduction to Simulation
Introduction to SimulationIntroduction to Simulation
Introduction to Simulation
 

Similar to Maintainability engineering

Resume_Instrumentation Engineer_7.5 year experience
Resume_Instrumentation Engineer_7.5 year experienceResume_Instrumentation Engineer_7.5 year experience
Resume_Instrumentation Engineer_7.5 year experienceDHRUVA MISHRA
 
Ch5 software imprementation1.0
Ch5 software imprementation1.0Ch5 software imprementation1.0
Ch5 software imprementation1.0Kittitouch Suteeca
 
Using Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A SimplifiedUsing Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A Simplifiedcbb010
 
Phase gate review development model august 8 2017 - dave litwiller
Phase gate review development model   august 8 2017 - dave litwillerPhase gate review development model   august 8 2017 - dave litwiller
Phase gate review development model august 8 2017 - dave litwillerDave Litwiller
 
Analytical Instrument Qualification - USP chapter 1058 revision
Analytical Instrument Qualification - USP chapter 1058 revisionAnalytical Instrument Qualification - USP chapter 1058 revision
Analytical Instrument Qualification - USP chapter 1058 revisionpi
 
commissioning.pdf
commissioning.pdfcommissioning.pdf
commissioning.pdfharis348605
 
software configuration management ppt
 software configuration management  ppt software configuration management  ppt
software configuration management pptYeshiwas Getachew
 
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...Verhaert Masters in Innovation
 
Applications Engineer Electrical Sr Specialist
Applications Engineer   Electrical Sr SpecialistApplications Engineer   Electrical Sr Specialist
Applications Engineer Electrical Sr Specialistmbarulic
 
Software testing and introduction to quality
Software testing and introduction to qualitySoftware testing and introduction to quality
Software testing and introduction to qualityDhanashriAmbre
 
Quality Management and Quality Standard
Quality Management and Quality StandardQuality Management and Quality Standard
Quality Management and Quality StandardMurageppa-QA
 
Chapter 4 - Performance Testing Tasks
Chapter 4 - Performance Testing TasksChapter 4 - Performance Testing Tasks
Chapter 4 - Performance Testing TasksNeeraj Kumar Singh
 
Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects Apoorva Bauskar
 
1 - Introduction to Computerized Systems Validation - for review.pptx
1 - Introduction to Computerized Systems Validation - for review.pptx1 - Introduction to Computerized Systems Validation - for review.pptx
1 - Introduction to Computerized Systems Validation - for review.pptxpatemalabanan
 
Acquisition Cost Estimating
Acquisition Cost EstimatingAcquisition Cost Estimating
Acquisition Cost Estimatingjrunderwood
 

Similar to Maintainability engineering (20)

Ray-Goodfellow.ppt
Ray-Goodfellow.pptRay-Goodfellow.ppt
Ray-Goodfellow.ppt
 
Resume_Instrumentation Engineer_7.5 year experience
Resume_Instrumentation Engineer_7.5 year experienceResume_Instrumentation Engineer_7.5 year experience
Resume_Instrumentation Engineer_7.5 year experience
 
Ch5 software imprementation1.0
Ch5 software imprementation1.0Ch5 software imprementation1.0
Ch5 software imprementation1.0
 
Using Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A SimplifiedUsing Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A Simplified
 
Phase gate review development model august 8 2017 - dave litwiller
Phase gate review development model   august 8 2017 - dave litwillerPhase gate review development model   august 8 2017 - dave litwiller
Phase gate review development model august 8 2017 - dave litwiller
 
Control System - execution plan
Control System - execution planControl System - execution plan
Control System - execution plan
 
Analytical Instrument Qualification - USP chapter 1058 revision
Analytical Instrument Qualification - USP chapter 1058 revisionAnalytical Instrument Qualification - USP chapter 1058 revision
Analytical Instrument Qualification - USP chapter 1058 revision
 
commissioning.pdf
commissioning.pdfcommissioning.pdf
commissioning.pdf
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
software configuration management ppt
 software configuration management  ppt software configuration management  ppt
software configuration management ppt
 
Production checklist for biotech startups
Production checklist for biotech startupsProduction checklist for biotech startups
Production checklist for biotech startups
 
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...Innovation day 2013   2.5 joris vanderschrick (verhaert) - embedded system de...
Innovation day 2013 2.5 joris vanderschrick (verhaert) - embedded system de...
 
