Successful Management Of Change Programmes (April 2007)

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

0 comments

Post a comment

    Post a comment
    Embed Video
    Edit your comment Cancel

    Favorites, Groups & Events

    Successful Management Of Change Programmes (April 2007) - Presentation Transcript

    1. Successful Management of Programmes
      An Introduction
    2. Change Management – introduction
      This presentation is designed to introduce the management of change within large, complex programmes
      Topics covered:
      • Why manage change at all?
      • Being successful at change
      • Overcoming common problems
      • The change project lifecycle
    3. Why manage change at all?
      The purpose of change is to solve business problems and deliverbenefits to the organisation e.g.
      Reduced costs
      Increased revenues
      Increased profits & increased shareholder value
      Move ahead of the competition
      Delivery of a system (or any other type of business change) without achieving any benefits to the organisation is not a successful change
    4. Change is rarely one-dimensional
      Rarely does a solution only involve one aspect of the organisation.
      To deliver the benefits, many associated changes may need to defined and implemented.
      Define new strategic direction
      Change behaviours
      Change skills base
      Change sourcing strategy
      Business Solution
      (A combination of these – one is rarely enough)
      Introduce new technology
      Business problem
      Define new processes
      Restructure
      Introduce new products
      Refresh Management Team
      Even the introduction of a new system may involve the definition of new processes, changes in skills and changes in behaviours to deliver the benefits that the business needs.
    5. Some common problems with change projects
      Business fit
      No-one wanted to use it
      It didn’t work the way we needed it too
      No one could make their mind up what they wanted.
      What we got was not what I asked for.
      Governance
      It cost much more than planned and was very late.
      It got out of control and we stopped it.
      The scope implemented was much less than scope we set out with.
      It did not deliver the benefits….
      Some 75% of projects fail to deliver against original targets1
      1 Source Gartner, 2002
    6. How To Ensure Success – the Do’s
      1. Programme Governance
      Strong Programme Management
      Create a focused strategy for change, prioritised on economic benefits for the business; base the strategy on objective analysis rather than on the sum of current management opinion; suspend/restrict current “pet” projects.
      Employ strong project management and work to a recognised project lifecycle.
      Install project teams with the right balance of change experience and business knowledge.
      Create a structured approach to change programmes; insist the structure is followed.
      Commit your people to agreements which incentivise completion to time, within cost, and to agreed (benefit-based) deliverables.
      Manage interfaces and work across functional boundaries – especially when using enterprise solutions.
      Leadership & vision
      Ensure strong and visible sponsorship from the appropriate director(s).
      Create a compelling vision for the future
      2. Proactive benefits realisation
      Focus on a benefits led solution with measurable outcomes – define success.
      Create a benefits realisation plan, linked to a feasible roll-out arrangement.
    7. How To Ensure Success – the Do’s
      3. Business Engagement
      Structured Communication
      Establish a well structured, focused communication strategy with appropriate interventions at all stages of the project lifecycle.
      Constantly review communications for effectiveness.
      Create Ownership
      Ensure there is sufficient business input at all stages.
      Enable the business to participate actively in the design – create a core design team
      Manage Stakeholders
      Know who’s affected and how it will affect them.
      Set expectations appropriately.
      Involve every layer – create a network of committed champions, as well as local transition teams, to extend the programme team’s work
    8. How To Ensure Success – the Do’s
      4. Align the Solution
      Develop a total solution – define a robust technology solution that considers and works with people, organisation, process and culture.
      Technology must be aligned to business needs and the design must be accessible to the business (interactive/RAD).
      Select the correct solution by considering all of the options.
      Ensure both the IT and HR Departments are aligned and engaged; create joint budgetary control between Change Programme and IT/HR spend.
      5. Embed the change
      Embedding change requires people to consistently and permanently adopt new practices, behaviours, skills or capability
      Embedding takes time - prepare for an on-going cycle of development
      Prepare people for the change and support them through the change – make training appropriate and timely
      Follow up – re-align employees’ KRAs and KPIs measures to desired performance
