GOLDEN OPPORTUNITY FOR INVESTORS TO SET UP SOLAR POWER PROJECTS IN PUNJAB
Objective: Punjab Energy Development Authority hereinafter referred to as PEDA acting through it
Director invites interested Bidders to purchase the RFP document to participate in the bidding process
for the selection of Bidder(s) for procurement of 500 MW solar power for long term purchase of power
from Grid Connected Solar PV Power Projects through tariff based competitive bidding process for
meeting its Renewable Purchase Obligations. The responsibility of the Successful Bidder(s) shall be to
supply power to the Procurer(s) as per the terms and conditions of the RFP. This RFP is being invited by
PEDA under phase-III of Solar PV Power Projects in Punjab.
Bid must be submitted to PEDA on or before 17:00 hours(IST) on or before 28.07.2015 .The techno-
commercial bid will be opened at 11.30 hours on 30.07.2015 in presence of such bidders or their
authorized representatives who would like to attend the bid opening. If it is a public holiday on the last
date for submission of the Bid, the submission and the receipt of the Bid shall be on the next working
day at the place of submission of Bid. The date of opening of financial bid will be intimated later on.
The Bid submitted by the bidder shall remain valid up to one hundred and eighty (180) days after the Bid
Deadline (“Bid Validity”).
SUMMARY of BID DOCUMENT
Bid Inviting Entity PEDA
Contract Period 25 Years
Total Capacity of The Bid 500 MW
Maximum Capacity to Bid 150 MW
Minimum Capacity to Bid 50 MW
Pre-bid Conference / Clarification 14.07.2015 at 11.30 A.M
Last date & Time of Submission of tender 28.07.2015 (17.00 Hrs)
Date and time of Bid Opening
(Tecno-Commercial)
30.07.2015 ( 11.30 Hrs)
Companies Eligible for Participation in Bid
(i) A company incorporated in India under the Companies Act 1956
(ii) A company incorporated outside India
(iii) Limited Liability Partnership and Limited Liability Companies whether incorporated in India or
outside India Bidding Consortium of maximum three Bidding Companies
Technical Criteria for Bid Participation:
EnvironmentFirst
“Let the Environment be your first Inspiration”
Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.)
info@environmentfirst.in +91 731 6007860 www.environmentfirst.in
Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula
GOLDEN OPPORTUNITY FOR INVESTORS TO SET UP SOLAR POWER PROJECTS IN PUNJAB
Objective: Punjab Energy Development Authority hereinafter referred to as PEDA acting through it
Director invites interested Bidders to purchase the RFP document to participate in the bidding process
for the selection of Bidder(s) for procurement of 500 MW solar power for long term purchase of power
from Grid Connected Solar PV Power Projects through tariff based competitive bidding process for
meeting its Renewable Purchase Obligations. The responsibility of the Successful Bidder(s) shall be to
supply power to the Procurer(s) as per the terms and conditions of the RFP. This RFP is being invited by
PEDA under phase-III of Solar PV Power Projects in Punjab.
Bid must be submitted to PEDA on or before 17:00 hours(IST) on or before 28.07.2015 .The techno-
commercial bid will be opened at 11.30 hours on 30.07.2015 in presence of such bidders or their
authorized representatives who would like to attend the bid opening. If it is a public holiday on the last
date for submission of the Bid, the submission and the receipt of the Bid shall be on the next working
day at the place of submission of Bid. The date of opening of financial bid will be intimated later on.
The Bid submitted by the bidder shall remain valid up to one hundred and eighty (180) days after the Bid
Deadline (“Bid Validity”).
SUMMARY of BID DOCUMENT
Bid Inviting Entity PEDA
Contract Period 25 Years
Total Capacity of The Bid 500 MW
Maximum Capacity to Bid 150 MW
Minimum Capacity to Bid 50 MW
Pre-bid Conference / Clarification 14.07.2015 at 11.30 A.M
Last date & Time of Submission of tender 28.07.2015 (17.00 Hrs)
Date and time of Bid Opening
(Tecno-Commercial)
30.07.2015 ( 11.30 Hrs)
Companies Eligible for Participation in Bid
(i) A company incorporated in India under the Companies Act 1956
(ii) A company incorporated outside India
(iii) Limited Liability Partnership and Limited Liability Companies whether incorporated in India or
outside India Bidding Consortium of maximum three Bidding Companies
Technical Criteria for Bid Participation:
EnvironmentFirst
“Let the Environment be your first Inspiration”
Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.)
info@environmentfirst.in +91 731 6007860 www.environmentfirst.in
Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula
GOLDEN OPPORTUNITY FOR INVESTORS TO SET UP SOLAR POWER PROJECTS IN PUNJAB
Objective: Punjab Energy Development Authority hereinafter referred to as PEDA acting through it
Director invites interested Bidders to purchase the RFP document to participate in the bidding process
for the selection of Bidder(s) for procurement of 500 MW solar power for long term purchase of power
from Grid Connected Solar PV Power Projects through tariff based competitive bidding process for
meeting its Renewable Purchase Obligations. The responsibility of the Successful Bidder(s) shall be to
supply power to the Procurer(s) as per the terms and conditions of the RFP. This RFP is being invited by
PEDA under phase-III of Solar PV Power Projects in Punjab.
Bid must be submitted to PEDA on or before 17:00 hours(IST) on or before 28.07.2015 .The techno-
commercial bid will be opened at 11.30 hours on 30.07.2015 in presence of such bidders or their
authorized representatives who would like to attend the bid opening. If it is a public holiday on the last
date for submission of the Bid, the submission and the receipt of the Bid shall be on the next working
day at the place of submission of Bid. The date of opening of financial bid will be intimated later on.
The Bid submitted by the bidder shall remain valid up to one hundred and eighty (180) days after the Bid
Deadline (“Bid Validity”).
SUMMARY of BID DOCUMENT
Bid Inviting Entity PEDA
Contract Period 25 Years
Total Capacity of The Bid 500 MW
Maximum Capacity to Bid 150 MW
Minimum Capacity to Bid 50 MW
