Citywide Transit Integration in a Large City: The Case of Sao Paulo, Brazil - Presentation Transcript
CITYWIDE TRANSIT INTEGRATION IN A LARGE CITY: THE CASE OF SÃO PAULO, BRAZIL Dario Hidalgo, PhD Senior Transport Engineer EMBARQ, The WRI Center for Sustainable Transport TRB Annual Meeting Washington DC, January 2009
Sao Paulo is a growing megacity with increasing problems in mobility and quality of life Metropolitan Area: 39 Cities, 19 Million People City of Sao Paulo: 10.4 Million (6% of Brazil) Source: Sao Paulo Municipality
High public transport share, but was declining
Total Trips ~ 30 Million (2001)
Public Transport Share
of Motorized Trips
68%
61%
56%
2001 51%
Source: Municipality of Sao Paulo
Mega challenges in congestion, air quality, safety and security, energy consumption and GHG emissions Photos: Municipality of Sao Paulo
The city is transforming radial/dispersed transit into an integrated system Source: Sao Paulo Municipality
This is resulting in a positive shift in modal share trends Percent Motorized Trips Graph: Sao Paulo Municipality
São Paulo Integrated System (formerly Interligado)
Bus Priority Treatments (BRT)
Totally segregated busway (Expresso Tiradentes)
Median busways (Passa-Rapido)
Preferential buslanes (Via Livre)
Integration terminals and transfer stations; bus stops
Fleet renovation
New concession contracts by areas
Inclusion of informal operators
Single Fare, using electronic fare collection system
ITS: Control and User Information
1200 km de serviço estrutural 3300 km de serviço local Source: Sao Paulo Municipality, 2004
Sao Paulo reform is way beyond recent BRT Experiences in Developing Cities Single Corridor Several Corridors Feeder Routes City Wide Route Reorganization Non Integrated Integrated Metrobús – Mexico BRT – Beijing TransMilenio - Bogotá Metrovía - Guayaquil Jakarta Quito (Trole, Ecovía, North) Transantiago Interligado – Sao Paulo Megabús - Pereira RIT - Curitiba Metrobus - Istanbul
350,000 passengers per day expected when completed.
Diesel-electric hybrid buses (15 m) and articulated buses.
Initial operations of the first section (8 km) started in March 2007
Photo: SPTrans
Median Busways (Passa-Rapido)
Overhaul and expansion
Open operation, buses can feed in and out from the busway.
Bus stops on the left hand side
Where median busways are not possible, pperation is on the curb side (buses have doors on both sides)
Enforcement with closed circuit TV cameras
Thirty one corridors, 321 km planned, 104 Km completed
Preferential bus lanes (“Operação Via Livre”)
Curbside lanes with horizontal and vertical road markings and special traffic signals
30 corridors, 204 km planned
Terminals
Enclosed paid areas with amenities (restrooms, stores)
Operated under concession contracts.
Fixed amount per bus serving the terminal
Billboards and dynamic advertisement
Newsstands and coffee-shops.
Plan includes 32 terminals; 14 of them implemented (Many existing terminals required only overhaul)
Transfer stations
328 transfer stations planned, 25 completed in the 2001-2004 period
Bus stops
12 types with sizes between 4m of length and 1.8 m width to 38 m of length and 3.5 m width
17,000 bus stops with an average spacing of 300m in the local network and 500 m in the structural network.
Fleet renewal
Diesel Euro II, III and alternative technologies
13,711 low-entry vehicles (14,903 currently)
Articulated 1,073
Padron 5,599
Conventional 2,423
Microbus 3,063
Minibus 1,553
Buses in the structural subsystem have doors on both sides
Cooperatives of self-employed van operators were required to acquire new minibuses
Fare Integration
Smart card ticketing
Time Based Fare - Free transfers within 3 hours of the first validation
Access to 22 cities (out of 39 in Metropolitan Area) with one single payment
Flat fare ~1.05 dollar/trip
Control system Source: Sao Paulo Municipality
Public Investment Source: Sao Paulo Municipality, Exchange rate 2.85 brazilian reales per US dollar (January 2004). 1/ Formerly named Paulistão ad Fura-Fila. Initial operations started in March 2007 2/ Includes infrastructure built before 2001 R$ 140 million 937,34 496,38 440,97 2 Total 80,52 48,24 32,28 Monitoring and Control 29,29 22,01 7,28 203,7 km 126,0 km 77,7 km Via-Livre (30 corridors – curbside) 237,89 79,60 158,6 2 31,8 km 31,8 km Expresso Tiradentes 1 (Fully Segregated) 328,59 210,76 117,83 320,7 km 226,1 km 94,6 km Passa-Rápido (31 corridors – median) 34,21 31,58 2,63 328 303 25 Transfer Stations 164,19 104,50 59,69 32 18 14 Terminal Facilities 62,66 62,66 Electronic Fare Collection Sys tem Total 2005-2008 2001- 2004 Total 2005-2008 2001- 2004 Component USD Million Units
Main Impact – Increase in Boardings and Linked Trips
Dialogue and information. Creation of the Municipal Council of Transport and Traffic, with broad representation.