    9. How to Ensure Success – the Don’ts
      Focus on the technology and ignore the people that will use it
      Hope that staff will make the solution work, even if it isn’t up to the job
      Over communicate when there is nothing to say
      Assume people will find out what is happening and when
      Forget the business until it’s time to implement the system
      Put inexperienced staff in project leadership roles
      Forget to plan and cost for resources in the business for essential preparation activities such as data migration, testing, pilots etc.
      Cave in to constant changes
      Allow the scope to creep
      Fail to review the programme in the light of emerging findings, economics, changing market conditions.
      Disband successful change teams and discard methodologies; ignore the necessity to build and maintain effective change capability.
    10. The key activities
    11. Programme Governance: Strong programme management
      Work to a recognised project lifecycle
      Projects & programmes are high risk activities – prepare for risk
      Change is the biggest and most disruptive risk of all – change must be resisted where possible and managed in a structured way where absolutely necessary
      Create baselines and manage changes in performance against them
      Use an honest and appropriate reporting process that shows progress, milestones, risks & issues
      Regularly report status of anticipated benefits and how they are being realised
      Log and control all inter-dependencies
      Experienced project team
      • The team must be led by experienced Project Professionals - resist using too many rising stars from the business in lead roles.
      • The team should have significant representation from the Business Units affected to provide current business knowledge, ensure solutions fit to the business and to become experts in the new solution.
      • The team needs to be augmented with change professionals to ensure the project really changes the business
      • Ensure the team has strong project management skills with project management disciplines such as Base-lining, Process Mapping, Business Case preparation, Planning, Risk Management, Reporting and Cost Control
    12. Programme Governance: Leadership and vision
      Sponsorship should be strong and visible from an appropriate Director
      Director who manages the Business Unit; usually Board Director or CEO
      Directors must commit to agreed changes to their businesses; If the Director is not passionate about change then DO NOT DO IT
      Director must ‘WALK THE TALK’ .
      Director must find time to provide guidance to team, lead communications activity and manage key stakeholders.
      Staff take their lead from the top – if passionate and articulate they will follow.
      Senior Management Support
      Support from Senior Management will be critical – especially with regard to the business case and ensuring continuity of the programme
      Gain support to secure involvement of critical business resources
      Compelling vision
      The programme needs a vision that is compelling for the business
      The vision has to be clearly and simply articulated
      The programme should have a common picture that can be understood by all
    13. Proactive benefits realisation
      Identify benefits from the beginning
      • Clear business objectives and outcomes for the programme should be identified from the start
      • Use root cause analysis to help identify possible benefits and link elements of the solution to solving root causes
      • Ensure all solution elements are linked to specific benefits
      Develop a realistic approach to measuring benefits
      • Identify measures to prove/disprove benefits; keep it simple where possible - don’t make KPI measurement into a cottage industry.
      • Determine when to start collecting data – baseline measures before implementation
      • Collect performance data at an appropriate time after implementation – don’t expect all benefits immediately
      Benefits driven solution
      • Any activity not linked to benefits should be stopped
      • Any change requests must also pass this test
    14. Business Engagement: Structured Communication
      Manage a well structured Communications Strategy & Plan
      All affected staff must know what is happening and be prepared for change – no-one likes surprises, or being told to commit significant efforts without justification.
      Staff must be enthused to support what’s happening. This comes from providing a vision and clear leadership as well as from good communication.
      Know the audience and have clear, simple objectives for every communication.
      Plan communication in advance and keep up the momentum
      Co-ordinate simple messages using a variety of communication channels. The more impact the message has on the audience, the more personal the communication should be. Examples include:
      Articles in staff magazines
      Web site on company intranet
      News Sheets/Fact sheets
      Cascade packs
      1:1 briefings for senior staff
      Road Shows/Fairs
      Technology demonstrations