Pre-bid Conference / Clarification 14.07.2015 at 11.30 A.M
Last date & Time of Submission of tender 28.07.2015 (17.00 Hrs)
Date and time of Bid Opening
(Tecno-Commercial)
30.07.2015 ( 11.30 Hrs)
Companies Eligible for Participation in Bid
(i) A company incorporated in India under the Companies Act 1956
(ii) A company incorporated outside India
(iii) Limited Liability Partnership and Limited Liability Companies whether incorporated in India or
outside India Bidding Consortium of maximum three Bidding Companies
Technical Criteria for Bid Participation:
EnvironmentFirst
“Let the Environment be your first Inspiration”
Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.)
info@environmentfirst.in +91 731 6007860 www.environmentfirst.in
Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula
(Newly Incorporated Bidding Company / Existing Bidding Company/Consortium: The
bidding company or in case of consortium, a member thereof should have installed and commissioned
Solar power projects of aggregate capacity 25 MW or higher grid connected capacity which is/are in
operation anywhere in the world before the last date of submission of e-bid. For this purpose, the
Bidder is required to furnish the letter from concerned Nodal Agency / Project Owner/client for
successful commissioning/operation of project before the last date of submission of e-bid.
The Bidders shall deploy commercially successful and operational technology wherein there is at least
one project successfully operational of the proposed technology, for at least one year before the last
date of submission of e - bid, anywhere in the world. The Bidder is required to furnish evidence of
meeting the above eligibility criteria for technology usage before financial closure.
Financial Criteria for Bid Participation:
The existing companies shall meet the financial criteria as stated below:-
Net Worth: Rs. 1,50,00,000/- (Rupees One Crore Fifty Lakh Only) per MW or equivalent US$* per MW of
the capacity. The computation shall be derived from any of the last three year‘s annual accounts.
Net Worth:
= Paid up share capital
Add: Free Reserves
Subtract: Revaluation Reserves
Subtract: Intangible Assets
Subtract: Miscellaneous Expenditures to the extent not written off and carry forward losses.
FEE and BANK GAURANTEES Involved in Bidding
i. Bid Document Fees (Non Refundable)
Rs. 5,000/- (Rupees five thousand rupees)
ii. E – bidding processing fee (Non refundable)
Rs. 2,247/- (Rupees Two Thousand Two Hundred and Forty Seven Only)
iii. Bid Processing Fee (Non Refundable)
Rs. 5,00,000/- (Rupees Five Lacs Only) per bid
(All above fees are non refundable and payable online through IPG / RTGS mode.)
iv. Earnest Money Deposit as per format 6.3 A;
Rs. 5,00,000/- (Rupees Five Lac only) per MW through IPG / RTGS or in the form of bank guarantee
Due Date
The Bidders should upload the response to RfP as specified in e-tender notice by (IST) 28th July 2015 by
5.00 PM.
Time Schedule for Commissioning of Solar PV Power Projects
EnvironmentFirst
“Let the Environment be your first Inspiration”
Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.)
info@environmentfirst.in +91 731 6007860 www.environmentfirst.in
Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula
(Newly Incorporated Bidding Company / Existing Bidding Company/Consortium: The
bidding company or in case of consortium, a member thereof should have installed and commissioned
Solar power projects of aggregate capacity 25 MW or higher grid connected capacity which is/are in
operation anywhere in the world before the last date of submission of e-bid. For this purpose, the
Bidder is required to furnish the letter from concerned Nodal Agency / Project Owner/client for
successful commissioning/operation of project before the last date of submission of e-bid.
The Bidders shall deploy commercially successful and operational technology wherein there is at least
one project successfully operational of the proposed technology, for at least one year before the last
date of submission of e - bid, anywhere in the world. The Bidder is required to furnish evidence of
meeting the above eligibility criteria for technology usage before financial closure.
Financial Criteria for Bid Participation:
The existing companies shall meet the financial criteria as stated below:-
Net Worth: Rs. 1,50,00,000/- (Rupees One Crore Fifty Lakh Only) per MW or equivalent US$* per MW of
the capacity. The computation shall be derived from any of the last three year‘s annual accounts.
Net Worth:
= Paid up share capital
Add: Free Reserves
Subtract: Revaluation Reserves
Subtract: Intangible Assets
Subtract: Miscellaneous Expenditures to the extent not written off and carry forward losses.
FEE and BANK GAURANTEES Involved in Bidding
i. Bid Document Fees (Non Refundable)
Rs. 5,000/- (Rupees five thousand rupees)
ii. E – bidding processing fee (Non refundable)
Rs. 2,247/- (Rupees Two Thousand Two Hundred and Forty Seven Only)
iii. Bid Processing Fee (Non Refundable)
Rs. 5,00,000/- (Rupees Five Lacs Only) per bid
(All above fees are non refundable and payable online through IPG / RTGS mode.)
iv. Earnest Money Deposit as per format 6.3 A;
Rs. 5,00,000/- (Rupees Five Lac only) per MW through IPG / RTGS or in the form of bank guarantee
Due Date
The Bidders should upload the response to RfP as specified in e-tender notice by (IST) 28th July 2015 by
5.00 PM.
Time Schedule for Commissioning of Solar PV Power Projects
EnvironmentFirst
“Let the Environment be your first Inspiration”
Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.)
info@environmentfirst.in +91 731 6007860 www.environmentfirst.in
Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula
(Newly Incorporated Bidding Company / Existing Bidding Company/Consortium: The
bidding company or in case of consortium, a member thereof should have installed and commissioned
Solar power projects of aggregate capacity 25 MW or higher grid connected capacity which is/are in
operation anywhere in the world before the last date of submission of e-bid. For this purpose, the
Bidder is required to furnish the letter from concerned Nodal Agency / Project Owner/client for
successful commissioning/operation of project before the last date of submission of e-bid.
