Your SlideShare is downloading. ×
Alexandre lopes braskem portuguese
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×

Introducing the official SlideShare app

Stunning, full-screen experience for iPhone and Android

Text the download link to your phone

Standard text messaging rates apply

Alexandre lopes braskem portuguese

407
views

Published on

General Assembly Presentation from Braskem

General Assembly Presentation from Braskem

Published in: Technology

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
407
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
10
Comments
0
Likes
0
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide
  • Possible faults detected now include power conditioner faults, like under voltage conditions and short circuit faults. Individual device and segment communication statistics provide additional diagnostic tools to isolate most installation issues. More advanced diagnostics of a segment can be performed as needed using an external tool connected to the segment via the terminal block.
  • Transcript

    • 1. Manutenção e Operação em FOUNDATION Fieldbus Alexandre Pereira Lopes1 March 2012
    • 2. Braskem - A caminho da liderança global da química sustentavelCom atuação no setor químico e petroquímico, aBraskem se destaca no cenário global como a maiorprodutora de resinas termoplásticas das Américas. • Polietileno (PE) • Polipropileno (PP) • Policloreto de Vinila (PVC) • Insumos químicos básicos como eteno, propeno, butadieno, benzeno, tolueno, cloro, soda e solventes, entre outors.A Braskem possui um dos portfólios mais completos domercado, ao incluir também produtos diferenciados apartir de matérias primas renováveis.2 March 2012
    • 3. Braskem em Números Números de 2010 mostram a atuação e a dimensão da empresa, uma das maiores do mundo em seu setor.3 March 2012
    • 4. Braskem na Cadeia Petroquímica INTEGRAÇÃO COMPETITIVA NAFTA CONDENSADO VALOR ADICIONADO GAS COMPETITIVIDADE EXTRAÇÃO 1° Geração 2° Geração 3° GeraçãoMatérias Primas Petroquímicos Resinas Transformadores Básicos Termoplásticas de Plásticos4 March 2012
    • 5. A Braskem e a tecnologia FFA Braskem possui várias plantas no Brasil com aplicações FF, incluindo unidades em:  São Paulo (ABC: Mauá/Santo André);  Paulínia, SP  Triunfo, RS  Salvador, BA (Camaçari)  Alagoas5 March 2012
    • 6. Exemplo: Composição de Tecnologias em Planta do ABC Instrumentos Inteligentes 1% 22 % Fieldbus 77 % Hart WirelessHart Total: > 1900 instrumentos6 March 2012
    • 7. Exemplo: Tipos de Instrumentos na Unidade Intermediários de Planta no ABC (Total de 263 instr.)Vendor Device NameFisher Controls Fisher DVC6000f - SC rev 1Invensys Process Systems 240FFMagnetrol Model 705 3.xPepperl + Fuchs Temperature MultiplexerRosemount Inc. 3051 Fieldbus Pressure Transmitter 3144 Fieldbus Temperature Transmitter 5300 Guided Wave Radar Level and Interface Transmitter 5600 TankRadar PRO Level Transmitter 752 Fieldbus Remote Display 848 Fieldbus Temperature DeviceRosemount Inc. TotalSMAR Advanced Positioner Transmitter Pressure TransmitterVEGA Grieshaber KG VEGA PULSYokogawa Electric EJA100A EJX ROTAMASS YTA320 YVP Valve Positioner7 March 2012
    • 8. Razão para a adoção da Tecnologia FF• Apesar das significativas possibilidades de economias de instalação e comissionamento, os principais benefícios da adoção da tecnologia Fieldbus Foundation podem ser vistos durante o período de operação da planta. Benefícios para a Manutenção e Operação8 March 2012
