GUIDE LINES FOR COAL HANDLING UNITS:-
(A) Location criteria
1. Coal handling unit/Agency shall not use any agriculture land and shall
be located at a minimum distance of 250 meters away from the
surrounding agriculture land.
2. Government waste land not suitable for any agriculture purpose
meeting with the requisite siting / distance criteria shall be preferred
for establishing coal handling units.
3. Coal handling unit/Agency shall be minimum 500 meters away from
the residential area, school/colleges, Historical Monuments, Religious
Places, Ecological sensitive area as well as forests area.
4. Coal handling unit/Agency shall be located at a minimum 500 meters
away from the Railway line, Express ways, National Highways, State
ways and District Roads and from water bodies like River, Nala,
Canal, Pond etc.
5. In case of coal handling activities at the ports and jetties or extension
thereof, the distance and land use criteria may be relaxed and
compensated by advanced/sophisticated pollution control measures
and mechanization & thick plantation, however all such ports and
jetties, where coal handling is carried out, shall provide closed
conveyor belt and mechanization for handling of coal.
(B) Storage and handling criteria
6. Coal handling unit/Agency shall store coal in such a way that coal
heap should not be higher than 5 meter and clear distance between
two adjoining heaps at G.L. should be 5 meters, so that in case of fire,
approach is available.
7. There should be mechanized loading/ unloading system from the
loading /unloading area to the stacking yards and in to the vehicles.
8. Coal handling unit/Agency shall take all corrective steps to resolve the
issue of air pollution at permitted coal storage/handling area where
coal is being stored.
(C) Transport criteria
9. Coal handling unit/Agency shall ensure that all trucks before leaving
the storage yard shall be showered with water with adequate system,
Shall be covered with tarpaulin or any other effective measure/device
completely and also that trucks are not over loaded as well as there is
no spillage during transportation.
10.The vehicle carrying the coal should not be overloaded by raising the
height of carriage. Weigh scale shall be provided within the loading
area only and port / coal park authority shall ensure that no
overloading is done.
11.The top of the vehicle should be covered with fixed cover instead of
tarpaulin cover to avoid spillage or dusting of coal.
12. Coal handling unit/Agency shall obtain transport permission from the
local Administration under the relevant rules.
(D) Pollution prevention criteria
13. Coal handling unit/Agency shall provide paved approach with
adequate traffic carrying capacity
14. Coal handling unit/Agency shall construct compound wall all along
periphery of the premises with minimum 9 meters height
15. Continuous water sprinkling shall be carried out on the top of the
heap at regular intervals to prevent dusting, fire & smoke. To prevent
fugitive emission during loading/unloading, fixed pipe network with
sufficient water storage and pump shall be installed. Water sprinkling
shall be carried out at each and every stage of handling to avoid
generation of coal dust or other dust within premises
16. Coal handling unit/Agency shall ensure regular sweeping of coal dust
from internal and main road and also ensure that there is adequate
space for free movement of vehicles.
17. The following adequate Air Pollution Control Measures shall be
installed and to be operated efficiently.
(a) Dust containment cum suppression system for the coal stack,
loading and unloading.
(b) Construction of effective wind breaking wall suitable to local
condition to prevent the suspension of particles from the heaps.
(c) Construction of metal road & RCC Pucca flooring in the plot area/
godown etc.
(d) System for regular cleaning and wetting of the floor area within the
premises.
(e) Entire coal storage area/ godown should be covered with
permanent weather shed roofing and side walls i.e., in closed shed,
in case of crushing/sieving/grading activity is carried out (i.e. G. I.
Sheet) along with adequate additional APCM should be installed.
18. Coal handling unit/Agency shall carryout three rows plantation with
tall growing tress all along the periphery of the coal handling
premises, inside & outside of the premises along with road.
19. Proper drainage system shall be provided in all coal storage area so
that water drained from sprinkling & runoff is collected at a common
tank and can be reused after screening through the coal slit or any
other effective treatment system.
20. All the engineering control measures and state of art technology
including covered conveyer belts, mechanized loading and
unloading, provision of silo etc. shall be provided in addition to the
measures recommended in the environmental guidelines for curbing
the pollution.
(E) Safety requirement
21. Coal handling unit/Agency shall provide adequate fire fighting
measure to avoid any fire or related hazards including adequate
water storage facility, and the premises shall be exclusively used for
storage of the coal.
22. An onsite emergency plan shall be prepared and implemented by
coal handling unit.
(F) Legal criteria
23. Necessary permission from all the applicable regulatory authorities
and adequate steps under the provisions of applicable environmental
acts/ rules shall be taken.
24. Coal handling unit/Agency shall prepare EMP (Environment
Management Plan) and implement the same in true spirit and thus
maintain overall environment of that area.
25. Coal handling unit/Agency shall not carry out the operation of
loading/unloading of coal/coal dust at any place, till adequate air
pollution control equipment for dust control/suppression are installed
and efficiently operated and the consent under the provisions of Air
(Prevention & Control of Pollution) Act, 1981 is obtained by the coal
yard owners/ Coal handling unit/Agency / coal importers.
26. Coal handling unit/Agency shall operate continuous Ambient Air
Quality Monitoring Stations as per CPCB guideline. The results of
parameters like SPM, RSPM, and SO2 and NOx shall be submitted
to the SPCB every month.
27. In case of port which provides the facility to individual developers an
agreement /MoU shall be made between port authority and
developer for curtailment of pollution. Port authority shall be
responsible for supervising and controlling the pollution control
related activities and implementation of the environmental guidelines.
28. The concentration of the following parameters in the ambient air
within the premises and a distance of 10 meters from the source
(other than the stack/vent) shall not exceed the following levels.
PARAMETERS PERMISSIBLE LIMIT
Annual 24 Hrs Average
Particulate Matter-10 (PM
10
) 60 Microgram/M
3
100 Microgram/M
3
Particulate Matter- 2.5 (PM
2.5
) 40 Microgram/M
3
60 Microgram/M
3
SO
2 50 Microgram/M
3
80 Microgram/M
3
NO
x 40 Microgram/M
3
80 Microgram/M
3

