Cosumnes CSD - Sheldon Place Park Conceptual Master Plan

  • 1,029 views
Published

 

Published in Art & Photos , Business , Travel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Be the first to comment
    Be the first to like this
No Downloads

Views

Total Views
1,029
On SlideShare
0
From Embeds
0
Number of Embeds
0

Actions

Shares
Downloads
8
Comments
0
Likes
0

Embeds 0

No embeds

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
    No notes for slide

Transcript

  • 1. PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 2. PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 3. PARK SITE WE ARE HERE
  • 4. FUNDING
    • PARK CONSTRUCTION
    • DEVELOPER/PARK IMPACT FEES
    • EASTERN ELK GROVE FINANCE PLAN
    • $710,000 CONSTRUCTION BUDGET
    • PARK MAINTENANCE
    • LANDSCAPE & LIGHTING ASSESSMENTS - $115/YEAR
    • MAINTENANCE OF 10 PARKS TOTALING 58 ACRES AND
    • 17 ACRES OF LANDSCAPE CORRIDORS
    PARK SITE B – SHELDON PLACE COMMUNITY WORKSHOP
  • 5. Why is it taking so long to build the rest of our park?!
  • 6. THE GOOD NEWS
    • The CSD has $710,000 of Park Impact Fees to build
    • Park Site B – Sheldon Place
  • 7.
    • Park development funds cannot be used for maintenance costs.
    • It would be fiscally irresponsible of the CSD to proceed with the
    • construction of a park that they cannot afford to maintain.
    THE NOT-SO-GOOD NEWS
    • The CSD does not yet own the park site.
    • Landscape and Lighting (L&L) assessments pay for park
    • maintenance. Current L&L assessments are not enough to
    • maintain Park Site B – Sheldon Place.
  • 8.
    • Proposition 218 was passed by the voters of California in 1996.
    • In the last 11 years, maintenance costs have risen at a rate that
    • has exceeded the CPI, typically 2 – 4%, and the District cannot
    • assume the maintenance of new parkland with the current
    • available funding.
    • The proposition prohibits raising assessments at a rate that
    • exceeds the CPI (Consumer Price Index) without a balloted vote.
    HOW DID THIS HAPPEN?
    • The assessment rate is 11 years old. Rates were determined prior
    • to build out of the benefit zone and before Sheldon Place was a
    • subdivision. There was no method for anticipating future parks.
  • 9. WHAT ARE OUR OPTIONS?
  • 10. OPTION #1 The ‘do nothing’ option - do not build the park.
  • 11. OPTION #2
    • The CSD is asking property owners in your area to vote on a new
    • park maintenance assessment.
    • Passing this measure would allow CSD design staff to proceed
    • with preparation of construction documents.
    • If passed, maintenance funding would be available for this park
    • and other parks in the area.
  • 12. PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
    • The Elk Grove West
    • Vineyard Park Assessment
    • will be $96 annually or
    • about $8 per month.
    • 51% of the returned ballots
    • must vote ‘yes’ on this
    • measure for passage.
    • Ballots arrived
    • May 1 and must be
    • returned by June 17
    • If this measure fails, the construction of Park Site B – Sheldon
    • Place will be postponed indefinitely.
  • 13. PARK SITE B – SHELDON PLACE 1.6 ACRES PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 14. PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 15.
    • CSD PARK DESIGN PRINCIPLES
    • These park design principles are taken from the CSD’s Draft Master Plan.
    • PARK SITE B – SHELDON PLACE IS DEFINED AS A LOCAL PARK.
    • SIZE – LOCAL PARKS GENERALLY RANGE IN SIZE FROM 1,500 S.F. TO 3
    • ACRES IN SIZE. THE PARK SITE IS 1.6 ACRES.
    • A LOCAL PARK TYPICALLY INCLUDES THE FOLLOWING AMENITIES:
