• Like
  • Save
GMRR Bridge #114 Emergency Irene Repair
Upcoming SlideShare
Loading in...5
×
 

GMRR Bridge #114 Emergency Irene Repair

on

  • 238 views

ECI Rail Constructors repairs a dangerously listing bridge after Tropical Storm Irene floods Vermont.

ECI Rail Constructors repairs a dangerously listing bridge after Tropical Storm Irene floods Vermont.

Statistics

Views

Total Views
238
Views on SlideShare
238
Embed Views
0

Actions

Likes
0
Downloads
2
Comments
0

0 Embeds 0

No embeds

Accessibility

Categories

Upload Details

Uploaded via as Adobe PDF

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    GMRR Bridge #114 Emergency Irene Repair GMRR Bridge #114 Emergency Irene Repair Presentation Transcript

    • GMRR Bridge #114Tropical Storm Irene Emergency Repairs Chester, Vermont ECI Rail Constructors, Inc. September 2011 www.eci-rail.com
    • Tropical Storm Irene
    • NWS Bulletin for Irene 5:00 PM on August 28, 2011• RAINFALL...IRENE IS EXPECTED TO PRODUCE TOTAL RAINFALL ACCUMULATIONS OF 4 TO 6 INCHES...WITH ISOLATED MAXIMUM AMOUNTS OF 8 INCHES... FROM NORTHEASTERN NEW YORK STATE NORTHEASTWARD THROUGH THE NORTHERN PORTION OF NEW ENGLAND. THESE RAINS...COMBINED WITH HEAVY RAINS OVER THE PAST FEW WEEKS...COULD CAUSE WIDESPREAD FLOODING AND LIFE-THREATENING FLASH FLOODS.
    • Initial ECI Site VisitTuesday – August 31
    • Mobilization & Access Construction Wed-Sat: Sept 1 to Sept 3
    • Mobilize CranemastersSaturday – September 3
    • Setup CranesSaturday – September 3
    • Bridge Brought to Vertical & Secured Sunday – September 4
    • Stabilize West Abutment Monday - September 5
    • Install Pedestal at NW Bearing Tuesday – September 6
    • Secure Work from Tropical Storm Lee Wednesday – September 7
    • Test Borings at East Abutment Thursday – September 8
    • Start Driving Pipe PilesThursday – September 8
    • Testing & Driving Pipe Piles Friday – September 9
    • 13.75-in-OD x 0.707-inch wall Pipe Pile Splicing – 2 hrs/joint
    • Final Driving of Pipe PilesSaturday – September 10
    • Shotcreting of West Abutment Sunday – September 10
    • Sheet Pile Wall to Extend Damaged West Abut Sunday - September 10
    • Temporary Bearing Pedestal Sunday - September 11
    • Setting Bridge on Temporary Bearing Supports Sunday - September 11
    • Pouring Concrete Backwall & Abut Extension Monday – September 11
    • Final Welding & Bracing of Piles & Pedestal Tuesday – September 13
    • Rebuilding Approach Embankment Tuesday – September 13
    • West Approach Track Reconstruction Tuesday – September 13
    • Team PhotoTuesday – September 13
    • First TrainWednesday – September 14