The Bidders shall deploy commercially successful and operational technology wherein there is at least
one project successfully operational of the proposed technology, for at least one year before the last
date of submission of e - bid, anywhere in the world. The Bidder is required to furnish evidence of
meeting the above eligibility criteria for technology usage before financial closure.
Financial Criteria for Bid Participation:
The existing companies shall meet the financial criteria as stated below:-
Net Worth: Rs. 1,50,00,000/- (Rupees One Crore Fifty Lakh Only) per MW or equivalent US$* per MW of
the capacity. The computation shall be derived from any of the last three year‘s annual accounts.
Net Worth:
= Paid up share capital
Add: Free Reserves
Subtract: Revaluation Reserves
Subtract: Intangible Assets
Subtract: Miscellaneous Expenditures to the extent not written off and carry forward losses.
FEE and BANK GAURANTEES Involved in Bidding
i. Bid Document Fees (Non Refundable)
Rs. 5,000/- (Rupees five thousand rupees)
ii. E – bidding processing fee (Non refundable)
Rs. 2,247/- (Rupees Two Thousand Two Hundred and Forty Seven Only)
iii. Bid Processing Fee (Non Refundable)
Rs. 5,00,000/- (Rupees Five Lacs Only) per bid
(All above fees are non refundable and payable online through IPG / RTGS mode.)
iv. Earnest Money Deposit as per format 6.3 A;
Rs. 5,00,000/- (Rupees Five Lac only) per MW through IPG / RTGS or in the form of bank guarantee
Due Date
The Bidders should upload the response to RfP as specified in e-tender notice by (IST) 28th July 2015 by
5.00 PM.
Time Schedule for Commissioning of Solar PV Power Projects
EnvironmentFirst
“Let the Environment be your first Inspiration”
Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.)
info@environmentfirst.in +91 731 6007860 www.environmentfirst.in
Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula
Selection of Solar PV Projects shall be carried out according to the timeline given
below:
Sr. No. Event Date (D)
1 Issue of Letter of Award (LoA) Zero date
2 Signing of Implementation Agreement Within 30 days from the issue of Letter of award
(LoA date + 30 days)
3 Signing of Power Purchase Agreement Within 30 days from the date of Signing of IA
(LoA + 60 days)
4 Financial closure / Financing Arrangement
for the project
Submission of documents for financial closure /
Financing Arrangement within 150 days from
the date of signing of PPA ( PPA + 150 days)
5 Commissioning of the Project 12 months from the date of signing of PPA
6 Extension of 30 days with fee Rs. 20000 /
MW / day
13 months from the date of signing of PPA
7 Further Extension of 60 days with Fee of
Rs. 40,000/MW/day
15 months from the date of signing of PPA
8 After 15 months Right retains with PEDA for forfeiture of
Performance BG
9 Commissioning post performance BG
forfeiture with Liquidated Damages
17 months from date of signing of PPA
For Further Details you can reach us at
EnvironmentFirst Energy Services (P) Ltd.
405 A I Prakrati Corporate I Y N Road I Indore 452001
Branches- Mumbai, Delhi, Jaipur, Panchkula,Chennai
Phone- 0731 6007860, 2970493
E-mail- info@environmentfirst.in
Web- www.environmentfirst.in
EnvironmentFirst
“Let the Environment be your first Inspiration”
Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.)
info@environmentfirst.in +91 731 6007860 www.environmentfirst.in
Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula
Selection of Solar PV Projects shall be carried out according to the timeline given
below:
Sr. No. Event Date (D)
1 Issue of Letter of Award (LoA) Zero date
2 Signing of Implementation Agreement Within 30 days from the issue of Letter of award
(LoA date + 30 days)
3 Signing of Power Purchase Agreement Within 30 days from the date of Signing of IA
(LoA + 60 days)
4 Financial closure / Financing Arrangement
for the project
Submission of documents for financial closure /
Financing Arrangement within 150 days from
the date of signing of PPA ( PPA + 150 days)
5 Commissioning of the Project 12 months from the date of signing of PPA
6 Extension of 30 days with fee Rs. 20000 /
MW / day
13 months from the date of signing of PPA
7 Further Extension of 60 days with Fee of
Rs. 40,000/MW/day
15 months from the date of signing of PPA
8 After 15 months Right retains with PEDA for forfeiture of
Performance BG
9 Commissioning post performance BG
forfeiture with Liquidated Damages
17 months from date of signing of PPA
For Further Details you can reach us at
EnvironmentFirst Energy Services (P) Ltd.
405 A I Prakrati Corporate I Y N Road I Indore 452001
Branches- Mumbai, Delhi, Jaipur, Panchkula,Chennai
Phone- 0731 6007860, 2970493
E-mail- info@environmentfirst.in
Web- www.environmentfirst.in
EnvironmentFirst
“Let the Environment be your first Inspiration”
Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.)
info@environmentfirst.in +91 731 6007860 www.environmentfirst.in
Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula
Selection of Solar PV Projects shall be carried out according to the timeline given
below:
Sr. No. Event Date (D)
1 Issue of Letter of Award (LoA) Zero date
2 Signing of Implementation Agreement Within 30 days from the issue of Letter of award
(LoA date + 30 days)
3 Signing of Power Purchase Agreement Within 30 days from the date of Signing of IA
(LoA + 60 days)
4 Financial closure / Financing Arrangement
for the project
Submission of documents for financial closure /
Financing Arrangement within 150 days from
the date of signing of PPA ( PPA + 150 days)
5 Commissioning of the Project 12 months from the date of signing of PPA
6 Extension of 30 days with fee Rs. 20000 /
MW / day
13 months from the date of signing of PPA
7 Further Extension of 60 days with Fee of
Rs. 40,000/MW/day
15 months from the date of signing of PPA
8 After 15 months Right retains with PEDA for forfeiture of
Performance BG
9 Commissioning post performance BG
forfeiture with Liquidated Damages
17 months from date of signing of PPA
For Further Details you can reach us at
EnvironmentFirst Energy Services (P) Ltd.
405 A I Prakrati Corporate I Y N Road I Indore 452001
Branches- Mumbai, Delhi, Jaipur, Panchkula,Chennai
Phone- 0731 6007860, 2970493
E-mail- info@environmentfirst.in
Web- www.environmentfirst.in