Applications Engineer Electrical Sr Specialist
Applications Engineer   Electrical Sr SpecialistApplications Engineer   Electrical Sr Specialist
Applications Engineer Electrical Sr Specialist
 
Software testing and introduction to quality
Software testing and introduction to qualitySoftware testing and introduction to quality
Software testing and introduction to quality
 
Quality Management and Quality Standard
Quality Management and Quality StandardQuality Management and Quality Standard
Quality Management and Quality Standard
 
Chapter 4 - Performance Testing Tasks
Chapter 4 - Performance Testing TasksChapter 4 - Performance Testing Tasks
Chapter 4 - Performance Testing Tasks
 
Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects Facility Qualification & Consideration of Validation Aspects
Facility Qualification & Consideration of Validation Aspects
 
1 - Introduction to Computerized Systems Validation - for review.pptx
1 - Introduction to Computerized Systems Validation - for review.pptx1 - Introduction to Computerized Systems Validation - for review.pptx
1 - Introduction to Computerized Systems Validation - for review.pptx
 
Acquisition Cost Estimating
Acquisition Cost EstimatingAcquisition Cost Estimating
Acquisition Cost Estimating
 
CV D. Maimbolwa
CV D. MaimbolwaCV D. Maimbolwa
CV D. Maimbolwa
 

More from Hilaire (Ananda) Perera P.Eng.

ESS and HASS: Concerns with the Practices and Standards
ESS and HASS:  Concerns with the Practices and StandardsESS and HASS:  Concerns with the Practices and Standards
ESS and HASS: Concerns with the Practices and StandardsHilaire (Ananda) Perera P.Eng.
 
CALCE Test Services and Failure Analysis (TSFA) Laboratory
CALCE Test Services and Failure Analysis (TSFA) LaboratoryCALCE Test Services and Failure Analysis (TSFA) Laboratory
CALCE Test Services and Failure Analysis (TSFA) LaboratoryHilaire (Ananda) Perera P.Eng.
 
IEEE 1633 Recommended Practice on Software Reliability
IEEE 1633 Recommended Practice on Software ReliabilityIEEE 1633 Recommended Practice on Software Reliability
IEEE 1633 Recommended Practice on Software ReliabilityHilaire (Ananda) Perera P.Eng.
 
Reliability Prediction Procedure for Mechanical Components
Reliability Prediction Procedure for Mechanical ComponentsReliability Prediction Procedure for Mechanical Components
Reliability Prediction Procedure for Mechanical ComponentsHilaire (Ananda) Perera P.Eng.
 
Early Life Failure Rate Calculation Procedure for Semiconductor Components
Early Life Failure Rate Calculation Procedure for Semiconductor ComponentsEarly Life Failure Rate Calculation Procedure for Semiconductor Components
Early Life Failure Rate Calculation Procedure for Semiconductor ComponentsHilaire (Ananda) Perera P.Eng.
 
Basic Design Considerations for Surface Mount Technology
Basic Design Considerations for Surface Mount TechnologyBasic Design Considerations for Surface Mount Technology
Basic Design Considerations for Surface Mount TechnologyHilaire (Ananda) Perera P.Eng.
 

