Function: Facility monitoring system (SiteScan) provides data on real-time capacity of physical infrastructure to CMDB CMDB maps relationships between facility equipment and managed objects in the IT domain, in this case, individual racks Aperture provides the user interface to display capacity mapped to racks and locations within racks
Function: IBM Director sends power usage data reported by the servers to Aperture, which maps this data onto racks, PDUs, and UPS SiteScan sends data from the facility equipment to Aperture Aperture displays results from multiple sources The user compares data from multiple sources and makes judgments about how to translate future IT requirements into power and cooling needs based on historical data The user add components to the data center to create a scenario and project future requirements
Adaptive power systems can scale for capacity and be configured to meet changing availability requirements. On the left, we have a single UPS. We can add an additional UPS. I can take the by-pass out of this module and put it in a separate piece of gear. And I can go up to a 2N or 2N+1 system. And here maybe I'll have two buses. Or I can add redundancy on those buses. So in terms of tiers, we start with a basic UPS, add a redundant UPS, add some gear and make it concurrently maintainable, and then go to full Tier Four, fault-tolerant UPS system. Scalability wise, I can take that 80 kVA UPS and scale to 100, to 120 kVA. I can scale it and parallel it, or just parallel it as is. So that's what we're doing with UPS technology, especially at 200 kVA systems and below.
Strategies for Finding and Unlocking Hidden Power Capacity in Your Data Center Infrastructure - Presentation Transcript
Strategies for Finding and Unlocking the Hidden Capacity in Your Data Center Infrastructure
Peter A. Panfil
Vice President and General Manager Liebert AC Power
Emerson Network Power
Strategies for Finding and Unlocking the Hidden Capacity in Your Data Center Infrastructure
Sizing data center power and cooling systems can feel like buying shoes for a fast-growing teenager: choose the size that fits today and you’ll be replacing a perfectly good pair of shoes in two months.
Fortunately, data center power and cooling systems are proving to be surprisingly adaptable. This session will help you determine how much “flex” exists within your data center infrastructure. We’ll show you how to assess the hidden capacity in your power and cooling systems and review strategies for unlocking this hidden capacity.
Whether you’re evaluating if your current facility can carry you into the future, or planning a new facility, this session will give you new insight into sizing – and growing – power and cooling capacity.
Agenda
Market dynamics
Assessing power and cooling capacities
Infrastructure management: Real-time visibility into capacity
Unlocking capacity by enhancing energy efficiency
Sizing power and cooling equipment for changing capacities
Power and cooling solutions for unpredictable capacity growth
Summary
Market Dynamics
Data Center Environment Key Trends From Fall 2005 to Today *Data Center Users’ Group Survey
Data Center Environment Key Trends From Fall 2005 To Today *Data Center Users’ Group Survey
New containment systems Liebert NX and NXL UPS, MPX Rack PDU
Liebert DS with Digital Scroll and EC fans New Liebert CRR
Liebert XD, EC fans, Digital Scroll Liebert NX and NXL UPS TP1 rated PDU transformers
Infrastructure Management – managing all the assets in the Data Center w/Aperture
Liebert DS UPS with Intelligent Eco Mode
Bundled solutions offerings
Liebert XD – 100% sensible, Digital Scroll with EC fan
Assessing power and cooling capacities
Design audit
Inventory of data center equipment
Standardization of maintenance procedures to comply with IEEE/NETA standards and manufacturers’ recommendations
Standardization of reliability processes i.e. power quality, disaster recovery and root cause, short circuit & coordination
Verification of accurate one-line diagrams per NFPA 70E
Evaluation of redundancy of critical systems
Creates a baseline for subsequent audit and maintenance activities
Load bank testing
Scope of Work
Application of a full load for a full 2-hour period
If applicable, building load shall be permitted to serve as part or total load – supplemented by load bank of sufficient size to equal 100 percent of nameplate kW rating of the EPS
Exercise cooling system
Accumulated carbon deposits burned off, if applicable
Removal of unburned fuel / oil
Benefits
Confirms generator output of specified kW
Operational assurance
Facilitates capacity expansion
Regulatory compliance
NFPA 110:6-4.2 “…emission standards”
Electrical assessment
Perform a single point of failure analysis to identify critical failure points in your power infrastructure
Determine capacity of all switchgear from the main to mission-critical PDUs
Determine current being drawn through all UPS equipment and breakers from the main to mission-critical PDUs
Perform analysis comparing measured current and power rating for all breakers from the main to mission-critical PDUs as well as any imbalances; note any areas of concern
Determine kW and KVA loading on each UPS and compare to rating of UPS
Evaluate the rated capacity of each generator versus UPS rated capacity ratings and note if generator full load rating is <150% of UPS rating
Determine load per rack/PDU
Computational fluid dynamics
Demonstrate the air flow characteristics of a raised floor
Better understand why hot spots are present
See effects of under floor obstructions on air flow
View heat-related risks in your facility
To view this presentation in its entirety, visit: http://w.on24.com/r.htm?e=135505&s=1&k=B64D9D4FE238521C32C282319625B6F1&partnerref=eTV
What is data center infrastructure management?