More Related Content

More from Harish Sharma

Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in IndiaHarish Sharma
 
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVRfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVHarish Sharma
 
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...Harish Sharma
 
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIRfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIHarish Sharma
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHHarish Sharma
 
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Harish Sharma
 
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...Harish Sharma
 
PPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of KarnatakaPPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of KarnatakaHarish Sharma
 
RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...Harish Sharma
 
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...Harish Sharma
 
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKARfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKAHarish Sharma
 
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Harish Sharma
 
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...Harish Sharma
 
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabScheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabHarish Sharma
 
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...Harish Sharma
 
Water Benefit Standard (WBS)
Water Benefit Standard (WBS) Water Benefit Standard (WBS)
Water Benefit Standard (WBS) Harish Sharma
 
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Harish Sharma
 
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...Harish Sharma
 
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...Harish Sharma
 
Draft scheme for allocation of solar power projects for land owning farmers
Draft scheme for allocation of solar power projects for land owning farmersDraft scheme for allocation of solar power projects for land owning farmers
Draft scheme for allocation of solar power projects for land owning farmersHarish Sharma
 

More from Harish Sharma (20)

Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in India
 
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IVRfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
RfS for 250 MW in Gujarat Solar Park under NSM Ph-II, Batch-IV
 
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
RfS for 50 MW in Solar Power projects Himachal Pradesh under NSM Ph-II, Batch...
 
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIRfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
 
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESHRfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
RfS 160 MW GRID CONNECTED SOLAR PV in UTTAR PRADESH
 
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
Implementation of 500 MW Grid Connected Roof Top Solar PV System Scheme in Di...
 
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
RfP FOR 1000 MW SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III TRANCH...
 
PPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of KarnatakaPPA draft for the development of solar power project in the state of Karnataka
PPA draft for the development of solar power project in the state of Karnataka
 
RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...RfP for tariff based competitive bidding by KREDL for the installation of 240...
RfP for tariff based competitive bidding by KREDL for the installation of 240...
 
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
RfP invited for setting up 1200 MW Solar PV by Jharkhand Renewable Energy Dev...
 
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKARfP for 1200 MW SOLAR  POWER PROJECTS IN KARNATAKA
RfP for 1200 MW SOLAR POWER PROJECTS IN KARNATAKA
 
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
 
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
Rfp for tariff based competitive bidding for upto 170 mw solar power plant by...
 
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabScheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
 
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...Request for Proposal (RfP)  For  Installation of 2 MW Canal Top Grid connecte...
Request for Proposal (RfP) For Installation of 2 MW Canal Top Grid connecte...
 
Water Benefit Standard (WBS)
Water Benefit Standard (WBS) Water Benefit Standard (WBS)
Water Benefit Standard (WBS)
 
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
Guidelines for Implementation of Scheme for Setting up of 2000 MW Grid-conne...
 
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
 
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
 
Draft scheme for allocation of solar power projects for land owning farmers
Draft scheme for allocation of solar power projects for land owning farmersDraft scheme for allocation of solar power projects for land owning farmers
Draft scheme for allocation of solar power projects for land owning farmers
 

Recently uploaded

(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...ShrutiBose4
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 

Recently uploaded (20)

(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 

Information note on RFP by PEDA for the allotment of 500 MW Solar Power Projects under Phase3