More from Hilaire (Ananda) Perera P.Eng. (20)

ESS and HASS: Concerns with the Practices and Standards
ESS and HASS:  Concerns with the Practices and StandardsESS and HASS:  Concerns with the Practices and Standards
ESS and HASS: Concerns with the Practices and Standards
 
CALCE Test Services and Failure Analysis (TSFA) Laboratory
CALCE Test Services and Failure Analysis (TSFA) LaboratoryCALCE Test Services and Failure Analysis (TSFA) Laboratory
CALCE Test Services and Failure Analysis (TSFA) Laboratory
 
IEEE 1633 Recommended Practice on Software Reliability
IEEE 1633 Recommended Practice on Software ReliabilityIEEE 1633 Recommended Practice on Software Reliability
IEEE 1633 Recommended Practice on Software Reliability
 
BIOMASS Based Power ( Electrical & Thermal )
BIOMASS Based Power ( Electrical & Thermal )BIOMASS Based Power ( Electrical & Thermal )
BIOMASS Based Power ( Electrical & Thermal )
 
Reliability Growth Testing (RGT) Plan
Reliability Growth Testing (RGT) Plan Reliability Growth Testing (RGT) Plan
Reliability Growth Testing (RGT) Plan
 
Statistical Confidence Level
Statistical Confidence LevelStatistical Confidence Level
Statistical Confidence Level
 
Reliability if "m" of "n" Must be Working
Reliability if "m" of "n" Must be WorkingReliability if "m" of "n" Must be Working
Reliability if "m" of "n" Must be Working
 
Outgoing Reliability Assurance of 'End-Units'
Outgoing Reliability Assurance of 'End-Units'Outgoing Reliability Assurance of 'End-Units'
Outgoing Reliability Assurance of 'End-Units'
 
Transient Suppressors
Transient SuppressorsTransient Suppressors
Transient Suppressors
 
Reliability Prediction Procedure for Mechanical Components
Reliability Prediction Procedure for Mechanical ComponentsReliability Prediction Procedure for Mechanical Components
Reliability Prediction Procedure for Mechanical Components
 
Software Reliability
Software ReliabilitySoftware Reliability
Software Reliability
 
Virtual Qualification
Virtual QualificationVirtual Qualification
Virtual Qualification
 
Availability
AvailabilityAvailability
Availability
 
Testability
TestabilityTestability
Testability
 
Accelerated Stress Testing
Accelerated Stress TestingAccelerated Stress Testing
Accelerated Stress Testing
 
Early Life Failure Rate Calculation Procedure for Semiconductor Components
Early Life Failure Rate Calculation Procedure for Semiconductor ComponentsEarly Life Failure Rate Calculation Procedure for Semiconductor Components
Early Life Failure Rate Calculation Procedure for Semiconductor Components
 
Use of Failure Mechanisms enhance FMEA and FMECA
Use of Failure Mechanisms enhance FMEA and FMECAUse of Failure Mechanisms enhance FMEA and FMECA
Use of Failure Mechanisms enhance FMEA and FMECA
 
Basic Design Considerations for Surface Mount Technology
Basic Design Considerations for Surface Mount TechnologyBasic Design Considerations for Surface Mount Technology
Basic Design Considerations for Surface Mount Technology
 
Thermal cycling screen development
Thermal cycling screen developmentThermal cycling screen development
Thermal cycling screen development
 
Design For Reliability
Design For ReliabilityDesign For Reliability
Design For Reliability
 

Recently uploaded

Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operationalssuser3e220a
 
Narcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfNarcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfPrerana Jadhav
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxSayali Powar
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxVanesaIglesias10
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Seán Kennedy
 
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...Nguyen Thanh Tu Collection
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptxMan or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptxDhatriParmar
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmStan Meyer
 
week 1 cookery 8 fourth - quarter .pptx
week 1 cookery 8  fourth  -  quarter .pptxweek 1 cookery 8  fourth  -  quarter .pptx
week 1 cookery 8 fourth - quarter .pptxJonalynLegaspi2
 
MS4 level being good citizen -imperative- (1) (1).pdf
MS4 level   being good citizen -imperative- (1) (1).pdfMS4 level   being good citizen -imperative- (1) (1).pdf
MS4 level being good citizen -imperative- (1) (1).pdfMr Bounab Samir
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQuiz Club NITW
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research DiscourseAnita GoswamiGiri
 