      • SMALL PLAYGROUNDS TARGETED FOR AGES 2-5 AND 5-12
      • SOME SHADED PLAY ELEMENTS
      • SMALL SPORT COURTS
      • SMALL PICNIC AREA W/ SHELTER
      • SWINGS
      • BENCHES
      • LANDSCAPING
      • ADA COMPLIANT AMENITIES
    • LAND USAGE – 90% ACTIVE/10% PASSIVE
    • LIGHTING – SECURITY LIGHTING ONLY
    PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 16.
    • Community Meeting #1 is a workshop format to develop ideas for the
    • the design of the park.
      • April 16 th
      • No attendees
    PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN COMMUNITY OUTREACH PROCESS
    • Community Meeting #2 is a presentation format for staff to present a conceptual master plan based on ideas from the first meeting and CSD design principles.
      • CSD Staff have completed outreach for 12 parks in past four
      • years
      • CSD Planning staff includes 3 licensed Landscape Architects
      • with many years experience in designing parks
  • 17. PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 18. PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 19. Picnic Area DECOMPOSED GRANITE SURFACING DRINKING FOUNTAIN SHADE STRUCTURE CONCRETE BARBECUE CONCRETE PICNIC TABLES (5) COLORED CONCRETE PAVEMENT DETAIL PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN COLORED CONCRETE
  • 20. PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 21. Playground 2-5 YEAR OLD AREA 5-12 YEAR OLD AREA
    • SEPARATE 2-5 and 5-12 PLAY AREAS
    • MOVEMENT PLAY EQUIPMENT
    • COMBINATION OF RESILIENT SURFACING
    • AND WOOD FIBER
    • PLAYGROUND ADJACENT TO PICNIC
    • AREA, SHADE STRUCTURE, TABLES AND
    • BENCHES
    • SHIP / OCEAN THEME
      • SHIP / OCEAN THEMED PLAY EQUIPMENT
      • OCEAN INSPIRED PLAY SURFACE
      • OCEAN INSPIRED COLORED CONCRETE
    PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 22. 2 – 5 Year Old Playground SHIP THEMED PLAY EQUIPMENT SPINNING EQUIPMENT SHADE CANOPY SWINGS PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN SPRINGING EQUIPMENT PEBBLE FLEX RUBBER PLAY SURFACE
  • 23. 5-12 Year Old Playground SWINGS SHIP THEMED PLAY STRUCTURE PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN PEBBLE FLEX RUBBER PLAY SURFACE NET CLIMBER SPINNING ELEMENT OCTOPUS PLAY ELEMENT
  • 24. PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 25. Adult Fitness Area BENCH THREE (3) ADULT FITNESS STATIONS DECOMPOSED GRANITE SURFACING PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 26. PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 27. Half Court Basketball OPEN GRASS AREA PARK BENCHES HALF COURT BASKETBALL PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN EVERGREEN SCREEN TREES
  • 28. PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 29. Landscaping
    • SHADE TREES
    • SHRUBS AND GROUNDCOVERS – LOW GROWING AND
    • LOW MAINTENANCE
    • PLANTS WITH SEASONAL COLOR TO COMPLIMENT THE
    • PLAYGROUND AND SHADE STRUCTURE
    • PLANTS WITH TEXTURE, COLOR AND SEASONAL
    • INTEREST
    • PERIMETER STREET TREES SPACED AT 30’ ON CENTER
    • GRASS MOUNDING
    PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 30.
    • NEXT STEPS
    • Public Comment on yourcsd.com – June/July 2009
    • CSD Board Master Plan & Environmental Document Approval – July 2009
    • Construction Drawings – July 2010 to Spring 2011
    • Project Out to Bid – Spring 2011 *
    • Construction – Summer 2011 to Spring 2012
    • Park Open – Summer 2012
    • * Pending the outcome of the 218 park assessment vote
    PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN
  • 31. PARK SITE B – SHELDON PLACE CONCEPTUAL MASTER PLAN