SlideShare a Scribd company logo
1 of 20
Download to read offline
Welcome to the Online Consultation
 KEELE STREET TO JANE STREET SECTION
 BLACK CREEK MAINTENANCE & STORAGE FACILITY
 ADDENDUM TO THE ENVIRONMENTAL PROJECT REPORT

 December 12, 2012 – January 4, 2013




December 12, 2012   Western Alignment and MSF Update   1
Purpose of the Online Consultation
 Since the approval of the Environmental Project Report (EPR) for The Eglinton Crosstown Light
 Rail Transit (LRT) Project by the Minister of the Environment in 2010, the Province of Ontario
 divided the Project into two implementation phases in order to meet funding limitations. The two
 phases are:
   • Phase 1 covers the 19 kilometre section from Mt. Dennis neighbourhood to Kennedy
     Station which will be implemented immediately; and
   • Phase 2 covers the 14 kilometre section from Pearson International Airport to the Mt.
     Dennis neighbourhood which will be deferred until further notice.
 This phasing has resulted in changes to the project in the section from Jane Street to West
 Launch Shaft. In addition, the Project now includes as part of Phase 1, the Black Creek
 Maintenance and Storage Facility (MSF) that was not assessed in the original EPR. Finally,
 refinements in the operating plan for the LRT and a desire to provide a connection to future GO
 Train service at Mt. Dennis have resulted in changes to the Project.
 The purpose of the online consultation is to receive your input regarding the changes to the
 Project and the Black Creek Maintenance and Storage Facility.
 More details on the Black Creek Maintenance and Storage Facility and the changes to the
 project appear on the following panels.
December 12, 2012                 Western Alignment and MSF Update                             2
Study Areas




December 12, 2012   Western Alignment and MSF Update   3
Why an Addendum to the EPR is Required?
The approved Project in the 2010 EPR included a street-level LRT alignment within the centre of
Eglinton Avenue between Jane Street to east of Black Creek Drive, with surface stops at Jane
Street, Weston Road and Black Creek Drive. As noted earlier, the MSF was not assessed at that
time.
The recent changes to the Project between Jane Street and West Launch Shaft include:
• An off-street (elevated) route north of Eglinton Avenue with a bridge over Black Creek Drive to
  avoid traffic interference with LRT vehicles accessing the MSF;
• An underground Mt. Dennis Station under the railway corridor, along with direct passenger
  connection to future GO rail station and Passenger Pick up and Drop off;
• A 15-bay bus terminal to provide passenger transfers between TTC bus, LRT and GO rail;
• An underground alignment from the Mt. Dennis Station to the Eglinton Flats area with a
  transition to surface LRT just east of Jane Street and a surface stop on the west side of Jane
  Street; and
• The previously proposed Black Creek Stop is now removed due to technical constraints.
An Addendum to the EPR is required to assess these changes and to assess the effects of the
Black Creek MSF

December 12, 2012                  Western Alignment and MSF Update                                 4
2012 − New Proposed Plan/Profile
   An off street LRT alignment north of Eglinton Avenue with an underground stop at Mt.
   Dennis, underground alignment west of Mt. Dennis and a surface stop at Jane Street.




 See link below to download the PDF of the 2012
            New Proposed Plan/Profile




December 12, 2012                 Western Alignment and MSF Update                        5
Jane Street / Eglinton Flats *
                                                       Key Project Elements:
                                                        • Jane Stop is maintained;
                                                        • U-Turns on Eglinton Avenue
                                                          are retained;
                                                        • Transition from surface to
 Original -2010                                           underground LRT portal
                                                          located east of Jane Street




                                                         *- Part of Phase 2
 New - 2012                                              Implementation
December 12, 2012   Western Alignment and MSF Update                            6
Mt. Dennis Neighbourhood
                                                       Key Project Elements:
                                                        • Underground alignment
                                                          between portal and Mt.
                                                          Dennis Station using cut
                                                          and cover construction,
                                                          road widening is no longer
                                                          required;
                                                        • Properties along north side
                                                          of Eglinton Avenue, west of
                                                          Weston Road are no longer
                                                          required;
                                                        • Limit of Phase 1
                                                          implementation is Weston
                                                          Road; and
                                                        • Weston Road stop has
                                                          been shifted east.