More Related Content

Viewers also liked (16)

Indian dairy industr1
Indian dairy industr1Indian dairy industr1
Indian dairy industr1
 
Barit year book
Barit year bookBarit year book
Barit year book
 
BDG International - Global Trade
BDG International - Global TradeBDG International - Global Trade
BDG International - Global Trade
 
OMAN DOWNSTREAM EXHIBITION & CONFERENCE 2017 BROCHURE
OMAN DOWNSTREAM EXHIBITION & CONFERENCE 2017 BROCHUREOMAN DOWNSTREAM EXHIBITION & CONFERENCE 2017 BROCHURE
OMAN DOWNSTREAM EXHIBITION & CONFERENCE 2017 BROCHURE
 
Indian fertilisers
Indian fertilisersIndian fertilisers
Indian fertilisers
 
Haresh Group
Haresh GroupHaresh Group
Haresh Group
 
Cassava
CassavaCassava
Cassava
 
Trademark Registration in UAE
Trademark Registration in UAETrademark Registration in UAE
Trademark Registration in UAE
 
Uae imports and exports guide
Uae imports and exports guideUae imports and exports guide
Uae imports and exports guide
 
atm-5
atm-5atm-5
atm-5
 
The global market potential of halal
The global market potential of halalThe global market potential of halal
The global market potential of halal
 
Organisation Study in Greenply
Organisation Study in GreenplyOrganisation Study in Greenply
Organisation Study in Greenply
 
"A STUDY ON COMMODITY MARKET"
"A STUDY ON COMMODITY MARKET""A STUDY ON COMMODITY MARKET"
"A STUDY ON COMMODITY MARKET"
 
Chapter 1 alcohols
Chapter 1 alcoholsChapter 1 alcohols
Chapter 1 alcohols
 
Fertiliser ppt
Fertiliser pptFertiliser ppt
Fertiliser ppt
 
Marketing plan for salon praba
Marketing plan for  salon prabaMarketing plan for  salon praba
Marketing plan for salon praba
 

Similar to Coal handling-guidelines

184648009 new-hot-bitumen-storage-tank-construction-guidelines-march-2012-2
184648009 new-hot-bitumen-storage-tank-construction-guidelines-march-2012-2184648009 new-hot-bitumen-storage-tank-construction-guidelines-march-2012-2
184648009 new-hot-bitumen-storage-tank-construction-guidelines-march-2012-2Sameer Ahmed
 
Technical specifications for Phase 1 Wastewater Network tank interceptors
Technical specifications for Phase 1 Wastewater Network tank interceptorsTechnical specifications for Phase 1 Wastewater Network tank interceptors
Technical specifications for Phase 1 Wastewater Network tank interceptorsLaith Abdel Nabi
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan David H Moloney
 
Coastal regulation zones and its relevance
Coastal regulation zones and its relevanceCoastal regulation zones and its relevance
Coastal regulation zones and its relevancePranav Padmakumar
 
Dust monitoring and control in metal Mines
Dust monitoring and control in metal MinesDust monitoring and control in metal Mines
Dust monitoring and control in metal MinesAdil Mathew
 
Cle thur mou_arapahoe
Cle thur mou_arapahoeCle thur mou_arapahoe
Cle thur mou_arapahoeFaryad Shah
 
Roadway Ordinance
Roadway OrdinanceRoadway Ordinance
Roadway Ordinancegscplanning
 
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperSHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperDennis McElroy
 
Appendix J Spill and Waste Management Plan.PDF
Appendix J Spill and Waste Management Plan.PDFAppendix J Spill and Waste Management Plan.PDF
Appendix J Spill and Waste Management Plan.PDFssuserfce39b
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016Ali Issa
 
design of common hazardous waste treatment, storage and ....
 design of common hazardous waste treatment, storage and .... design of common hazardous waste treatment, storage and ....
design of common hazardous waste treatment, storage and ....arvind kumar
 
Method_Statement_of_Deep_Cement_Mixing_M.pdf
Method_Statement_of_Deep_Cement_Mixing_M.pdfMethod_Statement_of_Deep_Cement_Mixing_M.pdf
Method_Statement_of_Deep_Cement_Mixing_M.pdfKhai Truong
 
design of common hazardous waste treatment, storage and 2
design of common hazardous waste treatment, storage and 2design of common hazardous waste treatment, storage and 2
design of common hazardous waste treatment, storage and 2Arvind Kumar
 
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1Tahar Hajji
 
VG Check list using JCB near track rev 00
VG Check list using JCB near track rev 00VG Check list using JCB near track rev 00
VG Check list using JCB near track rev 00Varadharajalu Gopal
 
Annex IV or the Prevention of pollution of sewage from ships
Annex IV or the Prevention of pollution of sewage from shipsAnnex IV or the Prevention of pollution of sewage from ships
Annex IV or the Prevention of pollution of sewage from shipsshutdafowkup17
 

Similar to Coal handling-guidelines (20)

NDL FUEL STATION OPERATION
NDL FUEL STATION OPERATIONNDL FUEL STATION OPERATION
NDL FUEL STATION OPERATION
 
184648009 new-hot-bitumen-storage-tank-construction-guidelines-march-2012-2
184648009 new-hot-bitumen-storage-tank-construction-guidelines-march-2012-2184648009 new-hot-bitumen-storage-tank-construction-guidelines-march-2012-2
184648009 new-hot-bitumen-storage-tank-construction-guidelines-march-2012-2
 
Technical specifications for Phase 1 Wastewater Network tank interceptors
Technical specifications for Phase 1 Wastewater Network tank interceptorsTechnical specifications for Phase 1 Wastewater Network tank interceptors
Technical specifications for Phase 1 Wastewater Network tank interceptors
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Coastal regulation zones and its relevance
Coastal regulation zones and its relevanceCoastal regulation zones and its relevance
Coastal regulation zones and its relevance
 
Dust monitoring and control in metal Mines
Dust monitoring and control in metal MinesDust monitoring and control in metal Mines
Dust monitoring and control in metal Mines
 