    • 9. Algumas Vantagens do FF• Possibilidade de redução de custos com fiação e instalação;• Instrumentos multivariaveis;• Simplificação da Instalação e de seu projeto (menos desenhos);• Variáveis em unidades de engenharia diretamente (sem conversão A/D, melhor precisão);• Controle no Campo (melhor MTBF, menor variabilidade);• Diagnósticos avançados;• Acesso remoto a calibração e diagnósticos do instrumento;• Manutenção otimizada.9 March 2012
    • 10. Algumas Lições Aprendidas com Projetos FF• Atenção especial deve ser dada aos requerimentos particulares do fieldbus e seus benefícios para a Planta:  Treinamento para todos os envolvidos;  A instalação física é muito importante;  Verificação/certificação das redes é necessária.  Uso de componentes aprovados;  Distribuição de instrumentos em redes;  Testes e verificações (integração, TAF, etc);  Especificação de diagnósticos de dispositivos e ferramentas de manutenção;Um bom planejamento para Gerenciamento de Ativosé fundamental para se alcançar os benefícios10 March 2012
    • 11. Outras LiçõesSegurança Intrínseca:• Tivemos problemas ao levar redes de baixa potência ao campo;• Hoje o padrão na Braskem é a utilização do conceito “Power Trunk” • Tronco com segurança aumentada • Barreiras de segurança no campo (caixas de junção)11 March 2012
    • 12. Solução Power Trunk Solução Típica: Solução Inovadora: Cartão FF com condicionador embutido - 450 mA por rede - Completamente redundante12 March 2012
    • 13. Outras LiçõesDiagnósticos de Rede:• Diagnósticos de rede são muito importantes para o comissionamento e manutenção;• Necessidade de Integração ao sistema de Gerenciamento de Ativos;13 March 2012
    • 14. Soluções para Diagnósticos de Rede• Solução Típica: OPC Ctlr, H1 24 Vdc Condicionador• Solução Inovadora: Condicionador integrado ao cartão H1 com diagnósticos de rede14 March 2012
    • 15. A importância do Sistema de Gerenciamento de Ativos
    • 16. Um instrumento FF pode possuir centenas de informações adicionais Resource Analog In PID ST_REV MEMORY_SIZE ST_REV FIELD_VAL ST_REV GAIN ALARM_SUM TAG_DESC NV_CYCLE_T TAG_DESC UPDATE_EVT TAG_DESC RESET ACK_OPTION STRATEGY FREE_SPACE STRATEGY BLOCK_ALM STRATEGY BAL_TIME ALARM_HYS ALERT_KEY FREE_TIME ALERT_KEY ALARM_SUM ALERT_KEY RATE HI_HI_PRI MODE_BLK SHED_RCAS MODE_BLK ACK_OPTION MODE_BLK BKCAL_IN HI_HI_LIM BLOCK_ERR SHED_ROUT BLOCK_ERR ALARM_HYS BLOCK_ERR OUT_HI_LIM HI_PRI RS_STATE FAIL_SAFE PV HI_HI_PRI PV OUT_LO_LIM HI_LIM TEST_RW SET_FSAFE OUT HI_HI_LIM SP BKCAL_HYS LO_PRI DD_RESOURCE CLR_FSAFE SIMULATE HI_PRI OUT BKCAL_OUT LO_LIM MANUFAC_ID MAX_NOTIFY XD_SCALE HI_LIM PV_SCALE RCAS_IN LO_LO_PRI DEV_TYPE LIM_NOTIFY OUT_SCALE LO_PRI OUT_SCALE ROUT_IN LO_LO_LIM DEV_REV CONFIRM_TIME GRANT_DENY LO_LIM GRANT_DENY SHED_OPT DV_HI_PRI DD_REV WRITE_LOCK IO_OPTS LO_LO_PRI CONTROL_OPTS RCAS_OUT DV_HI_LIM GRANT_DENY UPDATE_EVT STATUS_OPTS LO_LO_LIM STATUS_OPTS ROUT_OUT DV_LO_PRI HARD_TYPES BLOCK_ALM CHANNEL HI_HI_ALM IN TRK_SCALE DV_LO_LIM RESTART ALARM_SUM L_TYPE HI_ALM PV_FTIME TRK_IN_D HI_HI_ALM FEATURES ACK_OPTION LOW_CUT LO_ALM BYPASS TRK_VAL HI_ALM FEATURE_SEL WRITE_PRI PV_FTIME LO_LO_ALM CAS_IN FF_VAL LO_ALM CYCLE_TYPE WRITE_ALM SP_RATE_DN FF_SCALE LO_LO_ALM CYCLE_SEL SP_RATE_UP FF_GAIN DV_HI_ALM MIN_CYCLE_T SP_HI_LIM UPDATE_EVT DV_LO_ALM SP_LO_LIM BLOCK_ALMEssas informações precisam estar organizadas para ousuário. Dai a importancia do Gerenciamento de Ativos! 16 March 2012