December 12, 2012   Western Alignment and MSF Update                             7
Weston Road to Black Creek Drive
                                                       Key Project Elements:
                                                        • Underground Mt. Dennis
                                                          Station using cut and cover
                                                          construction;
                                                        • Property required from Bank
                                                          of Nova Scotia, Daycare and
                                                          Keelsdale Drive;
                                                        • Pedestrian connections for
                                                          future GO rail station;
                                                        • Passenger Pick Up and Drop
                                                          Off (PPUDO);
                                                        • 15 bay bus terminal with
                                                          new bus only signalized
                                                          intersection on Eglinton
                                                          Avenue;
                                                        • Kodak Building to be
                                                          retained; and
                                                        • Elevated LRT structure over
                                                          Black Creek Drive.
December 12, 2012   Western Alignment and MSF Update                             8
Black Creek Drive to West Launch Shaft
                                                       Key Project Elements:
                                                        • Elevated LRT structure over
                                                          Black Creek Drive and Black
                                                          Creek;
                                                        • Eglinton Avenue relocated to
                                                          the south, east of Black
                                                          Creek Drive;
                                                        • LRT ties into underground
                                                          alignment at West Launch
                                                          Shaft;
                                                        • Black Creek Stop has been
                                                          removed; and
                                                        • Property is required along
                                                          the north side of Eglinton
                                                          Avenue, east of Black Creek
                                                          Drive for elevated structure.




December 12, 2012   Western Alignment and MSF Update                             9
Mt. Dennis Station



                                                       Artistic Rendering of Mt. Dennis Station




December 12, 2012   Western Alignment and MSF Update                                     10
Maintenance and Storage Facility
                                                       Key Project Elements:
                                                        • Ultimate storage yard
                                                          capacity of 162 vehicles;
                                                        • Facilities for Maintenance
                                                          of vehicles;
                                                        • Office facilities and
                                                          employee parking; and
                                                        • Facilities for Maintenance
                                                          of Way vehicles and staff.




December 12, 2012   Western Alignment and MSF Update                           11
Effect on Adjacent Studies
There are two concurrent studies that are influenced by the proposed changes to
the Eglinton LRT within the study area.
                                                                               The Eglinton Connects Study being undertaken by the City of
                                                                               Toronto in partnership with Metrolinx is planning to develop an
                                                                               urban design vision for the entire Eglinton Corridor.




   Study area showing 800m radius from the centre of the mobility hub
   located at the proposed station area.


The Mount Dennis Mobility Hub Study
being undertaken by Metrolinx is planning
for seamless mobility around the station,
maximize connections to transit for the
surrounding neighbourhoods, create an
attractive public realm and leverage transit
investment for future investment in the
community .
December 12, 2012                                                       Western Alignment and MSF Update                                  12
Potential Impacts of the Changes
• Property: Acquisition of 4 properties is required, this is a
  reduction from the 37 properties identified in the 2010 report.
• Parks: The south edge of Coronation Park encroached upon
  by the elevated structure.
• Vegetation: Additional vegetation will be removed by the
  project. Permits and approvals will be obtained through City of
  Toronto and TRCA.
• Utilities: Overhead utilities along the north side of Eglinton
  Avenue will require relocation.
• Noise and Vibration: Meets provincial criteria