Environmental control measures
Environmental control measuresEnvironmental control measures
Environmental control measures
 
Cle thur mou_arapahoe
Cle thur mou_arapahoeCle thur mou_arapahoe
Cle thur mou_arapahoe
 
Roadway Ordinance
Roadway OrdinanceRoadway Ordinance
Roadway Ordinance
 
Short termim workplan_20100602_part3
Short termim workplan_20100602_part3Short termim workplan_20100602_part3
Short termim workplan_20100602_part3
 
Coal processing
Coal processingCoal processing
Coal processing
 
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR WhitepaperSHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
SHATEC Engineering Consultants - Graniterock dba FMG CIR Whitepaper
 
Appendix J Spill and Waste Management Plan.PDF
Appendix J Spill and Waste Management Plan.PDFAppendix J Spill and Waste Management Plan.PDF
Appendix J Spill and Waste Management Plan.PDF
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
design of common hazardous waste treatment, storage and ....
 design of common hazardous waste treatment, storage and .... design of common hazardous waste treatment, storage and ....
design of common hazardous waste treatment, storage and ....
 
Method_Statement_of_Deep_Cement_Mixing_M.pdf
Method_Statement_of_Deep_Cement_Mixing_M.pdfMethod_Statement_of_Deep_Cement_Mixing_M.pdf
Method_Statement_of_Deep_Cement_Mixing_M.pdf
 
design of common hazardous waste treatment, storage and 2
design of common hazardous waste treatment, storage and 2design of common hazardous waste treatment, storage and 2
design of common hazardous waste treatment, storage and 2
 
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
 
VG Check list using JCB near track rev 00
VG Check list using JCB near track rev 00VG Check list using JCB near track rev 00
VG Check list using JCB near track rev 00
 
Annex IV or the Prevention of pollution of sewage from ships
Annex IV or the Prevention of pollution of sewage from shipsAnnex IV or the Prevention of pollution of sewage from ships
Annex IV or the Prevention of pollution of sewage from ships
 

Recently uploaded

Group 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdfGroup 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdfs2015004
 
Science, Technology and Nation Building.pptx
Science, Technology and Nation Building.pptxScience, Technology and Nation Building.pptx
Science, Technology and Nation Building.pptxgrandmarshall132
 
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证jdkhjh
 
885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Education885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Educationz xss
 
See How do animals kill their prey for food
See How do animals kill their prey for foodSee How do animals kill their prey for food
See How do animals kill their prey for fooddrsk203
 
Asexual-and-Sexual-Reproduction.huhupptx
Asexual-and-Sexual-Reproduction.huhupptxAsexual-and-Sexual-Reproduction.huhupptx
Asexual-and-Sexual-Reproduction.huhupptxMyBrightestStarParkJ
 
Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Open Access Research Paper
 
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCR
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCRCall In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCR
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCRjennyeacort
 
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhidelih Escorts
 
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girlsssuser7cb4ff
 
Perceptions and practices of rice farmers in the lowland areas of Diplahan, Z...
Perceptions and practices of rice farmers in the lowland areas of Diplahan, Z...Perceptions and practices of rice farmers in the lowland areas of Diplahan, Z...
Perceptions and practices of rice farmers in the lowland areas of Diplahan, Z...Open Access Research Paper
 
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdfsrivastavaakshat51
 
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full NightCall Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
UNIT ONE ppt history of Ethiopia and horn.pptx
UNIT ONE ppt history of Ethiopia and horn.pptxUNIT ONE ppt history of Ethiopia and horn.pptx
UNIT ONE ppt history of Ethiopia and horn.pptxzeyohannesamare
 
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...Aqsa Yasmin
 
办理德州理工大学毕业证书TTU文凭学位证书
办理德州理工大学毕业证书TTU文凭学位证书办理德州理工大学毕业证书TTU文凭学位证书
办理德州理工大学毕业证书TTU文凭学位证书zdzoqco
 

Recently uploaded (20)

Group 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdfGroup 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdf
 
Science, Technology and Nation Building.pptx
Science, Technology and Nation Building.pptxScience, Technology and Nation Building.pptx
Science, Technology and Nation Building.pptx
 
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
原版1:1复刻塔夫斯大学毕业证Tufts毕业证留信学历认证
 
885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Education885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Education
 
See How do animals kill their prey for food
See How do animals kill their prey for foodSee How do animals kill their prey for food
See How do animals kill their prey for food
 
Asexual-and-Sexual-Reproduction.huhupptx
Asexual-and-Sexual-Reproduction.huhupptxAsexual-and-Sexual-Reproduction.huhupptx
Asexual-and-Sexual-Reproduction.huhupptx
 
Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...
 