How to Fix XML SyntaxError in Odoo the 17
How to Fix XML SyntaxError in Odoo the 17How to Fix XML SyntaxError in Odoo the 17
How to Fix XML SyntaxError in Odoo the 17Celine George
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 

Recently uploaded (20)

Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operational
 
Narcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfNarcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdf
 
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptxINCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptx
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...
31 ĐỀ THI THỬ VÀO LỚP 10 - TIẾNG ANH - FORM MỚI 2025 - 40 CÂU HỎI - BÙI VĂN V...
 
prashanth updated resume 2024 for Teaching Profession
prashanth updated resume 2024 for Teaching Professionprashanth updated resume 2024 for Teaching Profession
prashanth updated resume 2024 for Teaching Profession
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptxMan or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and Film
 
week 1 cookery 8 fourth - quarter .pptx
week 1 cookery 8  fourth  -  quarter .pptxweek 1 cookery 8  fourth  -  quarter .pptx
week 1 cookery 8 fourth - quarter .pptx
 
MS4 level being good citizen -imperative- (1) (1).pdf
MS4 level   being good citizen -imperative- (1) (1).pdfMS4 level   being good citizen -imperative- (1) (1).pdf
MS4 level being good citizen -imperative- (1) (1).pdf
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research Discourse
 
How to Fix XML SyntaxError in Odoo the 17
How to Fix XML SyntaxError in Odoo the 17How to Fix XML SyntaxError in Odoo the 17
How to Fix XML SyntaxError in Odoo the 17
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
Paradigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTAParadigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTA
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 