December 12, 2012       Western Alignment and MSF Update           13
Potential Impacts of the Changes
• Waterways: Widening of the Eglinton Avenue Road bridge at
  Black Creek will be required. The new LRT elevated structure
  over Black Creek will span the entire waterway. No impact to
  fish habitat is anticipated.
• Contaminated Soils and Groundwater: Contaminated soils
  and groundwater will be managed in accordance with
  provincial legislation and regulations.
• Cultural Heritage: Kodak Building #9 and its heritage
  features will be maintained. Bank of Nova Scotia Building to
  be removed and documented.
• Archaeology: No impact to archaeological resources.
December 12, 2012      Western Alignment and MSF Update          14
Mitigation of Potential Impacts During Construction
Measures will be implemented during construction to avoid, minimize or mitigate adverse
environmental impacts including:
 • Erosion and sedimentation control;
 • Minimize release of dust and other airborne pollutants and mud and litter;
 • Reinstatement of temporary work sites following construction;
 • Development and implementation of traffic management plans;
 • Installation of decking at cut-and-cover excavations;
 • Restriction of truck haul of construction materials and equipment to major arterial roads;
 • Noise and vibration control;
 • Construction staging and sequencing to mitigate the potential impacts on local businesses
   to the extent possible; and
 • Ongoing management and monitoring of construction activities.



December 12, 2012                 Western Alignment and MSF Update                       15
Mitigation of Potential Impacts of LRT
Operations and Maintenance
Measures will be implemented during LRT operations and
maintenance to avoid, minimize or mitigate adverse effects including:
• Stormwater run-off from will be treated in accordance with
  applicable City of Toronto, Toronto and Region Conservation
  Authority (TRCA) and Ministry of the Environment (MOE)
  requirements;
• Noise generated by LRT vehicles and by bus terminal operations
  will be attenuated, if required, to meet MOE standards;
• Vibration generated by LRT vehicles and by bus terminal
  operations will be attenuated, if required, to meet MOE standards;
• Air emissions generated by bus terminal operations will be
  attenuated, if required, to meet MOE standards; and
• The potential for traction power stray current will be controlled using
  isolated and insulated power supplies.
December 12, 2012                Western Alignment and MSF Update           16
EPR Consultation Process and Next Steps
                                    We are Here




December 12, 2012   Western Alignment and MSF Update   17
Commitments to Future Work
Metrolinx is proceeding with the delivery of the Eglinton LRT through Public Private
Partnership and Alternative Financing + Procurement (AFP).
Through this process Metrolinx is committed to:
• Continuing Public Consultation: Consult with the public, property owners and stakeholder
  agencies during the design of the LRT alignment, stops/ stations, bus terminals and
  ancillary facilities.
• Incorporate City of Toronto urban design criteria into the design of the LRT facilities.
• Construction Issues: Conduct further research, analysis and develop plans including :
    ― Noise, vibration and air emissions monitoring and mitigation
    ― Traffic, transit and pedestrian management strategies
    ― Utility and municipal services relocation plans
    ― Emergency response plans (Fire, Police and Emergency Medical Services)
    ― Vegetation restoration, edge management and streetscape plans
    ― Soil and groundwater management strategy
    ― Erosion and sedimentation control plan
December 12, 2012                Western Alignment and MSF Update                            18
Format for Feedback
• Please submit your feedback online at ww.thecrosstown.ca by January 4th, 2012.

• A consultation report will be posted online within 10 to 15 business days.




                                         19
Please Get in Touch With Us!
The Crosstown Team
                                                            Community Office Hours
Franca Di Giovanni,
Denise Jayawardene                                         Monday, Wednesday, Friday:
Mark Iogna                                                   9:00 a.m. – 5:00 p.m.
Nicole Di Carlo
                                                     Tuesday & Thursday: by appointment
E-mail: crosstown@metrolinx.com
Online: www.thecrosstown.ca
Tel: 416-782-8118
Visit our West Community Office
at 1848 Eglinton Avenue West
(at Dufferin)

                    THANK YOU FOR YOUR PARTICIPATION
December 12, 2012             Western Alignment and MSF Update                          20

More Related Content

More from Crosstown TO

Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfCrosstown TO
 

More from Crosstown TO (20)

Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
 

Recently uploaded

Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdfvaibhavkanaujia
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改yuu sss
 
Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in designnooreen17
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case StudySophia Viganò
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfneelspinoy
 
Untitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxUntitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxmapanig881
 
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10uasjlagroup
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back17lcow074
 
Iconic Global Solution - web design, Digital Marketing services
Iconic Global Solution - web design, Digital Marketing servicesIconic Global Solution - web design, Digital Marketing services
Iconic Global Solution - web design, Digital Marketing servicesIconic global solution
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一Fi L
 
