Brandon Flood Protection Plan
• Funding Agreement
• Improvements
• Schedule
• Cost
Brandon Flood Protection Plan
• Funding Agreement
– $20M
– 90% Province 10% City
• Technical Review Committee
• Management...
Brandon Flood Protection Plan
• Improvements
– North Side of the Assiniboine
– South Side of the Assiniboine
– 17th St Eas...
Brandon Flood Protection Plan
• Improvements North Side
– Create new dike west of 18th St N
– Raise dikes Kirkcaldy Drive
...
Brandon Flood Protection Plan
• Improvement South Side
– Raise dikes
– Permanent Pumping Stations
• Cattle Auction Mart
• ...
Brandon Flood Protection Plan
• Improvements 17th St East Dike
– Primary Dike on 17th St E
– Secondary CPR access
• Reside...
Brandon Flood Protection Plan
• Improvement Discussion
• First Street will be allowed to be breached at 100+
year flood
– ...
Brandon Flood Protection Plan
• Schedule
– 2013
• 18th St North Dike
• Kirkcaldy Dr Land Drainage Sewer
– 2014
• North, So...
Brandon Flood Protection Plan
• Cost
– $32M reduced to $24M
– Further cost reduction through the detailed
design process.
...
Brandon Flood Protection Plan
• Questions / Comments
Flood mitigation council presentation 2 july 2013
Flood mitigation council presentation 2 july 2013
Upcoming SlideShare
Loading in...5
×

Flood mitigation council presentation 2 july 2013

516

Published on

Published in: Technology, Spiritual
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
516
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
2
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Flood mitigation council presentation 2 july 2013

  1. 1. Brandon Flood Protection Plan • Funding Agreement • Improvements • Schedule • Cost
  2. 2. Brandon Flood Protection Plan • Funding Agreement – $20M – 90% Province 10% City • Technical Review Committee • Management Committee
  3. 3. Brandon Flood Protection Plan • Improvements – North Side of the Assiniboine – South Side of the Assiniboine – 17th St East Dike – Land Drainage Sewer Upgrades (North Side) – Wastewater Sewer Upgrades (North Side)
  4. 4. Brandon Flood Protection Plan • Improvements North Side – Create new dike west of 18th St N – Raise dikes Kirkcaldy Drive – Land Drainage Sewer Improvements – Permanent Pumping Station – New Wastewater Lift Station • Discovery Center • Kasiurak Bay • Experimental Farm • Brandon Youth Soccer
  5. 5. Brandon Flood Protection Plan • Improvement South Side – Raise dikes – Permanent Pumping Stations • Cattle Auction Mart • Co-op Feeds • Eleanor Kidd Park • Brandon Softball
  6. 6. Brandon Flood Protection Plan • Improvements 17th St East Dike – Primary Dike on 17th St E – Secondary CPR access • Residents Primary Dike • Green Spot • CPR • MB Hydro
  7. 7. Brandon Flood Protection Plan • Improvement Discussion • First Street will be allowed to be breached at 100+ year flood – Economics – Upstream impact • PTH 110 (Eastern Access) will be raised
  8. 8. Brandon Flood Protection Plan • Schedule – 2013 • 18th St North Dike • Kirkcaldy Dr Land Drainage Sewer – 2014 • North, South and 17th St E Dikes – 2015 • North, South and 17th St E Dikes
  9. 9. Brandon Flood Protection Plan • Cost – $32M reduced to $24M – Further cost reduction through the detailed design process. • Revised pricing • Tender strategy – Future Funding 2014 and beyond
  10. 10. Brandon Flood Protection Plan • Questions / Comments
  1. A particular slide catching your eye?

    Clipping is a handy way to collect important slides you want to go back to later.

×