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCR
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCRCall In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCR
Call In girls Connaught Place (DELHI)⇛9711147426🔝Delhi NCR
 
PLANTILLAS DE MEMORAMA CIENCIAS NATURALES
PLANTILLAS DE MEMORAMA CIENCIAS NATURALESPLANTILLAS DE MEMORAMA CIENCIAS NATURALES
PLANTILLAS DE MEMORAMA CIENCIAS NATURALES
 
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
9873940964 Full Enjoy 24/7 Call Girls Near Shangri La’s Eros Hotel, New Delhi
 
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
 
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Serviceyoung call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
 
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
 
Perceptions and practices of rice farmers in the lowland areas of Diplahan, Z...
Perceptions and practices of rice farmers in the lowland areas of Diplahan, Z...Perceptions and practices of rice farmers in the lowland areas of Diplahan, Z...
Perceptions and practices of rice farmers in the lowland areas of Diplahan, Z...
 
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
 
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full NightCall Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
Call Girls Ahmedabad 7397865700 Ridhima Hire Me Full Night
 
UNIT ONE ppt history of Ethiopia and horn.pptx
UNIT ONE ppt history of Ethiopia and horn.pptxUNIT ONE ppt history of Ethiopia and horn.pptx
UNIT ONE ppt history of Ethiopia and horn.pptx
 
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
 
办理德州理工大学毕业证书TTU文凭学位证书
办理德州理工大学毕业证书TTU文凭学位证书办理德州理工大学毕业证书TTU文凭学位证书
办理德州理工大学毕业证书TTU文凭学位证书
 