  • 1. EnvironmentFirst “Let the Environment be your first Inspiration” Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.) info@environmentfirst.in +91 731 6007860 www.environmentfirst.in Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula GOLDEN OPPORTUNITY FOR INVESTORS TO SET UP SOLAR POWER PROJECTS IN PUNJAB Objective: Punjab Energy Development Authority hereinafter referred to as PEDA acting through it Director invites interested Bidders to purchase the RFP document to participate in the bidding process for the selection of Bidder(s) for procurement of 500 MW solar power for long term purchase of power from Grid Connected Solar PV Power Projects through tariff based competitive bidding process for meeting its Renewable Purchase Obligations. The responsibility of the Successful Bidder(s) shall be to supply power to the Procurer(s) as per the terms and conditions of the RFP. This RFP is being invited by PEDA under phase-III of Solar PV Power Projects in Punjab. Bid must be submitted to PEDA on or before 17:00 hours(IST) on or before 28.07.2015 .The techno- commercial bid will be opened at 11.30 hours on 30.07.2015 in presence of such bidders or their authorized representatives who would like to attend the bid opening. If it is a public holiday on the last date for submission of the Bid, the submission and the receipt of the Bid shall be on the next working day at the place of submission of Bid. The date of opening of financial bid will be intimated later on. The Bid submitted by the bidder shall remain valid up to one hundred and eighty (180) days after the Bid Deadline (“Bid Validity”). SUMMARY of BID DOCUMENT Bid Inviting Entity PEDA Contract Period 25 Years Total Capacity of The Bid 500 MW Maximum Capacity to Bid 150 MW Minimum Capacity to Bid 50 MW Pre-bid Conference / Clarification 14.07.2015 at 11.30 A.M Last date & Time of Submission of tender 28.07.2015 (17.00 Hrs) Date and time of Bid Opening (Tecno-Commercial) 30.07.2015 ( 11.30 Hrs) Companies Eligible for Participation in Bid (i) A company incorporated in India under the Companies Act 1956 (ii) A company incorporated outside India (iii) Limited Liability Partnership and Limited Liability Companies whether incorporated in India or outside India Bidding Consortium of maximum three Bidding Companies Technical Criteria for Bid Participation: EnvironmentFirst “Let the Environment be your first Inspiration” Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.) info@environmentfirst.in +91 731 6007860 www.environmentfirst.in Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula GOLDEN OPPORTUNITY FOR INVESTORS TO SET UP SOLAR POWER PROJECTS IN PUNJAB Objective: Punjab Energy Development Authority hereinafter referred to as PEDA acting through it Director invites interested Bidders to purchase the RFP document to participate in the bidding process for the selection of Bidder(s) for procurement of 500 MW solar power for long term purchase of power from Grid Connected Solar PV Power Projects through tariff based competitive bidding process for meeting its Renewable Purchase Obligations. The responsibility of the Successful Bidder(s) shall be to supply power to the Procurer(s) as per the terms and conditions of the RFP. This RFP is being invited by PEDA under phase-III of Solar PV Power Projects in Punjab. Bid must be submitted to PEDA on or before 17:00 hours(IST) on or before 28.07.2015 .The techno- commercial bid will be opened at 11.30 hours on 30.07.2015 in presence of such bidders or their authorized representatives who would like to attend the bid opening. If it is a public holiday on the last date for submission of the Bid, the submission and the receipt of the Bid shall be on the next working day at the place of submission of Bid. The date of opening of financial bid will be intimated later on. The Bid submitted by the bidder shall remain valid up to one hundred and eighty (180) days after the Bid Deadline (“Bid Validity”). SUMMARY of BID DOCUMENT Bid Inviting Entity PEDA Contract Period 25 Years Total Capacity of The Bid 500 MW Maximum Capacity to Bid 150 MW Minimum Capacity to Bid 50 MW Pre-bid Conference / Clarification 14.07.2015 at 11.30 A.M Last date & Time of Submission of tender 28.07.2015 (17.00 Hrs) Date and time of Bid Opening (Tecno-Commercial) 30.07.2015 ( 11.30 Hrs) Companies Eligible for Participation in Bid (i) A company incorporated in India under the Companies Act 1956 (ii) A company incorporated outside India (iii) Limited Liability Partnership and Limited Liability Companies whether incorporated in India or outside India Bidding Consortium of maximum three Bidding Companies Technical Criteria for Bid Participation: EnvironmentFirst “Let the Environment be your first Inspiration” Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.) info@environmentfirst.in +91 731 6007860 www.environmentfirst.in Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula GOLDEN OPPORTUNITY FOR INVESTORS TO SET UP SOLAR POWER PROJECTS IN PUNJAB Objective: Punjab Energy Development Authority hereinafter referred to as PEDA acting through it Director invites interested Bidders to purchase the RFP document to participate in the bidding process for the selection of Bidder(s) for procurement of 500 MW solar power for long term purchase of power from Grid Connected Solar PV Power Projects through tariff based competitive bidding process for meeting its Renewable Purchase Obligations. The responsibility of the Successful Bidder(s) shall be to supply power to the Procurer(s) as per the terms and conditions of the RFP. This RFP is being invited by PEDA under phase-III of Solar PV Power Projects in Punjab. Bid must be submitted to PEDA on or before 17:00 hours(IST) on or before 28.07.2015 .The techno- commercial bid will be opened at 11.30 hours on 30.07.2015 in presence of such bidders or their authorized representatives who would like to attend the bid opening. If it is a public holiday on the last date for submission of the Bid, the submission and the receipt of the Bid shall be on the next working day at the place of submission of Bid. The date of opening of financial bid will be intimated later on. The Bid submitted by the bidder shall remain valid up to one hundred and eighty (180) days after the Bid Deadline (“Bid Validity”). SUMMARY of BID DOCUMENT Bid Inviting Entity PEDA Contract Period 25 Years Total Capacity of The Bid 500 MW Maximum Capacity to Bid 150 MW Minimum Capacity to Bid 50 MW Pre-bid Conference / Clarification 14.07.2015 at 11.30 A.M Last date & Time of Submission of tender 28.07.2015 (17.00 Hrs) Date and time of Bid Opening (Tecno-Commercial) 30.07.2015 ( 11.30 Hrs) Companies Eligible for Participation in Bid (i) A company incorporated in India under the Companies Act 1956 (ii) A company incorporated outside India (iii) Limited Liability Partnership and Limited Liability Companies whether incorporated in India or outside India Bidding Consortium of maximum three Bidding Companies Technical Criteria for Bid Participation:
  • 2. EnvironmentFirst “Let the Environment be your first Inspiration” Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.) info@environmentfirst.in +91 731 6007860 www.environmentfirst.in Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula (Newly Incorporated Bidding Company / Existing Bidding Company/Consortium: The bidding company or in case of consortium, a member thereof should have installed and commissioned Solar power projects of aggregate capacity 25 MW or higher grid connected capacity which is/are in operation anywhere in the world before the last date of submission of e-bid. For this purpose, the Bidder is required to furnish the letter from concerned Nodal Agency / Project Owner/client for successful commissioning/operation of project before the last date of submission of e-bid. The Bidders shall deploy commercially successful and operational technology wherein there is at least one project successfully operational of the proposed technology, for at least one year before the last date of submission of e - bid, anywhere in the world. The Bidder is required to furnish evidence of meeting the above eligibility criteria for technology usage before financial closure. Financial Criteria for Bid Participation: The existing companies shall meet the financial criteria as stated below:- Net Worth: Rs. 1,50,00,000/- (Rupees One Crore Fifty Lakh Only) per MW or equivalent US$* per MW of the capacity. The computation shall be derived from any of the last three year‘s annual accounts. Net Worth: = Paid up share capital Add: Free Reserves Subtract: Revaluation Reserves Subtract: Intangible Assets Subtract: Miscellaneous Expenditures to the extent not written off and carry forward losses. FEE and BANK GAURANTEES Involved in Bidding i. Bid Document Fees (Non Refundable) Rs. 5,000/- (Rupees five thousand rupees) ii. E – bidding processing fee (Non refundable) Rs. 2,247/- (Rupees Two Thousand Two Hundred and Forty Seven Only) iii. Bid Processing Fee (Non Refundable) Rs. 5,00,000/- (Rupees Five Lacs Only) per bid (All above fees are non refundable and payable online through IPG / RTGS mode.) iv. Earnest Money Deposit as per format 6.3 A; Rs. 5,00,000/- (Rupees Five Lac only) per MW through IPG / RTGS or in the form of bank guarantee Due Date The Bidders should upload the response to RfP as specified in e-tender notice by (IST) 28th July 2015 by 5.00 PM. Time Schedule for Commissioning of Solar PV Power Projects EnvironmentFirst “Let the Environment be your first Inspiration” Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.) info@environmentfirst.in +91 731 6007860 www.environmentfirst.in Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula (Newly Incorporated Bidding Company / Existing Bidding Company/Consortium: The bidding company or in case of consortium, a member thereof should have installed and commissioned Solar power projects of aggregate capacity 25 MW or higher grid connected capacity which is/are in operation anywhere in the world before the last date of submission of e-bid. For this purpose, the Bidder is required to furnish the letter from concerned Nodal Agency / Project Owner/client for successful commissioning/operation of project before the last date of submission of e-bid. The Bidders shall deploy commercially successful and operational technology wherein there is at least one project successfully operational of the proposed technology, for at least one year before the last date of submission of e - bid, anywhere in the world. The Bidder is required to furnish evidence of meeting the above eligibility criteria for technology usage before financial closure. Financial Criteria for Bid Participation: The existing companies shall meet the financial criteria as stated below:- Net Worth: Rs. 1,50,00,000/- (Rupees One Crore Fifty Lakh Only) per MW or equivalent US$* per MW of the capacity. The computation shall be derived from any of the last three year‘s annual accounts. Net Worth: = Paid up share capital Add: Free Reserves Subtract: Revaluation Reserves Subtract: Intangible Assets Subtract: Miscellaneous Expenditures to the extent not written off and carry forward losses. FEE and BANK GAURANTEES Involved in Bidding i. Bid Document Fees (Non Refundable) Rs. 5,000/- (Rupees five thousand rupees) ii. E – bidding processing fee (Non refundable) Rs. 2,247/- (Rupees Two Thousand Two Hundred and Forty Seven Only) iii. Bid Processing Fee (Non Refundable) Rs. 5,00,000/- (Rupees Five Lacs Only) per bid (All above fees are non refundable and payable online through IPG / RTGS mode.) iv. Earnest Money Deposit as per format 6.3 A; Rs. 5,00,000/- (Rupees Five Lac only) per MW through IPG / RTGS or in the form of bank guarantee Due Date The Bidders should upload the response to RfP as specified in e-tender notice by (IST) 28th July 2015 by 5.00 PM. Time Schedule for Commissioning of Solar PV Power Projects EnvironmentFirst “Let the Environment be your first Inspiration” Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.) info@environmentfirst.in +91 731 6007860 www.environmentfirst.in Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula (Newly Incorporated Bidding Company / Existing Bidding Company/Consortium: The bidding company or in case of consortium, a member thereof should have installed and commissioned Solar power projects of aggregate capacity 25 MW or higher grid connected capacity which is/are in operation anywhere in the world before the last date of submission of e-bid. For this purpose, the Bidder is required to furnish the letter from concerned Nodal Agency / Project Owner/client for successful commissioning/operation of project before the last date of submission