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一Fi ss
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一F La
 
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一diploma 1
 
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree 毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree ttt fff
 
FiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfFiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfShivakumar Viswanathan
 
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services DubaiDubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubaikojalkojal131
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVAAnastasiya Kudinova
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024CristobalHeraud
 
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一D SSS
 
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...mrchrns005
 

Recently uploaded (20)

Passbook project document_april_21__.pdf
Passbook project document_april_21__.pdfPassbook project document_april_21__.pdf
Passbook project document_april_21__.pdf
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
 
Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in design
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case Study
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdf
 
Untitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxUntitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptx
 
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
CREATING A POSITIVE SCHOOL CULTURE CHAPTER 10
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back
 
Iconic Global Solution - web design, Digital Marketing services
Iconic Global Solution - web design, Digital Marketing servicesIconic Global Solution - web design, Digital Marketing services
Iconic Global Solution - web design, Digital Marketing services
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
 
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一
定制(CQU文凭证书)中央昆士兰大学毕业证成绩单原版一比一
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
 
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一
办理(麻省罗威尔毕业证书)美国麻省大学罗威尔校区毕业证成绩单原版一比一
 
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree 毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
毕业文凭制作#回国入职#diploma#degree澳洲弗林德斯大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
 
FiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfFiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdf
 
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services DubaiDubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
 
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
PORTAFOLIO   2024_  ANASTASIYA  KUDINOVAPORTAFOLIO   2024_  ANASTASIYA  KUDINOVA
PORTAFOLIO 2024_ ANASTASIYA KUDINOVA
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
 
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
 
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
Business research proposal mcdo.pptxBusiness research proposal mcdo.pptxBusin...
 

Keele Street to Jane Section and Black Creek Maintenance & Storage Facility Environmental Project Report Addendum Online Consultation

