Production Process of
Wotech Heat Pumps

Wotech Electrical Limited
PART A COMPONENTS INSPECTION
1. Titanium heat exchanger ( for pool heat pump)
Refrigerant water leakage check:
Connect the...
A round green QC passed sticker will be put on the heat exchanger to show
this is QC passed.
A green square sticker will p...
Refrigerant circuit leakage check:
Titanium heat exchangers are kept at high pressure of nitrogen in the
titanium coil ins...
•

After 48 hours workers will unscrew the gas valve to check if any gas
pressure inside the titanium coil to find the lea...
2.Evaporator

Weld the evaporator with the
refrigerant distributing copper
pipes (one side blocked)

Charge 30 bar gas pre...
3. Tube in shell heat exchanger

•

Connect each shell in tube
heat exchanger with water
pipes and charge 6 bar water
pres...
4.Pressure gauges

•
•
•

Pressure gauges are treated the same
for 72 hours with notes marking pressure status. Leakage ca...
5.Mother board and control display

•

All mother boards and control
displays will be connected with
electricity, they wou...
6. Fan motor

•

All fan motors are to be checked
by this equipment, it shows main
phase current, vice phase current
and e...
7. Flow switch

•

Flow switches will be connected with water and power,
set certain flow to see if they function. 100% ch...
Part B Preproduction
1. Subassembly of electronic system

12/35
•

Electronic system is built QC will check the wiring connections.
Different bulbs standing for compressor, water pump, f...
2. Fan motor subassembly

14/35
2. Copper pipe work subassembly

Workers are welding copper pipe work
Carefully.

Copper pipe work subassembly ready
for p...
Part C ,Production
1. Building refrigeration system
When all important components are checked and QC passed they would
be ...
During soldering nitrogen is blown into the pipe work to avoid soldering
residues dropping into the tubing and stuck refri...
2. First leakage check on refrigeration system

Refrigeration system will be charged with nitrogen when bubble testing
sta...
3. Vacuum refrigeration system

After bubble testing system will be vacuumed for 25 minutes before being
charged refrigera...
4. Refrigerant charge

Refrigerant charge equipment will first check the heat pump
refrigeration system is vacuumed well e...
Refrigerant charge equipment is calibrated
frequently by official measuring bureau and
marked with green stickers on all t...
•

•

There are scale indication calibrators which
enable it to to make sure at different ambient
temperature the right vo...
5. Second leakage check on refrigerant system

It is necessary to blow away the residues of refrigerant on the heat pump
B...
Freon leak detector can find
leakage of 2g/year on the
Refrigerant system. It alarms
When freon leak is found above
2 g/ye...
6. Connect electronic system to refrigerant system

Wirings between mother board and
components for compressor, fan motor,...
7. Electrical safety items testing
Each heat pump must be checked with electrical
safety items and standards:
A.
B.
C.
D.
...
8. Performance testing

Each heat pump will have to be tested 30 mins for
heating and 30 mins for cooling
(if there is coo...
9. Dry the heat pump

After performance testing water in the heat exchanger will be dried and blow
away.
28/35
10. Third time leakage check on refrigeration system

After performance testing refrigerant will run through the system . ...
11. Heat pump second start-up

Before packed in carton each heat pump will be connected with power to see
If all wirings a...
12. Cleaning , labeling and accessory bag, packaging

31/35
13. Heat pump ready for loading

32/35
14. Product traceability

Each heat pump has its own product ID
check list with serial nr. on right upper
corner during th...
Part D ,Quality control
There is a product ID check list with each unit
marking down all the process of the unit, each ste...
The End
Thank you.

Prepared by: Stella Yau

Date: Oct. 27th.2012
Upcoming SlideShare
Loading in...5
×

Production Process of Wotech Heat Pump Products

667

Published on

A brief introduction of Wotech production process will let you know more about how to manufacture our air source heat pumps and how professional we are. Our products are safe, green and cost-effective.

Published in: Business, Technology
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
667
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
3
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Transcript of "Production Process of Wotech Heat Pump Products "

  1. 1. Production Process of Wotech Heat Pumps Wotech Electrical Limited
  2. 2. PART A COMPONENTS INSPECTION 1. Titanium heat exchanger ( for pool heat pump) Refrigerant water leakage check: Connect the heat exchanger with water pipes and charge water pressure up to 4 bar to see if water leaks from the PVC shell. 100% check on every heat exchanger with 4 bar water pressure and 6 bar as random check on some pieces. P.S.: Water pressure for normal pool system is 2 bar only. 2/35
  3. 3. A round green QC passed sticker will be put on the heat exchanger to show this is QC passed. A green square sticker will put on the heat exchanger to show this passed 6 bar random check. Flow switches been checked before they are installed on the heat exchangers so green stickers are also on each flow switch here. 3/35
  4. 4. Refrigerant circuit leakage check: Titanium heat exchangers are kept at high pressure of nitrogen in the titanium coil inside for 48 hours to check refrigerant circuit leakage before being assembled, this is 100% check. 4/35
  5. 5. • After 48 hours workers will unscrew the gas valve to check if any gas pressure inside the titanium coil to find the leaks. 100% check. Those fail will be rejected to suppliers. 5/35
  6. 6. 2.Evaporator Weld the evaporator with the refrigerant distributing copper pipes (one side blocked) Charge 30 bar gas pressure (nitrogen) into the evaporator and drop it into the water to find leaks. 100% check. 6/35
  7. 7. 3. Tube in shell heat exchanger • Connect each shell in tube heat exchanger with water pipes and charge 6 bar water pressure to see if any leaks on copper pipes inside the heat exchanger. 100% check. 7/35
  8. 8. 4.Pressure gauges • • • Pressure gauges are treated the same for 72 hours with notes marking pressure status. Leakage can be easily found during the process. 100% check. Those which pass the test will be put green QC passed stickers on the back. 8/35
  9. 9. 5.Mother board and control display • All mother boards and control displays will be connected with electricity, they would be tested under big range of electricity fluctuation– 177 volt to 264 volt for 72 hours. Electronic components with poor quality will easily fail in this test. 100% check. 9/35
  10. 10. 6. Fan motor • All fan motors are to be checked by this equipment, it shows main phase current, vice phase current and etc, make sure if the specification meets Wotech requirement. 100% check. 10/35
  11. 11. 7. Flow switch • Flow switches will be connected with water and power, set certain flow to see if they function. 100% check. 11/35
  12. 12. Part B Preproduction 1. Subassembly of electronic system 12/35
  13. 13. • Electronic system is built QC will check the wiring connections. Different bulbs standing for compressor, water pump, fan motor, 4-way valve and etc will be on only when the wiring is correct. QC will also check if the program is written per customer’s request. 100% check. 13/35
  14. 14. 2. Fan motor subassembly 14/35
  15. 15. 2. Copper pipe work subassembly Workers are welding copper pipe work Carefully. Copper pipe work subassembly ready for production. 15/35
  16. 16. Part C ,Production 1. Building refrigeration system When all important components are checked and QC passed they would be built on the heat pumps. first step is to build refrigeration system, compressor, evaporator, condenser and copper pipe work. 16/35
  17. 17. During soldering nitrogen is blown into the pipe work to avoid soldering residues dropping into the tubing and stuck refrigerant system. 17/35
  18. 18. 2. First leakage check on refrigeration system Refrigeration system will be charged with nitrogen when bubble testing starts. Soap-subs will be brushed on all the soldering points to check if any leakage. This is the first time leakage check on refrigeration on production line. High pressure and low pressure switch will be also checked if they function or not. 18/35
  19. 19. 3. Vacuum refrigeration system After bubble testing system will be vacuumed for 25 minutes before being charged refrigerant. 19/35
  20. 20. 4. Refrigerant charge Refrigerant charge equipment will first check the heat pump refrigeration system is vacuumed well enough to reach the set Standard before it charges refrigerant , or would give alarm and stop charging. 20/35
  21. 21. Refrigerant charge equipment is calibrated frequently by official measuring bureau and marked with green stickers on all the measur -ing components. There are 2 different refrigerant charge system inside R407c and R410a. 21/35
  22. 22. • • There are scale indication calibrators which enable it to to make sure at different ambient temperature the right volume is charged. To make sure the refrigerant always work well after charging the refrigerant by this equipment the first unit of same model of the order will be checked the volume by electronic weight. If the volume is correct production will be proceeded on the rest heat pump. 22/35
  23. 23. 5. Second leakage check on refrigerant system It is necessary to blow away the residues of refrigerant on the heat pump Before the second leakage check on refrigerant system. All the soldering points and all possible weak points will be checked by gas Sniffer equipment. 23/35
  24. 24. Freon leak detector can find leakage of 2g/year on the Refrigerant system. It alarms When freon leak is found above 2 g/year. 24/35
  25. 25. 6. Connect electronic system to refrigerant system Wirings between mother board and components for compressor, fan motor, 4-way valve, high & low pressure switches, sensors and etc must be connected properly. Wirings and insulations look neat and tidy . 25/35
  26. 26. 7. Electrical safety items testing Each heat pump must be checked with electrical safety items and standards: A. B. C. D. Grounding: within 5 seconds <100 mΩ Withstand voltage: within 3 seconds 1800V, <5mA Insulation: 500 V, >2 MΩ Leakage: within 2 seconds 234V <0.75mA 26/35
  27. 27. 8. Performance testing Each heat pump will have to be tested 30 mins for heating and 30 mins for cooling (if there is cooling mode) . Water flow will Be fixed, sensors will be installed on important positions to check if heat pump performs as designed. All test results will be marked on the unique product ID check list. Those which does not perform well enough will be taken off from production line for investigation. 27/35
  28. 28. 9. Dry the heat pump After performance testing water in the heat exchanger will be dried and blow away. 28/35
  29. 29. 10. Third time leakage check on refrigeration system After performance testing refrigerant will run through the system . If any leaks it Would be much easier to find now. 29/35
  30. 30. 11. Heat pump second start-up Before packed in carton each heat pump will be connected with power to see If all wirings are still in good contact. It is aware that when the heat pump is Dried out the water, wirings is got loose and in bad contact. 30/35
  31. 31. 12. Cleaning , labeling and accessory bag, packaging 31/35
  32. 32. 13. Heat pump ready for loading 32/35
  33. 33. 14. Product traceability Each heat pump has its own product ID check list with serial nr. on right upper corner during the whole production. All the process are printed and to be marked if they are properly done. After the heat pump is packed QC will keep all these check list for filing and future reference. Serial nr. are also marked on side panel, fan motor, capacitor and etc, for this we can always trace them back. 33/35
  34. 34. Part D ,Quality control There is a product ID check list with each unit marking down all the process of the unit, each step will have 3 persons checked and marked on the sheet as a record, if problems found during production remarks would be written on the sheet and products sent back to be reworked and solve the problem until everything is ok. We have technical operation instruction at each stage of the production line to instruction workers how to meet our requirements of quality and workmanship. 34/35
  35. 35. The End Thank you. Prepared by: Stella Yau Date: Oct. 27th.2012