    • 17. Considerações sobre Gerenciamento de AtivosUm dos grandes benefícios do FF é a grande disponibilidade de informações adicionais dos instrumentos, com destaques para diagnósticos. Assim:  O planejamento da implementação de uma ferramenta de gerenciamento de ativos na fase de concepção do projeto é muito importante;  A ferramenta deve já estar operacional no início da fase de comissionamento para a otimização desta etapa do projeto;  Quais diagnósticos são importantes para a minha planta? (impacto na seleção de instrumentos);  Quais funcionalidade são necessárias na ferramenta de gestão de ativos?  Podem ser necessárias adaptações aos procedimentos de manutenção da planta;  Integração da ferramenta de gerenciamento de ativos com sistemas de gestão de manutenção tipo CMMS: – Alertas de manutenção podem gerar Ordens de Serviço automaticamente.17 March 2012
    • 18. Exemplo de Arquitetura de Sistema com Gerenciamento de Ativos Clientes de Gerenciamento de Ativos Corporativa Portal de Gerenciamento Gerenciamento de Alarmes de Ativos Serviços Gerenciamento Operação de Ativos ControleDCS DCS SIS Rotativos18 March 2012
    • 19. Conectividade com várias TecnologiasWireless19 March 2012
    • 20. Exemplo de Alerta de manutenção a partir de diagnósticos FF integrados ao Gerenciamento de Ativos20 March 2012
    • 21. Exemplo de Benefício RealEconomia obtida com o uso dediagnósticos de válvulas decontrole
    • 22. Aplicação – redução de perdas para Flare  Tipicamente uma planta de PP possui válvulas de controle que aliviam para a tocha. Em condições ideais, estas devem estar fechadas 100% do tempo.  Uma válvula com abertura indevida pode levar à perdas de matéria prima.22 March 2012
    • 23. A Detecção do Problema Utilizando-se a ferramenta de gerenciamento de ativos com diagnósticos avançados (ValveLink), descobriu-se que uma válvula com posicionador FF estava operando 3% aberta indevidamente. Curso projetado: 0 a 1,25 in Curso atual: 0,25 a 1 in23 March 2012
    • 24. A Detecção do Problema  A válvula também apresentava problema de Bench-set (ajuste da mola) Bench-set projetado: 6 a 15 psi Bench-set atual: 4 a 15 psi24 March 2012
    • 25. A Solução  A solução para estes problemas foi executar o ajuste do Bench-set e uma calibração da válvula através do próprio software AMS DM e ValveLink Curso atual: 0 a 1,25 in; Bench-set atual: 6 a 15 psi25 March 2012
    • 26. Resultado• A abertura de 3% desta válvula representava uma perda de 20kg/h de propeno• Financeiramente, este vazamento representava cerca de R$ 440 mil/ano (US$ 250mil/ano).• Este benefício operacional foi possivel graças ao uso de posicionador de válvulas dotado de tecnologia FF utilizado em conjunto com ferramenta de gerenciamento de ativos (AMS Device Manager com ValveLink).26 March 2012
    • 27. Exemplo deInteroperabilidadeTroca de sistema mantendo-se asredes e instrumentos existentes
    • 28. Sucesso com Interoperabilidade• Tivemos uma experiência muito interessante com a troca de um sistema (DCS) em uma de nossas plantas;• Foi possivel realizar a migração mantendo-se todos os instrumentos e dispositivos de rede FF existentes;• Porém, tivemos um certo trabalho, pricipalmente para acertar as versões corretas das DD’s dos instrumentos.28 March 2012
    • 29. Resumo• Atenção especial deve ser dada a requerimentos particulares em projetos com Foundation Fieldbus;• Fieldbus traz ganhos de instalação e comissionamento, mas o valor real é visto durante a operação;• Ferramentas de Gerenciamento de Ativos (de rede e de instrumentos) são fundamentais para o aproveitamento das potencialidades da tecnologia para a otimização da Manutenção e Operação da planta.29 March 2012
    • 30. Onde obter mais informações  CHAYA, Heitor Hiroshi; SILVA, Alexandre Augusto. A Prática do Gerenciamento de Ativos na Indústria Petroquimica, Intech América do Sul, número 125, Outubro de 2010.  Home-page Braskem: www.braskem.com.br  alexandre.lopes@braskem.com.br30 March 2012