      Craft the communications to the effect you are trying to achieve within the programme life cycle; – timing is everything
      Your people need facts and guidance, not high-level platitudes or vacuous repetition.
      Continually review communications and adapt the plan throughout the programme
    15. Business Engagement: Create Ownership
      Significant input is required from the business at all stages
      The solution must be owned by the business – otherwise it won’t be used nor the benefits fully achieved
      Appropriate staff members must have input to the solution design – use the best and well respected staff to help shape the solution – the core design team
      Empower core team members to be able to make informed choices – ensure they can understand the impact of any choices they make, especially if it involves technology
      Widen the numbers of people involved through review teams – use them to review the design and test for robustness
      Walk through the solution design with all affected staff – allow them to ask questions and understand fully what the impact will be
    16. Business Engagement: Manage stakeholders
      Know who the stakeholders are
      Who will be affected by the change and how will the change may affect them
      Establish early where the cultural hurdles lie (Know whether they are positive, neutral or negative towards the change)
      Manage expectations
      Be realistic and truthful about what the change will involve,.
      Air difficult subjects early especially in terms of large changes in job content and headcount reduction/migration– it gives people time to adjust. If swept under the carpet it becomes a bigger problem later
      Build a network of people to help with the change
      Identify ‘champions’ for change across the business – they will extend the reach of the programme team
      Identify local transition teams
      Make them an extension of the project team, who share intimate knowledge of the solution
    17. Align the solution
      Designing technology is very difficult and detailed
      • Visualising the client need is challenging for IT staff.
      • Understanding what the designers are saying is challenging for business staff.
      • Actively seek out “hybrid” skills to manage the interface between the Business and Technology Change Teams.
      Avoid written specifications for Business users
      • Start by articulating business process and mock this up in the system.
      • Use an interactive process.
      • Go round the loop 2 or 3 times.
      Avoid bespoking
      • Use packages wherever possible & resist changing them.
      In a large programme deliver useful functionality regularly in a sequenced roll-out plan.
      • Do not wait 5 years for a big bang
      • Allows time to ensure solutions can work
      • Allows lessons to be learnt
      • Releases benefits more effectively by taking into account the rate at which the workforce can absorb change.
    18. Embedding the change
      Change needs to be embedded to achieve the benefits
      • The toughest challenge may be the organisational and behavioural change to your workforce.
      This means:-
      Headcount reduction; ensuring the “leavers” area as far as possible the ones you want to shed
      Transformation (often radical) of job content and skill requirements, particularly at supervisory level. This implies re-selection of managers.
      Documentation and consistency of job descriptions, KRAs, KPIs with heavy reliance on your HR function.
      A tough series of decisions from your Directors and senior managers.
      • Use a maturity model to determine what capability is required for functions or processes.
      Develop a route map to build competence initially, develop capability over time and finally to aim for excellence
      Plan reviews – test progress against the maturity model and route map
      • Cultural change needs to managed with resolve – management must lead by example
    19. Embedding the Change
      Provide support initially to help people ‘get it right’
      • Develop work instructions – work through how each job role can do their job with a new system in detail - this will help to reinforce good practice and avoid going back to old ways and old systems
      Provide appropriate and timely training so that staff can use what they’ve learnt immediately
      ‘Floorwalkers’ provide on the spot help in the early days of implementation to avoid frustration
      Use coaching to praise new behaviours observed and to address old behaviours
      • Provide adequate IT and process support
    20. A typical Change Project Lifecycle
    21. Contact
      TIPS Consulting Ltd
      Hamilton House
      Mabledon Place
      Bloomsbury
      London
      WC1H 9BB
      Tel - +44 (0) 207 554 8637
      Fax - +44 (0) 207 554 8501
      Web – www.tipsconsulting.co.uk

    + Tony LockwoodTony Lockwood, 2 years ago

    custom

    1189 views, 0 favs, 0 embeds more stats

    An overview of how to lead successful change within more

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 1189
      • 1189 on SlideShare
      • 0 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 263
    Most viewed embeds

    more

    All embeds

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories