Cassilis Hydro Electric Scheme Slide Presentation August 2006 - Presentation Transcript
Cassilis Hydro
Scheme
Victoria’s Pioneer Hydro-Electric Scheme
Operated from 1908 – 1916
Presented by
John McCutchan
As part of the
NOTE : The Slides contained in this file are from the Engineering Heritage Victoria
original presentation - with titles added. They are for
Speakers’ Program
illustrative purposes and not intended to tell the full story
August 2006
by themselves. Accompanying audio files will be
available in the near future. Copyright may apply to some
Email : ehv@engineersaustralia.org.au
of the maps and photographs contained herein.
Slide 2 : General Location of Cassilis - in the east of Victoria (Australia)
Slide 9 : One of 4
Waterfalls on the
Victoria River
Slide 10 :
The Victoria River drops a
total of 120 metres before
joining the Cobungra River
Slide 11 : John Avery
Assistant to Mr Coote
Slide 12 :
The 1907 Tender Specification
(cover page only)
Slide 13
John Avery’s marginal
notes on Tender
Specification
Slide 14
more Avery marginal
notes and sketches
Slide 15
… and more Avery
marginal notes &
sketches
Slide 16 : Receipt for John Avery’s purchase of “Half-Plate Camera” - 1900
Slide 17 : The 7 Tenders received from around the world
Slide 18 : Extract from the successful tender by Staerker & Fischer
Slide 19 : Part of Bundara-Munjie Parish Plan - showing the location of the Water Race
Slide 20 : excavation of the 5 km water race
Slide 21 : the Water Race in winter
Slide 22 : construction of the Small Pondage at the end of the Water Race
Slide 23 : the completed Pondage
Slide 24 :
Pipeline
Specification
Slide 25 : the successful Pipeline Tender from Mephan Ferguson - 1907
Slide 26 : lowering a 6m length of riveted pipe down the hill
Slide 27 : the Pipeline was buried after pressure testing
Slide 28 : all plant was conveyed 110 miles from Bairnsdale Railway Station
Slide 29 :
some of the route
covered rough tracks
Slide 30 : a load arriving at the Power Station site
Slide 31 : the Pelton Wheel & 2.5 tonne flywheel
Slide 32 : erecting the Turbine
Slide 33 : temporary accommodation for the erection team !
Slide 34 :
A 1911 Technical
Description of the
Plant
Slide 35 :
The Voith
Hydraulic
Governor
Slide 36 : the Set achieved a max efficiency rating of about 70%
Slide 37 : the 670 HP (400 kW) Main Set & the 17 HP auxiliary set.
Slide 38 :
The Switchboard
LH Panel : Tirrell Voltage Regulator
Centre : HV circuit breaker overload relays & instruments
RH Panel : Controls for the 110 V dc auxiliary set
Slide 39 : the completed Power Station beside the Cobungra River
Slide 40 :
The 26 km 12 kV Transmission
Line crossed the Great Dividing
Range
Slide 41 :
Suitable trees on the
line were topped to
serve as “poles”
Slide 42 : about 490 poles were erected at 45 metre intervals
Slide 43 : poles on Transmission Line
Slide 44 :
The Conductors were
4.5mm diameter solid
hard-drawn copper
Slide 45 : The Treatment Works after electrification
Slide 46 :
Electricity Output
figures for the
first 16 months
Slide 47 : graph of Electricity Production
- shows shortage during 1908/09 summer
Slide 48 :
Gold Production Figures
for the Mine
Slide 49 : construction of small storage dam in 1916
Slide 50 : but … the tipped clay (wall material) was not properly compacted
Slide 51 : by the time this “description” was published, the dam had washed away!
