Flood mitigation council presentation 2 july 2013
Upcoming SlideShare
Loading in...5
×

Like this? Share it with your network

Share
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Be the first to comment
    Be the first to like this
No Downloads

Views

Total Views
647
On Slideshare
647
From Embeds
0
Number of Embeds
0

Actions

Shares
Downloads
1
Comments
0
Likes
0

Embeds 0

No embeds

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
    No notes for slide

Transcript

  • 1. Brandon Flood Protection Plan • Funding Agreement • Improvements • Schedule • Cost
  • 2. Brandon Flood Protection Plan • Funding Agreement – $20M – 90% Province 10% City • Technical Review Committee • Management Committee
  • 3. Brandon Flood Protection Plan • Improvements – North Side of the Assiniboine – South Side of the Assiniboine – 17th St East Dike – Land Drainage Sewer Upgrades (North Side) – Wastewater Sewer Upgrades (North Side)
  • 4. Brandon Flood Protection Plan • Improvements North Side – Create new dike west of 18th St N – Raise dikes Kirkcaldy Drive – Land Drainage Sewer Improvements – Permanent Pumping Station – New Wastewater Lift Station • Discovery Center • Kasiurak Bay • Experimental Farm • Brandon Youth Soccer
  • 5. Brandon Flood Protection Plan • Improvement South Side – Raise dikes – Permanent Pumping Stations • Cattle Auction Mart • Co-op Feeds • Eleanor Kidd Park • Brandon Softball
  • 6. Brandon Flood Protection Plan • Improvements 17th St East Dike – Primary Dike on 17th St E – Secondary CPR access • Residents Primary Dike • Green Spot • CPR • MB Hydro
  • 7. Brandon Flood Protection Plan • Improvement Discussion • First Street will be allowed to be breached at 100+ year flood – Economics – Upstream impact • PTH 110 (Eastern Access) will be raised
  • 8. Brandon Flood Protection Plan • Schedule – 2013 • 18th St North Dike • Kirkcaldy Dr Land Drainage Sewer – 2014 • North, South and 17th St E Dikes – 2015 • North, South and 17th St E Dikes
  • 9. Brandon Flood Protection Plan • Cost – $32M reduced to $24M – Further cost reduction through the detailed design process. • Revised pricing • Tender strategy – Future Funding 2014 and beyond
  • 10. Brandon Flood Protection Plan • Questions / Comments