  • 1. Welcome to the Online Consultation KEELE STREET TO JANE STREET SECTION BLACK CREEK MAINTENANCE & STORAGE FACILITY ADDENDUM TO THE ENVIRONMENTAL PROJECT REPORT December 12, 2012 – January 4, 2013 December 12, 2012 Western Alignment and MSF Update 1
  • 2. Purpose of the Online Consultation Since the approval of the Environmental Project Report (EPR) for The Eglinton Crosstown Light Rail Transit (LRT) Project by the Minister of the Environment in 2010, the Province of Ontario divided the Project into two implementation phases in order to meet funding limitations. The two phases are: • Phase 1 covers the 19 kilometre section from Mt. Dennis neighbourhood to Kennedy Station which will be implemented immediately; and • Phase 2 covers the 14 kilometre section from Pearson International Airport to the Mt. Dennis neighbourhood which will be deferred until further notice. This phasing has resulted in changes to the project in the section from Jane Street to West Launch Shaft. In addition, the Project now includes as part of Phase 1, the Black Creek Maintenance and Storage Facility (MSF) that was not assessed in the original EPR. Finally, refinements in the operating plan for the LRT and a desire to provide a connection to future GO Train service at Mt. Dennis have resulted in changes to the Project. The purpose of the online consultation is to receive your input regarding the changes to the Project and the Black Creek Maintenance and Storage Facility. More details on the Black Creek Maintenance and Storage Facility and the changes to the project appear on the following panels. December 12, 2012 Western Alignment and MSF Update 2
  • 3. Study Areas December 12, 2012 Western Alignment and MSF Update 3
  • 4. Why an Addendum to the EPR is Required? The approved Project in the 2010 EPR included a street-level LRT alignment within the centre of Eglinton Avenue between Jane Street to east of Black Creek Drive, with surface stops at Jane Street, Weston Road and Black Creek Drive. As noted earlier, the MSF was not assessed at that time. The recent changes to the Project between Jane Street and West Launch Shaft include: • An off-street (elevated) route north of Eglinton Avenue with a bridge over Black Creek Drive to avoid traffic interference with LRT vehicles accessing the MSF; • An underground Mt. Dennis Station under the railway corridor, along with direct passenger connection to future GO rail station and Passenger Pick up and Drop off; • A 15-bay bus terminal to provide passenger transfers between TTC bus, LRT and GO rail; • An underground alignment from the Mt. Dennis Station to the Eglinton Flats area with a transition to surface LRT just east of Jane Street and a surface stop on the west side of Jane Street; and • The previously proposed Black Creek Stop is now removed due to technical constraints. An Addendum to the EPR is required to assess these changes and to assess the effects of the Black Creek MSF December 12, 2012 Western Alignment and MSF Update 4
  • 5. 2012 − New Proposed Plan/Profile An off street LRT alignment north of Eglinton Avenue with an underground stop at Mt. Dennis, underground alignment west of Mt. Dennis and a surface stop at Jane Street. See link below to download the PDF of the 2012 New Proposed Plan/Profile December 12, 2012 Western Alignment and MSF Update 5
  • 6. Jane Street / Eglinton Flats * Key Project Elements: • Jane Stop is maintained; • U-Turns on Eglinton Avenue are retained; • Transition from surface to Original -2010 underground LRT portal located east of Jane Street *- Part of Phase 2 New - 2012 Implementation December 12, 2012 Western Alignment and MSF Update 6
  • 7. Mt. Dennis Neighbourhood Key Project Elements: • Underground alignment between portal and Mt. Dennis Station using cut and cover construction, road widening is no longer required; • Properties along north side of Eglinton Avenue, west of Weston Road are no longer required; • Limit of Phase 1 implementation is Weston Road; and • Weston Road stop has been shifted east. December 12, 2012 Western Alignment and MSF Update 7
  • 8. Weston Road to Black Creek Drive Key Project Elements: • Underground Mt. Dennis Station using cut and cover construction; • Property required from Bank of Nova Scotia, Daycare and Keelsdale Drive; • Pedestrian connections for future GO rail station; • Passenger Pick Up and Drop Off (PPUDO); • 15 bay bus terminal with new bus only signalized intersection on Eglinton Avenue; • Kodak Building to be retained; and • Elevated LRT structure over Black Creek Drive. December 12, 2012 Western Alignment and MSF Update 8
  • 9. Black Creek Drive to West Launch Shaft Key Project Elements: • Elevated LRT structure over Black Creek Drive and Black Creek; • Eglinton Avenue relocated to the south, east of Black Creek Drive; • LRT ties into underground alignment at West Launch Shaft; • Black Creek Stop has been removed; and • Property is required along the north side of Eglinton Avenue, east of Black Creek Drive for elevated structure. December 12, 2012 Western Alignment and MSF Update 9
  • 10. Mt. Dennis Station Artistic Rendering of Mt. Dennis Station December 12, 2012 Western Alignment and MSF Update 10
  • 11. Maintenance and Storage Facility Key Project Elements: • Ultimate storage yard capacity of 162 vehicles; • Facilities for Maintenance of vehicles; • Office facilities and employee parking; and • Facilities for Maintenance of Way vehicles and staff. December 12, 2012 Western Alignment and MSF Update 11