Maintainability engineering

  • 1. MAINTAINABILITY ENGINEERING Maintainability Analysis Purpose The purpose of this task is to translate data from contractor’s studies, engineering reports and information which is available from the Contracting Activity (CA) into a detailed design approach and to provide inputs to the detailed maintenance and support plan, which is part of the Logistics Support Analysis (LSA). The four main goals are: • To establish design criteria that will provide the desired system features • To allow for design decisions to be made through the evaluation of alternatives and through the use of trade-off studies • To contribute toward establishing maintenance, repair and servicing policies and support maintainability achievement • To verify that the design complies with maintainability design requirements Scope The following Table reproduced from MIL-STD-470B (Maintainability Program For Systems And Equipment) contains identification to show when the Maintainability Analysis (Task 205) is used in different Program Phases. In the Contract Data Requirements List (CDRL), the Task 205 is referred as DI-R-7109 and the recommended delivery date to the customer is 30 days prior to PDR & CDR TASK TITLE TASK TYPE PROGRAM PHASE OSD Concept 205 Maintainability Analysis ENG Validatio n FSD Production S(3) G(3) G(1) C(1) ENG - Maintainability Engineering OSD - Operational System Developments (Modifications) G - Generally Applicable S - Selectively Applicable C - Generally Applicable to design changes only (1) - Requires considerable interpretation of intent to be cost effective (3) - Appropriate for those task elements suitable to definition during phase http://www.linkedin.com/in/hilaireperera Hilaire Ananda Perera PEng Long Term Quality Assurance S
  • 2. MAINTAINABILITY ENGINEERING Maintainability Analysis, Continued Definitions CDRL = Contract Data Requirements List PDR = Preliminary Design Review CDR = Critical Design Review FSD = Full Scale Development MTTR = Mean Time To Repair Mmax(φ) = Maximum Time To Repair for the φ percentile BIT = Built - In - Test Responsibilitie s It is the responsibility of the maintainability engineer assigned to the particular project to do the Analysis. The Analysis should be reviewed and approved by the Maintainability Group Leader and the Project Manager. Procedure The maintainability analysis integrates data from contractor’s studies with engineering reports and information which is available from the CA into a detailed design approach. Outputs from Tasks 201 and 202 of MIL-STD2165, if called out should form the basis for testability and diagnostic analysis. The elements specified in the Statement Of Work and to be considered in the maintainability analysis should include: • Mean Time To Repair (MTTR) and Maximum Time To Repair for the φ percentile (Mmax(φ)) for all levels (organizational, intermediate, depot) of maintenance. MIL-HDBK-472 Notice 1, Procedure V is an easy method for this task. If repair times cannot be synthesized from data books, time and motion studies should be performed and data statistically corrected to obtain times for analysis. • Maintenance man-hours and maintenance time expended/maintenance task/flight hour/operating hour for all appropriate levels of maintenance • False Alarm Rates (FAR), Cannot Duplicate (CND) Rates, Retest OK (RTOK) Rates associated with all levels of maintenance http://www.linkedin.com/in/hilaireperera Hilaire Ananda Perera PEng Long Term Quality Assurance
  • 3. MAINTAINABILITY ENGINEERING Maintainability Analysis, Continued Procedure (Continued) • Proportion of faults detectable (all levels of maintenance, including system/equipment/unit built-in detection, and external fault detection subsystems) • Level(s) of isolation or ambiguity (for example, does the built-in-test or external test system or tester identify N possible units or assemblies etc., only one of which is failed) for the system, equipment, unit, assembly, subassembly, etc., for each level of maintenance. • Identification of the required mix of automatic, semiautomatic, built-in and manual test capability, plus the maintenance aids and manual diagnostic procedures required at all levels of repair and their associated software and technical costs, skill levels required and manpower requirements, as well as acquisition costs if available. • Levels of repair associated with each equipment design and each test system alternative as derived from the LSA. • Development of unique external test systems and testers versus use of existing units (stock listed or commercial) • Producibility considerations relating to the realization of each test system alternative. • Determination of system/subsystem/equipment parameters that are monitored and not monitored by BIT or other diagnostic/test systems. • Impact of scheduled and preventive maintenance workload: • Mean time between scheduled and preventive maintenance at each required level of maintenance • Mean preventive maintenance time http://www.linkedin.com/in/hilaireperera Hilaire Ananda Perera PEng Long Term Quality Assurance
  • 4. MAINTAINABILITY ENGINEERING Maintainability Analysis, Continued Procedure (Continued) • Maintainability mathematical models, life cycle cost models, and acquisition cost estimates if specified in the Statement Of Work should be developed from the inputs and considerations described above to: • Show the impacts on cost, maintainability and on system readiness parameters of the germane maintainability elements • Allocate quantitative maintainability requirements to all significant item levels of the system/subsystem/equipment. (details are in Task 202 of MIL-STD-470B) • Develop the most cost effective maintainability design and test system configuration which meets support and personnel constraints as well as system readiness and mission performance objectives • Performance Design Trade-offs. NOTE: This task has significant possibilities for overlap with LSA efforts, and should therefore be coordinated closely with the LSA community and LSA Statement Of Work, to ensure consistency and prevent duplication. • Trade-offs between maintainability design alternatives and equipment design parameters should be made to provide an economical design which best satisfies systems or equipment requirements • Trade-offs involving impacts on maintainability attributed to changes in areas such as packaging, fault detection and isolation portions of the design or to external test equipment or testers should be incorporated in status reports submitted . http://www.linkedin.com/in/hilaireperera Hilaire Ananda Perera PEng Long Term Quality Assurance
  • 5. MAINTAINABILITY ENGINEERING Maintainability Analysis, Continued Associated Documents Customer provided Statement Of Work and the Equipment Specifications ISO 9001 Level II Document: Design Control - The Product Assurance Process MIL-STD-470: Maintainability Program For Systems And Equipment MIL-HDBK-472: Maintainability Prediction MIL-STD-2165: Testability Program For Electronic Systems And Equipment MIL-STD-721: Definitions Of Terms For Reliability And Maintainability http://www.linkedin.com/in/hilaireperera Hilaire Ananda Perera PEng Long Term Quality Assurance