Slide 52 : Sale of the Mine
Slide 53 : the Final Auction of all of the Plant etc
Slide 54 : a possible (much longer) water race to tap the larger Cobungra River
Slide 55 :
Minimum monthly
flows in the
Cobungra River
1926-35
Slide 56 :
Detail - showing that a
storage dam would have
been needed because of
the low summer flows
Slide 57 :
Section through the
Cassilis Mine showing
the 180m deep internal
shaft
Slide 58 - Location of :
1. Victoria Falls Historic Area
2. Cassilis Historic Area
Slide 59 : The Water Race was filled in to create the Victoria Falls Road in 1965
Slide 60 : The present Victoria Falls Road turnoff from the Alpine Road
Slide 61 : Picnic Area beside the Victoria River (recent photo)
Slide 62 : Interpretation Notes beside the Victoria River (recent photo).
Slide 63 : The Tourist Road (formerly the Water Race) above the Victoria River (recent photo)
Slide 64 : The Pondage at the end of the Water Race (recent photograph)
Slide 65 :
The inlet structure
for the old
Pipeline
(recent photo).
Slide 66 : the tapered entry to the 34 inch pipe (recent photo).
Slide 67 : Remains of the Power Station beside the Cobungra River (recent photo).
Slide 68 : View across the Power Station floor (recent photo).
Slide 69 : The foundations of the Water Turbine (recent photo)
Slide 70 : The concrete cubicles once housed the surge diverters on the Transmission Line
Slide 71 : the completed Power Station in operation
Slide 72 : Recent view from the same photopoint as Slide 71
Slide 73 : this “name” – painted on the concrete – led to
meeting the last man to operate the Power Station
Slide 74 :
Les Kracke,
interviewed in 1979
Slide 75 :
The reference written
for Les Kracke in
1916
Slide 76 : the reference written for Les Kracke
Slide 77 : An insulator from the telephone line which ran beside the transmission line.
Slide 78 : Another insulator from the telephone line
Slide 79 : The transmission line easement was still shown on the Parish Plan in 1980
Slide 80 : A broken Transmission Line Insulator
Slide 81 : Remains of Sub-station at the Mine Entrance (recent photo)
Slide 82 : The Sub-station at the Treatment Works
Slide 83 : The remnants of the Sub-station in recent times
Slide 84 : the Treatment Works – after electrification.
The Sub-station is in the lower right corner.
Slide 85 : Recent view from the same photopoint as Slide 84
Slide 86 :
The next home for the plant was
at the Magnet Silver Mine, near
Waratah (Tasmania).
Slide 87 :
Magnet is west of Waratah
Slide 88 :
Water was obtained from
dams on the Arthur River
Slide 89 : Remains at Magnet in 1981 – Power Station foundations on left – Mill Building on right
Slide 90 : The foundation block for the Water Turbine at Magnet
Slide 91 : The Power Station in front of the Mill at Magnet
Slide 92 : Note the unused lengths of pipe. The Magnet pipeline was shorter
than the Cobungra one.
Slide 93 : The 670 HP Set in action at Magnet
Slide 94 : The Magnet Switchboard – note the three panels on the left.
Slide 95 : the 3 Switchboard panels at Cobungra
Slide 96 : Auction Notice for the Magnet Mine (1940)
Slide 97 : The 2 foot gauge Magnet Tramway – on which all of the Magnet plant was removed
Slide 98 :
The Magnet Tramway
ended at Magnet
Junction beside the Emu
Bay Railway branch line
to Waratah
Slide 99 : Magnet Junction was located beside the one-time airfield
Slide 100 : Some of the pipes from Cobungra would not have been needed at Magnet
Slide 101 : An original 1907 pipe lying at Magnet Junction
Slide 102 : the same pipe ready to be installed in 1908
Slide 103 : Early Hydro-electric Schemes in Victoria
The End
Thanks are due to three generations of the Avery Family
who looked after many of the documents and photographs
used in this presentation – for 100 years. Their generosity in
making the material so readily available is acknowledged.
This Talk was prepared and delivered by
John McCutchan
PowerPoint presentation prepared by
Don Bartlett
Email : ehv@engineersaustralia.org.au
0 comments
Post a comment