  • 12. Effect on Adjacent Studies There are two concurrent studies that are influenced by the proposed changes to the Eglinton LRT within the study area. The Eglinton Connects Study being undertaken by the City of Toronto in partnership with Metrolinx is planning to develop an urban design vision for the entire Eglinton Corridor. Study area showing 800m radius from the centre of the mobility hub located at the proposed station area. The Mount Dennis Mobility Hub Study being undertaken by Metrolinx is planning for seamless mobility around the station, maximize connections to transit for the surrounding neighbourhoods, create an attractive public realm and leverage transit investment for future investment in the community . December 12, 2012 Western Alignment and MSF Update 12
  • 13. Potential Impacts of the Changes • Property: Acquisition of 4 properties is required, this is a reduction from the 37 properties identified in the 2010 report. • Parks: The south edge of Coronation Park encroached upon by the elevated structure. • Vegetation: Additional vegetation will be removed by the project. Permits and approvals will be obtained through City of Toronto and TRCA. • Utilities: Overhead utilities along the north side of Eglinton Avenue will require relocation. • Noise and Vibration: Meets provincial criteria December 12, 2012 Western Alignment and MSF Update 13
  • 14. Potential Impacts of the Changes • Waterways: Widening of the Eglinton Avenue Road bridge at Black Creek will be required. The new LRT elevated structure over Black Creek will span the entire waterway. No impact to fish habitat is anticipated. • Contaminated Soils and Groundwater: Contaminated soils and groundwater will be managed in accordance with provincial legislation and regulations. • Cultural Heritage: Kodak Building #9 and its heritage features will be maintained. Bank of Nova Scotia Building to be removed and documented. • Archaeology: No impact to archaeological resources. December 12, 2012 Western Alignment and MSF Update 14
  • 15. Mitigation of Potential Impacts During Construction Measures will be implemented during construction to avoid, minimize or mitigate adverse environmental impacts including: • Erosion and sedimentation control; • Minimize release of dust and other airborne pollutants and mud and litter; • Reinstatement of temporary work sites following construction; • Development and implementation of traffic management plans; • Installation of decking at cut-and-cover excavations; • Restriction of truck haul of construction materials and equipment to major arterial roads; • Noise and vibration control; • Construction staging and sequencing to mitigate the potential impacts on local businesses to the extent possible; and • Ongoing management and monitoring of construction activities. December 12, 2012 Western Alignment and MSF Update 15
  • 16. Mitigation of Potential Impacts of LRT Operations and Maintenance Measures will be implemented during LRT operations and maintenance to avoid, minimize or mitigate adverse effects including: • Stormwater run-off from will be treated in accordance with applicable City of Toronto, Toronto and Region Conservation Authority (TRCA) and Ministry of the Environment (MOE) requirements; • Noise generated by LRT vehicles and by bus terminal operations will be attenuated, if required, to meet MOE standards; • Vibration generated by LRT vehicles and by bus terminal operations will be attenuated, if required, to meet MOE standards; • Air emissions generated by bus terminal operations will be attenuated, if required, to meet MOE standards; and • The potential for traction power stray current will be controlled using isolated and insulated power supplies. December 12, 2012 Western Alignment and MSF Update 16
  • 17. EPR Consultation Process and Next Steps We are Here December 12, 2012 Western Alignment and MSF Update 17
  • 18. Commitments to Future Work Metrolinx is proceeding with the delivery of the Eglinton LRT through Public Private Partnership and Alternative Financing + Procurement (AFP). Through this process Metrolinx is committed to: • Continuing Public Consultation: Consult with the public, property owners and stakeholder agencies during the design of the LRT alignment, stops/ stations, bus terminals and ancillary facilities. • Incorporate City of Toronto urban design criteria into the design of the LRT facilities. • Construction Issues: Conduct further research, analysis and develop plans including : ― Noise, vibration and air emissions monitoring and mitigation ― Traffic, transit and pedestrian management strategies ― Utility and municipal services relocation plans ― Emergency response plans (Fire, Police and Emergency Medical Services) ― Vegetation restoration, edge management and streetscape plans ― Soil and groundwater management strategy ― Erosion and sedimentation control plan December 12, 2012 Western Alignment and MSF Update 18
  • 19. Format for Feedback • Please submit your feedback online at ww.thecrosstown.ca by January 4th, 2012. • A consultation report will be posted online within 10 to 15 business days. 19
  • 20. Please Get in Touch With Us! The Crosstown Team Community Office Hours Franca Di Giovanni, Denise Jayawardene Monday, Wednesday, Friday: Mark Iogna 9:00 a.m. – 5:00 p.m. Nicole Di Carlo Tuesday & Thursday: by appointment E-mail: crosstown@metrolinx.com Online: www.thecrosstown.ca Tel: 416-782-8118 Visit our West Community Office at 1848 Eglinton Avenue West (at Dufferin) THANK YOU FOR YOUR PARTICIPATION December 12, 2012 Western Alignment and MSF Update 20