Data centers consist of multiple interrelated subsystems
Can be overwhelmingly complex for any but the smallest facilities
Objective is to deliver services at a targeted service level
Service Level Agreement (SLA) implies targets for availability and performance
Management of a large data center to the SLA at optimum cost can become intractable
One approach is to break down the task into smaller, manageable domains
The Data Center Physical Infrastructure (servers, storage, rack space) and the Critical Facilities (power, cooling) each comprise multiple domains
There is an opportunity to bridge the gap between the IT Physical Infrastructure, Critical Facilities and Data Center Service Management to optimize the data center
Scenario 1- Capacity view Facility IT SiteScan Aperture VISTA Deploy hardware without exceeding power, space, or cooling capacity VISTA shows available capacity for a proposed change SiteScan provides real-time data on power and cooling capacity
Scenario 2- Capacity planning Facility IT SiteScan IT Management Application Aperture VISTA Assess available capacity and needs for future, and plan required power and cooling capacity upgrades VISTA displays past and projected capacity requirements SiteScan provides real-time and historical usage data IT management provides IT asset utilization data
Bridging IT and facilities
Critical infrastructure monitoring
Provides visibility into current state
Supports analysis and planning
Data center service management
Controlled procedures for moves, adds and changes
Accurate, current view of data center configuration
Manages dependencies between Critical Infrastructure and IT Physical Infrastructure
Data center infrastructure management
Merges monitoring and management across domains
Delivers holistic services at a targeted service level
Provides actionable reporting on availability and performance
Unlocking capacity by enhancing energy efficiency
Emerson Network Power presents Energy Logic
Emerson Network Power approach to reducing data center energy consumption
Sequential roadmap that starts with IT equipment and moves through to support infrastructure
Emphasis is on cascade of savings
Based on research and modeling
Provides quantified savings and an estimated ROI
Frees up power, cooling and space capacity without compromising availability or flexibility
The ‘Cascade’ effect 1 Watt saved at the server component level results in cumulative savings of about 2.84 Watts in total consumption
Energy Logic: Cascade savings strategies
Total Energy Logic savings with all 10 strategies applied
Unoptimized data center layout
Optimized data center layout 65% space freed up from optimization from 5,000 sq. ft. to 1,768 sq. ft.
Address space, power and cooling constraints
Sizing power and cooling equipment for changing capacities
Considerations for sizing power
Set an initial density target – either watts per sq ft or kW per rack
A good starting point is kW per rack kW per rack x10 is approximately the watts/sq ft req’d 12kW per rack results in 120 watts/sq ft
Another method is using floor tiles 3500W per floor tile equates to about 90W per sq ft 3500W per floor tile equates to 1 ton of cooling per floor tile 3500W per floor tile equates to between 6 and 8 kW per rack
Size the incoming feed for growth – 2x is a good start
Power system architecture
Eliminate single points of failure and improve online maintainability
Investigate alternate high availability bus and dist configurations
Consider scalable power (and cooling solutions) that can easily keep up with unpredictable growth
Eliminate Single Points of Failure and Improve Online Maintainability Electrical Dist. Panel Electrical Dist. Panel Rack 4 Electrical Dist. Panel Rack 1 Rack 2 Rack 3 = Single Point of Failure Eliminated
Dual bus redundant module UPS, with maintenance bypass
Redundant electrical distribution
Smart rack PDUs (eliminates excess cabling under the floor and improves air flow)
Dual power supplies per server
UPS A1 UPS A2 UPS B1 UPS B2
High availability power configurations Catcher Dual Bus Does not require complex switchgear STS does the power tie Maximum Loading (N-1)/N For 4x1000 kVA=3000 kVA Max Load Dual Corded Dual Bus Requires custom switchgear for power tie Maximum Loading N/2 For 4x1000 kVA=2000 kVA Max Load UPS 1 UPS 2 PDU PDU STS STS UPS 3 UPS 4 PDU PDU STS STS Interleaved Dual Bus Does not require complex switchgear STS does the power tie Maximum Loading N/2 For 4x1000 kVA=2000 kVA Max Load UPS 1 UPS 2 UPS 3 UPS 4 PDU PDU PDU PDU STS STS STS STS UPS 1 UPS 2 UPS 3 Catcher STS STS STS PDU PDU PDU
IT loads have a large variation in cooling and airflow requirements
Virtualization, power management, new equipment
Need to match cooling capacity with the IT load
Eliminates over cooling and improves cooling efficiency with reduced cycling
Use optimal set points
Proper cold aisle temperature – adjust room set point (68°F to 70°F)
Raise the chilled water temperature above 45°F
Review ASHRAE guidelines
Consider a thermal assessment to help jump start the process
Baseline strategies for cooling efficiency: Seal the data center environment
Cooling can be lost through floors, walls and ceilings
Keep doors closed at all times