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
 

Coal handling-guidelines

  • 1. GUIDE LINES FOR COAL HANDLING UNITS:- (A) Location criteria 1. Coal handling unit/Agency shall not use any agriculture land and shall be located at a minimum distance of 250 meters away from the surrounding agriculture land. 2. Government waste land not suitable for any agriculture purpose meeting with the requisite siting / distance criteria shall be preferred for establishing coal handling units. 3. Coal handling unit/Agency shall be minimum 500 meters away from the residential area, school/colleges, Historical Monuments, Religious Places, Ecological sensitive area as well as forests area. 4. Coal handling unit/Agency shall be located at a minimum 500 meters away from the Railway line, Express ways, National Highways, State ways and District Roads and from water bodies like River, Nala, Canal, Pond etc. 5. In case of coal handling activities at the ports and jetties or extension thereof, the distance and land use criteria may be relaxed and compensated by advanced/sophisticated pollution control measures and mechanization & thick plantation, however all such ports and jetties, where coal handling is carried out, shall provide closed conveyor belt and mechanization for handling of coal.
  • 2. (B) Storage and handling criteria 6. Coal handling unit/Agency shall store coal in such a way that coal heap should not be higher than 5 meter and clear distance between two adjoining heaps at G.L. should be 5 meters, so that in case of fire, approach is available. 7. There should be mechanized loading/ unloading system from the loading /unloading area to the stacking yards and in to the vehicles. 8. Coal handling unit/Agency shall take all corrective steps to resolve the issue of air pollution at permitted coal storage/handling area where coal is being stored. (C) Transport criteria 9. Coal handling unit/Agency shall ensure that all trucks before leaving the storage yard shall be showered with water with adequate system, Shall be covered with tarpaulin or any other effective measure/device completely and also that trucks are not over loaded as well as there is no spillage during transportation. 10.The vehicle carrying the coal should not be overloaded by raising the height of carriage. Weigh scale shall be provided within the loading area only and port / coal park authority shall ensure that no overloading is done.
  • 3. 11.The top of the vehicle should be covered with fixed cover instead of tarpaulin cover to avoid spillage or dusting of coal. 12. Coal handling unit/Agency shall obtain transport permission from the local Administration under the relevant rules. (D) Pollution prevention criteria 13. Coal handling unit/Agency shall provide paved approach with adequate traffic carrying capacity 14. Coal handling unit/Agency shall construct compound wall all along periphery of the premises with minimum 9 meters height 15. Continuous water sprinkling shall be carried out on the top of the heap at regular intervals to prevent dusting, fire & smoke. To prevent fugitive emission during loading/unloading, fixed pipe network with sufficient water storage and pump shall be installed. Water sprinkling shall be carried out at each and every stage of handling to avoid generation of coal dust or other dust within premises 16. Coal handling unit/Agency shall ensure regular sweeping of coal dust from internal and main road and also ensure that there is adequate space for free movement of vehicles. 17. The following adequate Air Pollution Control Measures shall be installed and to be operated efficiently. (a) Dust containment cum suppression system for the coal stack, loading and unloading.
  • 4. (b) Construction of effective wind breaking wall suitable to local condition to prevent the suspension of particles from the heaps. (c) Construction of metal road & RCC Pucca flooring in the plot area/ godown etc. (d) System for regular cleaning and wetting of the floor area within the premises. (e) Entire coal storage area/ godown should be covered with permanent weather shed roofing and side walls i.e., in closed shed, in case of crushing/sieving/grading activity is carried out (i.e. G. I. Sheet) along with adequate additional APCM should be installed. 18. Coal handling unit/Agency shall carryout three rows plantation with tall growing tress all along the periphery of the coal handling premises, inside & outside of the premises along with road. 19. Proper drainage system shall be provided in all coal storage area so that water drained from sprinkling & runoff is collected at a common tank and can be reused after screening through the coal slit or any other effective treatment system. 20. All the engineering control measures and state of art technology including covered conveyer belts, mechanized loading and unloading, provision of silo etc. shall be provided in addition to the measures recommended in the environmental guidelines for curbing the pollution.
  • 5. (E) Safety requirement 21. Coal handling unit/Agency shall provide adequate fire fighting measure to avoid any fire or related hazards including adequate water storage facility, and the premises shall be exclusively used for storage of the coal. 22. An onsite emergency plan shall be prepared and implemented by coal handling unit. (F) Legal criteria 23. Necessary permission from all the applicable regulatory authorities and adequate steps under the provisions of applicable environmental acts/ rules shall be taken. 24. Coal handling unit/Agency shall prepare EMP (Environment Management Plan) and implement the same in true spirit and thus maintain overall environment of that area. 25. Coal handling unit/Agency shall not carry out the operation of loading/unloading of coal/coal dust at any place, till adequate air pollution control equipment for dust control/suppression are installed and efficiently operated and the consent under the provisions of Air (Prevention & Control of Pollution) Act, 1981 is obtained by the coal yard owners/ Coal handling unit/Agency / coal importers.
  • 6. 26. Coal handling unit/Agency shall operate continuous Ambient Air Quality Monitoring Stations as per CPCB guideline. The results of parameters like SPM, RSPM, and SO2 and NOx shall be submitted to the SPCB every month. 27. In case of port which provides the facility to individual developers an agreement /MoU shall be made between port authority and developer for curtailment of pollution. Port authority shall be responsible for supervising and controlling the pollution control related activities and implementation of the environmental guidelines. 28. The concentration of the following parameters in the ambient air within the premises and a distance of 10 meters from the source (other than the stack/vent) shall not exceed the following levels. PARAMETERS PERMISSIBLE LIMIT Annual 24 Hrs Average Particulate Matter-10 (PM 10 ) 60 Microgram/M 3 100 Microgram/M 3 Particulate Matter- 2.5 (PM 2.5 ) 40 Microgram/M 3 60 Microgram/M 3 SO 2 50 Microgram/M 3 80 Microgram/M 3 NO x 40 Microgram/M 3 80 Microgram/M 3