Cosumnes CSD - MacDonald Park Conceptual Master Plan - Presentation Transcript
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN PRESENTATION
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN
PARK SITE WE ARE HERE
FUNDING
PARK CONSTRUCTION
DEVELOPER/PARK IMPACT FEES
EASTERN ELK GROVE FINANCE PLAN
$470,000 CONSTRUCTION BUDGET
PARK MAINTENANCE
LANDSCAPE & LIGHTING ASSESSMENTS - $115/YEAR
MAINTENANCE OF 10 PARKS TOTALING 58 ACRES AND
17 ACRES OF LANDSCAPE CORRIDORS
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN
Why is it taking so long to build the rest of our park?!
THE GOOD NEWS
The CSD has $470,000 of Park Impact Fees to build
MacDonald Park Phase 2
Park development funds cannot be used for maintenance costs.
It would be fiscally irresponsible of the CSD to proceed with the
construction of a park that they cannot afford to maintain.
THE NOT-SO-GOOD NEWS
The CSD does not yet own the park site.
Landscape and Lighting (L&L) assessments pay for park
maintenance. Current L&L assessments are not enough to
maintain Park Site B – Sheldon Place.
Proposition 218 was passed by the voters of California in 1996.
In the last 11 years, maintenance costs have risen at a rate that
has exceeded the CPI, typically 2 – 4%, and the District cannot
assume the maintenance of new parkland with the current
available funding.
The proposition prohibits raising assessments at a rate that
exceeds the CPI (Consumer Price Index) without a balloted vote.
HOW DID THIS HAPPEN?
The assessment rate is 11 years old. Rates were determined prior
to build out of the benefit zone and before Sheldon Place was a
subdivision. There was no method for anticipating future parks.
WHAT ARE OUR OPTIONS?
OPTION #1 The ‘do nothing’ option - do not build the park.
OPTION #2
The CSD is asking property owners in your area to vote on a new
park maintenance assessment.
Passing this measure would allow CSD design staff to proceed
with preparation of construction documents.
If passed, maintenance funding would be available for this park
and other parks in the area.
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN
The Elk Grove West
Vineyard Park Assessment
will be $96 annually or
about $8 per month.
51% of the returned ballots
must vote ‘yes’ on this
measure for passage.
Ballots will be arriving
May 1 and must be
returned by June 17
If this measure fails, the construction of MacDonald Phase 2 –
will be postponed indefinitely.
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN Community Forum Thursday, April 23 rd 6:30 – 8:00 p.m. Elk Grove Elementary 9373 Crowell Drive
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN MACDONALD PARK – PHASE 2 1.1 ACRES
CSD PARK DESIGN PRINCIPLES
These park design principles are taken from the CSD’s Draft Master Plan.
MACDONALD PARK IS DEFINED AS A LOCAL PARK.
SIZE – LOCAL PARKS GENERALLY RANGE IN SIZE FROM 1,500 S.F. TO 3
ACRES IN SIZE. THE PARK SITE IS 2.2 ACRES.
A LOCAL PARK TYPICALLY INCLUDES THE FOLLOWING AMENITIES:
SMALL PLAYGROUNDS TARGETED FOR AGES 2-5 AND 5-12
SOME SHADED PLAY ELEMENTS
SMALL SPORT COURTS/PRACTICE FIELD
SMALL PICNIC SHELTER
SWINGS
BENCHES
LANDSCAPING
ADA COMPLIANT AMENITIES
LAND USAGE – 90% ACTIVE/10% PASSIVE
LIGHTING – SECURITY LIGHTING ONLY
PARK DESIGN PRINCIPLES MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN
REMOVE EXISITNG WALKWAYS BENCH TYP. REMOVE PORTION OF EXISTING TRAIL BUFFER PLANTING TRAIL INTERPRETIVE SIGNAGE MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN WHITEHOUSE CREEK BECKINGTON DRIVE SPRING AZURE WAY CONTINUE TRAIL TO BECKINGTON DRIVE MOUNDING SHADE STRUCTURE W/ PICNIC TABLES OPEN GRASS AREA EXISTING PARK BIKE RACKS NEW ADA COMPLIANT PATHWAYS TO TOT LOT EXISTING TOT LOT RENOVATE EXISTING PARK SIGN REPLACE SAND W/ FIBER IN TOT LOT EXISTING DRINKING FOUNTAIN PROPOSED TREES TYP. PLANTING AREA TYP.
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN BECKINGTON DRIVE SPRING AZURE WAY
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN BECKINGTON DRIVE SPRING AZURE WAY
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN REMOVE EXISTING TRAIL SPUR NEW PAVED TRAIL PLANTING AREA INTERPRETATIVE SIGNAGE Trail Area
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN BECKINGTON DRIVE SPRING AZURE WAY
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN REPLACE SAND WITH WOOD FIBER NEW ADA COMPLIANT ACCESS RENOVATE PARK SIGN Existing Tot Lot Area EXISTING PLAY EQUIPMENT (1997) WOOD FIBER EXISTING PLAY EQUIPMENT IS ADA COMPLIANT
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN Landscaping OPEN GRASSED AREA
SHADE TREES
SHRUBS AND GROUNDCOVERS – LOW
GROWING, LOW MAINTENANCE AND
LOW WATER USE
SEASONAL CHANGE - FLOWERS AND
LEAF COLOR
MOUNDING
LARGE OPEN GRASSED AREA FOR
INFORMAL PLAY
NEXT STEPS IF 218 ASSESSMENT VOTE PASSES
CSD Board to approve Master Plan - July 2009
Plans & Specifications – Winter/Spring 2010
Bidding Process – Spring 2010
Construction - Summer/Fall 2010
Maintenance - Period Winter/Spring 2010-11
Park Open to public – Spring 2011
MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN
REMOVE EXISITNG WALKWAYS BENCH TYP. REMOVE PORTION OF EXISTING TRAIL BUFFER PLANTING TRAIL INTERPRETIVE SIGNAGE MACDONALD PARK PHASE 2 CONCEPTUAL MASTER PLAN WHITEHOUSE CREEK BECKINGTON DRIVE SPRING AZURE WAY CONTINUE TRAIL TO BECKINGTON DRIVE MOUNDING SHADE STRUCTURE W/ PICNIC TABLES OPEN GRASS AREA EXISTING PARK BIKE RACKS NEW ADA COMPLIANT PATHWAYS TO TOT LOT EXISTING TOT LOT RENOVATE EXISTING PARK SIGN REPLACE SAND W/ FIBER IN TOT LOT EXISTING DRINKING FOUNTAIN PROPOSED TREES TYP. PLANTING AREA TYP.
0 comments
Post a comment