Use a vapor seal to isolate the data center atmosphere
Baseline strategies for cooling efficiency: Optimize airflow
Rack arrangement
Hot-aisle/cold-aisle
Place CRAC units perpendicular to hot aisles
Baseline strategies for cooling efficiency: Optimize airflow
Cable management
Overhead cabling
Expansion channels
Bring power closer to equipment
Increase voltage of IT equipment
Air containment
Perforated tiles should only be used in cold aisles
Use blanking panels to fill open spaces in racks
Use cabling grommets to fill open spaces around cables
Power solutions for unpredictable capacity growth
Unpredictable growth requires an adaptive architecture Scale for Capacity 80 kVA 40 kVA 60 kVA + Concurrently Maintainable Data Center Fault-Tolerant Data Center Redundant- Component Data Center S+S Dual Bus N+1 Centralized Bypass 1+N Distributed Bypass 1+1 Redundancy Configure for Availability Or Capacity
Power scalability options protect initial investment Add modules to a Fault-Tolerant Configuration Add modules to a Redundant-Component Configuration Add capacity to installed modules 100% Initial Capacity 150% Potential Capacity Capacity Capacity Redundancy + Future Capacity or Availability Expansion Future Expansion Future Expansion Future Expansion
The ultimate in scalability
Imagine a growing family buys a five bedroom home for the price of a three bedroom home
When they need the space, they obtain the keys to the additional rooms
Softscale technology makes it possible
Enabled by advances in UPS design that optimizes the UPS efficiency curve, allowing allows the UPS to operate with the same high efficiency at 50 percent utilization as it does at 100 percent utilization
Allows smaller data centers to take advantage of the higher reliability and lower cost per kilowatt of a large UPS compared to a smaller UPS
Brings availability, flexibility, and efficiency to medium-sized data centers
The Liebert NX with Softscale
True online, double-conversion UPS provides protection against the full range of power irregularities
Allows paralleling of UPS modules for capacity or redundancy
Highly efficient during normal operation and in Eco-mode, saving energy dollars
Provides a cost-effective growth solution with Softscale technology
Increased capacity via phone
Purchase Softscale upgrade
Liebert representative visits the site to ensure proper wiring and breaker sizing
Customer Engineer visits the site and uses a software key to quickly and easily increase UPS output capacity
Grow your UPS capacity from 40 to 60 or 80kVA, or 80 to 100 or 120kVA without adding hardware
Capacity
System growth
Capacity growth achieved through Softscale and paralleling
Growth through Softscale technology
40kVA -> 60kVA -> 80kVA
80kVA -> 100kA -> 120kVA
Growth through system paralleling
Parallel up to 3 modules for capacity + 1 for redundancy
80kVA + 80kVA + 80kVA = 240kVA capacity
80kVA + 80kVA + 80kVA +80kVA = 240kVA redundant
40 kVa Module 80 kVa Module Enabled by Softscale
Cooling solutions for unpredictable capacity growth
Liebert XD System: A flexible solution to high heat densities
Offers floor-mount, floor space saving rack-mount and ceiling-mount cooling module configurations
Can cool more than 30 kW per rack
Offers multiple configurations
Pumped refrigerant-based cooling modules
Liebert XDH
Liebert XDO
Liebert XDV
Pumped refrigerant-based pumping and chiller units
Liebert XDC
Liebert XDP
Water-based cooling modules and racks
Liebert XDK-W
Liebert XDR-W
Water-based pumping unit
Liebert XDP-W
“ Plug and play” expansion offers flexible growth plan
Requires little or no floor space
Complements Liebert precision cooling units
Allows adaptive and scalable expansion (“pay as you grow”) without interruption of cooling operations
Provides models to suit data center needs, mounting on, above or between the racks
Provides an excellent solution for spot and zone cooling of high heat density equipment
Liebert XDH Liebert XDO Liebert XDV
Liebert XD extreme density cooling solves XD heat loads XDV 10kW XDO 20kW CRAC 5-6kW XDH 20 & 30kW Up to 40kW per rack
Summary
Assess your environment to understand opportunities and constraints
Leverage infrastructure management to monitor and manage domains
Enhance energy efficiency to free up capacity
Properly size power and cooling equipment for changing capacities
Consider scalable power and cooling solutions that can easily keep up with unpredictable growth
Time Warner Cable
Case study, approx. 10 slides
Questions?
Contact Information:
Peter A. Panfil 975 Pittsburgh Drive Delaware, OH 43015 Office: 740-833-8665 [email_address]
Nearly 64 percent of data center managers expect to more
Nearly 64 percent of data center managers expect to run out of data center power capacity by 2011, but amidst free-falling IT budgets, many lack the resources to keep up with future demand. Fortunately, there are cost-effective measures organizations can take to optimize and increase capacity in the power systems they already own. This presentation from Emerson Network Power's Business Innovators webcast series demonstrates strategies for discovering and unlocking the capacity in your data center's power infrastructure.
For more information, visit: http://www.Liebert.com less
0 comments
Post a comment