Successful Management Of Change Programmes Programme Governance (April 2007)

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

2 comments

Comments 1 - 2 of 2 previous next Post a comment

  • + guest3bed02 guest3bed02 2 years ago
    Thanks for your comment - have you taken a look at the other five in the series?
  • + guest46a468 guest46a468 2 years ago
    This is brilliant. You got see it
Post a comment
Embed Video
Edit your comment Cancel

1 Favorite

Successful Management Of Change Programmes Programme Governance (April 2007) - Presentation Transcript

  1. Successful Management of Programmes
    Programme Governance
  2. 2
    Programme Governance
    This presentation is designed to provide a set of principles and guidelines for governing large, complex programmes
    Topics covered:
    • Programme management and structure
    • Programme roles
    • Role of the Programme Sponsor
    • Project Control
    • Programme Planning
    • Integration with other functions
  3. 3
    Principles for Programme Governance
    Manage both upwards and downwards. The programme needs clear direction from above and needs careful control and management downwards.
    Have the right steering group (senior level people from affected functions, IM, HR and change directors) to provide direction and support.
    Maintain senior level input and engagement.
    Stay within business strategy and corporate governance
    Work to a recognised lifecycle
    Control the programme:
    Stay within remit
    Manage and resist change
    Control and manage risks
    Deliver on time, to cost & quality
    Report progress and relevant issues honestly to all interested parties.
  4. 4
    A typical Change Project Lifecycle
  5. 5
    Programme management and structure: Guidelines
    • Clearly state goals, ambitions and benefits
    • Use the ‘hour glass’ to define the programme and scope
    • Plan to deliver against the programme scope and create a baseline plan
    • Prepare an investment case against the baseline plan and scope
    • Regularly report the status of benefits and how they will be realised
    • Constantly review scope against proposed solution elements – be prepared to reject some and add others depending on the overall benefit accrued.
    • Log and control all dependencies.
    • Have an honest and appropriate reporting process that shows progress, milestones, risks and issues
    • Create and shape your management plan.
    • Deliver against your commitment
    • Change management skills should form an integral part of all programme activities.
  6. 6
    Standard Project Structure
    Change skills are woven through the fabric of the team. It is how things are done that characterise change as much as whatis done. It is not a separate team but an integral part of the how things are done throughout the programme.
    Sponsor – Strategic Direction & Vision
    Programme Director – To manage delivery
    Business Process Owners
    Project Stream leader (s)
    Project Implementation Support
    Design Integration
    IM Project Manager
    Controls Team
    Communications
    Third Party Suppliers
    Core Design Team & Facilitation
    Support
    Training
    Data
  7. Change management is more than just a set of activities or tools – it’s a way of thinking and working
    Change Programme Activities
    Carry out those activities to plan, analyse, design and implement the change
    What is done
    Individual empathy
    Understand and help individuals to deal with the emotional, rational and political aspects of change
    Organisational empathy
    Understand and adapt the change programme to the cultural environment
    How its done
  8. 8
    Programme Roles: Guidelines
    Role of IS.
    IS are a key supplier to the programme of technology.
    IS own the technical architecture.
    IS ensure the solution fits to the architecture and can be supported.
    Role of the Programme Director.
    To ensure delivery – provide the right lifecycle and programme control
    To advise the sponsor
    Partnership with the sponsor
    Advise sponsor and contribute to the direction of the programme (raising issues and providing key facts about the programme).
    Role of the steering group
    To ensure the programme is on the right track to meet the business objectives
    To resolve any issues raised by the programme
    To provide guidance and senior level support to the programme
  9. 9
    Role of the Programme Sponsor: Guidelines
    • The Sponsor is custodian of the business interest.
    • They need to be driven by business benefits.
    • They should be committed to the programme and passionate about its success. They will be key to getting the programme through the investment board.
    • They should be able to clearly articulate the business benefit of the programme.
    • They need to give sufficient time to the project and to understanding the solution and its impact on the business.
    • They need to behave as a client and customer, testing the robustness of plans and due diligence on behalf of the business.
    • They need to provide/secure business resources for the programme and understand why this is important.
    • They should manage the politics upwards, especially at board level.
    • They should be visible and prepared to represent the programme with senior management and other stakeholders and at events, such as roadshows.
  10. 10
    Programme Control: Guidelines
    Complement project management skills with
    Planning
    Risk management
    Management reporting
    Cost Control
    Estimating & commercial management
    Change management
    Create baselines and manage against them.
    Prepare for and manage risk.
    Ensure compliance with the Project Control Cycle. Ensure the appropriate change and project management products are produced and managed.
    Resist change and scope creep where possible. Manage change in a structured way. All change must have an impact assessment before the change is enacted.
  11. 11
    Programme Planning: Guidelines
    Work to a recognised project lifecyle.
    Create a plan with the right level of detail – cost and resource load the plan to ensure you can deliver what is required, what it will cost and when it can be delivered.
    Baseline the plan, so the impact of changes can be assessed before they can be accepted.
    Link the plan to risk management and plan for risk mitigation.
    Be disciplined – update and progress the plan on a regular basis, whether it is weekly, fortnightly or monthly.
  12. 12
    Integration with other functions: Guidelines
    Understand all inputs to your processes & clearly specify any changes.
    Defining & sharing data is key.
    Ensure that others can deliver your requirements.
    Keep checking progress and timescales (others have different priorities).
    Understand your process outputs and your customer requirements.
    My Project
    Areas of overlap & dependency
  13. 13
    Contact
    TIPS Consulting Ltd
    Hamilton House
    Mabledon Place
    Bloomsbury
    London
    WC1H 9BB
    Tel - +44 (0) 207 554 8637
    Fax - +44 (0) 207 554 8501
    Web – www.tipsconsulting.co.uk

+ Tony LockwoodTony Lockwood, 2 years ago

custom

1652 views, 1 favs, 0 embeds more stats

Part of a five part series looking at the role of P more

More info about this document

© All Rights Reserved

Go to text version

  • Total Views 1652
    • 1652 on SlideShare
    • 0 from embeds
  • Comments 2
  • Favorites 1
  • Downloads 213
Most viewed embeds

more

All embeds

less

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

Cancel
File a copyright complaint
Having problems? Go to our helpdesk?

Categories