of e-bid. The Bidders shall deploy commercially successful and operational technology wherein there is at least one project successfully operational of the proposed technology, for at least one year before the last date of submission of e - bid, anywhere in the world. The Bidder is required to furnish evidence of meeting the above eligibility criteria for technology usage before financial closure. Financial Criteria for Bid Participation: The existing companies shall meet the financial criteria as stated below:- Net Worth: Rs. 1,50,00,000/- (Rupees One Crore Fifty Lakh Only) per MW or equivalent US$* per MW of the capacity. The computation shall be derived from any of the last three year‘s annual accounts. Net Worth: = Paid up share capital Add: Free Reserves Subtract: Revaluation Reserves Subtract: Intangible Assets Subtract: Miscellaneous Expenditures to the extent not written off and carry forward losses. FEE and BANK GAURANTEES Involved in Bidding i. Bid Document Fees (Non Refundable) Rs. 5,000/- (Rupees five thousand rupees) ii. E – bidding processing fee (Non refundable) Rs. 2,247/- (Rupees Two Thousand Two Hundred and Forty Seven Only) iii. Bid Processing Fee (Non Refundable) Rs. 5,00,000/- (Rupees Five Lacs Only) per bid (All above fees are non refundable and payable online through IPG / RTGS mode.) iv. Earnest Money Deposit as per format 6.3 A; Rs. 5,00,000/- (Rupees Five Lac only) per MW through IPG / RTGS or in the form of bank guarantee Due Date The Bidders should upload the response to RfP as specified in e-tender notice by (IST) 28th July 2015 by 5.00 PM. Time Schedule for Commissioning of Solar PV Power Projects
  • 3. EnvironmentFirst “Let the Environment be your first Inspiration” Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.) info@environmentfirst.in +91 731 6007860 www.environmentfirst.in Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula Selection of Solar PV Projects shall be carried out according to the timeline given below: Sr. No. Event Date (D) 1 Issue of Letter of Award (LoA) Zero date 2 Signing of Implementation Agreement Within 30 days from the issue of Letter of award (LoA date + 30 days) 3 Signing of Power Purchase Agreement Within 30 days from the date of Signing of IA (LoA + 60 days) 4 Financial closure / Financing Arrangement for the project Submission of documents for financial closure / Financing Arrangement within 150 days from the date of signing of PPA ( PPA + 150 days) 5 Commissioning of the Project 12 months from the date of signing of PPA 6 Extension of 30 days with fee Rs. 20000 / MW / day 13 months from the date of signing of PPA 7 Further Extension of 60 days with Fee of Rs. 40,000/MW/day 15 months from the date of signing of PPA 8 After 15 months Right retains with PEDA for forfeiture of Performance BG 9 Commissioning post performance BG forfeiture with Liquidated Damages 17 months from date of signing of PPA For Further Details you can reach us at EnvironmentFirst Energy Services (P) Ltd. 405 A I Prakrati Corporate I Y N Road I Indore 452001 Branches- Mumbai, Delhi, Jaipur, Panchkula,Chennai Phone- 0731 6007860, 2970493 E-mail- info@environmentfirst.in Web- www.environmentfirst.in EnvironmentFirst “Let the Environment be your first Inspiration” Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.) info@environmentfirst.in +91 731 6007860 www.environmentfirst.in Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula Selection of Solar PV Projects shall be carried out according to the timeline given below: Sr. No. Event Date (D) 1 Issue of Letter of Award (LoA) Zero date 2 Signing of Implementation Agreement Within 30 days from the issue of Letter of award (LoA date + 30 days) 3 Signing of Power Purchase Agreement Within 30 days from the date of Signing of IA (LoA + 60 days) 4 Financial closure / Financing Arrangement for the project Submission of documents for financial closure / Financing Arrangement within 150 days from the date of signing of PPA ( PPA + 150 days) 5 Commissioning of the Project 12 months from the date of signing of PPA 6 Extension of 30 days with fee Rs. 20000 / MW / day 13 months from the date of signing of PPA 7 Further Extension of 60 days with Fee of Rs. 40,000/MW/day 15 months from the date of signing of PPA 8 After 15 months Right retains with PEDA for forfeiture of Performance BG 9 Commissioning post performance BG forfeiture with Liquidated Damages 17 months from date of signing of PPA For Further Details you can reach us at EnvironmentFirst Energy Services (P) Ltd. 405 A I Prakrati Corporate I Y N Road I Indore 452001 Branches- Mumbai, Delhi, Jaipur, Panchkula,Chennai Phone- 0731 6007860, 2970493 E-mail- info@environmentfirst.in Web- www.environmentfirst.in EnvironmentFirst “Let the Environment be your first Inspiration” Registered Office: EnvironmentFirst Energy Services (P) Ltd.; Prakrati Corporate, 405 – Block A; Y N Road, Indore – 452001 (M.P.) info@environmentfirst.in +91 731 6007860 www.environmentfirst.in Representative Locations: Mumbai, Delhi, Chennai, Ahmedabad, Jaipur, Panchkula Selection of Solar PV Projects shall be carried out according to the timeline given below: Sr. No. Event Date (D) 1 Issue of Letter of Award (LoA) Zero date 2 Signing of Implementation Agreement Within 30 days from the issue of Letter of award (LoA date + 30 days) 3 Signing of Power Purchase Agreement Within 30 days from the date of Signing of IA (LoA + 60 days) 4 Financial closure / Financing Arrangement for the project Submission of documents for financial closure / Financing Arrangement within 150 days from the date of signing of PPA ( PPA + 150 days) 5 Commissioning of the Project 12 months from the date of signing of PPA 6 Extension of 30 days with fee Rs. 20000 / MW / day 13 months from the date of signing of PPA 7 Further Extension of 60 days with Fee of Rs. 40,000/MW/day 15 months from the date of signing of PPA 8 After 15 months Right retains with PEDA for forfeiture of Performance BG 9 Commissioning post performance BG forfeiture with Liquidated Damages 17 months from date of signing of PPA For Further Details you can reach us at EnvironmentFirst Energy Services (P) Ltd. 405 A I Prakrati Corporate I Y N Road I Indore 452001 Branches- Mumbai, Delhi, Jaipur, Panchkula,Chennai Phone- 0731 6007860, 2970493 E-mail- info@environmentfirst.in Web- www.environmentfirst.in