Negotiation process with the bus operators’ representative.
Opposition from transport industry leaders
Regulations were changed to allow several components: integrated fare collection system; conditions for the transport concessions, integration of informal operators, among others
Regulatory Regime
Initially a municipal project, expanded later to the state and other municipalities
Coordination with other levels of government
High level coordination group (Secretary of Transport, Director of SPTrans and Director of CET).
Planning and implementation groups under a single coordination authority
Designation of several professionals of the municipal agencies to the project
Information and discussion with the community; non-intrusive design
Neighborhoods opposed busways
Use of existing right of ways, low cost solutions for bus stops, integration points and terminals;
Loan from the Brazilian Development Bank BNDES was obtained for investments
Limited funding availability
Participation of a competent team of professionals
The route reorganization approach was fairly straightforward: segmentation of services (local, structural) and elimination of redundancies. The new network is rather complex
Large scale reorganization
Small operators incorporated into the new scheme through cooperatives under contract
Opposition from van operators (Peruveiros) Solution/Mitigation Barrier
Launch of Integration Scheme
Problems
Distribution of credits was difficult
Many facilities were inadequate – small bus stops and transfer stations cause bus queuing and delays
Via Livre corridors (curbside) were invaded (delivery trucks, taxi cabs)
Incomplete user information on routes and frequencies (maps were difficult to understand)
Delays in infrastructure deployment, including those caused by lawsuits filed by neighbors’ organizations
Financial difficulties for small operators (cooperatives)
Design Issues
Busways are open; no real operational control on the supply level (spatial and temporal)
Reliability of the operation is variable and limited capacity of the bus stops often leads to spillovers and reduced commercial speeds
Soft segregation; control with CCTV cameras does not seem enough to deter bus lanes invasion
Photo: Sao Paulo Municipality
Perceived Quality of Service for Municipal Buses remains low Source: ANTP Main User Concerns Emission Levels (99%) Congestion (88%) Long waiting times (82%) Long travel times (80%)
Financial Stress Revenues Costs Source, Souza, A, ANTP/BNDS 2007
Recommended Improvements*
Completion of priority corridors, transfer stations, control and monitoring devices
Enforcement of contracts
Technical definition of fares to avoid financial stress
Include high capacity BRT applications to improve commercial speeds on main corridors:
Strong longitudinal segregation of the bus lanes
Increased prepayment (enclosed stations, and paid areas);
Continuous adjustment of services taking advantage of the intrinsic flexibility of buses
Inclusion of emergency response systems. ITS applied for oversight, but not to perform real time operational actions
* Many already being considered and implemented by the municipality
Lessons Learned
The São Paulo experience can be considered a good practice in implementation of transport reform in developing cities:
Transit services became more attractive as user cost and travel time was reduced
Fleet was renewed and several operational inefficiencies were trimmed down
Integration efforts continue, including coordination with the Metro and regional rail and bus
Key elements of success were political commitment, coordinated effort of several agencies, technical preparation, and inclusion of existing bus companies as well as informal operators.
Several aspects need further attention to improve service quality and user perception. Effort is underway.
São Paulo vs. Santiago
Advantages:
Service changes were introduced gradually (as corridors and terminals became available)
Existing operators (formal and informal) were included
Integration with Metro and regional rail occurred later in the process
Disadvantages:
Transantiago was able to capture the benefits of a more open competitive tendering for bus operations and introduced stronger controls on the private operators
São Paulo vs. Bogot á
Advantages
São Paulo achieved a citywide integration, Bogota only partial (20% of the public transport trips)
Bogotá's transit provision still dominated by an inefficient operational scheme (“Guerra del Centavo” 80% of the trips )
TransMilenio corridors exhibit much higher capacity and commercial speeds (except Expresso Tiradentes)
0 comments
Post a comment