1
Presentation On
Total Station Surveying
Binabh Devkota
binabhdevkota@gmail.com
Course: GEOM 201
Teacher: Er. Basudev Bhandari
Introduction
• Total Station
-Digital instrument
-Combination of EDM, Digital Theodolite
and microprocessor
-Angle measurement
(horizontal and vertical)
-Distance measurement
(slope, horizontal, vertical)
-Direct co-ordinates calculation
-One of the most used modern instruments
2
Terms Used In Total Station Survey
• Vertical axis: axis about which instrument can be rotated in horizontal
plane
• Horizontal(trunnion) axis: axis about which instrument can be rotated in
vertical plane
• Line of sight or line of collimation: line through intersection of cross
hairs, optical center of object glass and continued
• Swinging: rotating 180⁰ in horizontal plane about vertical axis
• Transiting: rotating 180⁰ in vertical plane about horizontal axis
• Face left/right observation: observation done when vertical circle is
left/right to observer
3
Parts of Total Station
4
Source: http://theconstructor.org/surveying/total-station-operation-uses-advantage/6605/
Temporary Adjustments
• Centering: process in which the vertical axis of the instrument is
coincided with the plumb line
• Levelling: making the vertical axis of instrument truly vertical
• focusing: adjustment of telescope to obtain clear visibility of image
through eyepiece and objective lens
5Source: http://www.usouthal.edu/geography/allison/GY301/Total%20Station%20Setup%20and%20Operation.pdf
Fundamental Measurements
• Distance
• Rotation of optical axis in horizontal
plane
• Inclination of optical axis in vertical
plane
6
Source: http://www.minesurveyor.net/equiptotalstation.php
Source: https://www.alibaba.com/product-
detail/PJK-CHEAP-NON-PRISM-TOTAL-
STATION_60297734758.html
Additional Features
• Co-ordinate Calculation
• Remote Elevation Measurement
• Missing Line Measurement
• Recording of data
7
Source:
http://www.topcon.co.jp/en/positioning/produ
cts/product/ts00/GTS-250_E.html
Source:
http://www.usouthal.edu/geography
/allison/GY301/Total%20Station%20S
etup%20and%20Operation.pdf
Applications
• Mining/Tunnelling
• Metrology
• Civil Engineering
• Control Surveying
• Topographical surveying
8
Source:
http://www.sudburyminingsolutions.com/new-
total-station-offers-scanning-capability.html
Source: https://www.zenithsurvey.co.uk/category/leica-builder/
References
• Punimia, D. B., Jain, K. A., & Jain, K. A. (2005). SURVEYING VOL. I.
Jodhpur: Laxmi Publications (P) LTD
• Hoffman, A. (2013, March 22). The Total Station & Land Surveys: A
Background Story. Retrieved October 13, 2016, from GODFREY
HOFFMAN ASSOCIATES: http://www.godfreyhoffman.com/civil-
engineering-blog/bid/278047/the-total-station-land-surveys-a-
background-story
• surveyhistory.org. (n.d.). The Surveyor's Basic Tools. Retrieved January
20, 2017, from Survey History:
http://www.surveyhistory.org/the_surveyor's_basic_tools.htm
9
10

Total station surveying

  • 1.
    1 Presentation On Total StationSurveying Binabh Devkota binabhdevkota@gmail.com Course: GEOM 201 Teacher: Er. Basudev Bhandari
  • 2.
    Introduction • Total Station -Digitalinstrument -Combination of EDM, Digital Theodolite and microprocessor -Angle measurement (horizontal and vertical) -Distance measurement (slope, horizontal, vertical) -Direct co-ordinates calculation -One of the most used modern instruments 2
  • 3.
    Terms Used InTotal Station Survey • Vertical axis: axis about which instrument can be rotated in horizontal plane • Horizontal(trunnion) axis: axis about which instrument can be rotated in vertical plane • Line of sight or line of collimation: line through intersection of cross hairs, optical center of object glass and continued • Swinging: rotating 180⁰ in horizontal plane about vertical axis • Transiting: rotating 180⁰ in vertical plane about horizontal axis • Face left/right observation: observation done when vertical circle is left/right to observer 3
  • 4.
    Parts of TotalStation 4 Source: http://theconstructor.org/surveying/total-station-operation-uses-advantage/6605/
  • 5.
    Temporary Adjustments • Centering:process in which the vertical axis of the instrument is coincided with the plumb line • Levelling: making the vertical axis of instrument truly vertical • focusing: adjustment of telescope to obtain clear visibility of image through eyepiece and objective lens 5Source: http://www.usouthal.edu/geography/allison/GY301/Total%20Station%20Setup%20and%20Operation.pdf
  • 6.
    Fundamental Measurements • Distance •Rotation of optical axis in horizontal plane • Inclination of optical axis in vertical plane 6 Source: http://www.minesurveyor.net/equiptotalstation.php Source: https://www.alibaba.com/product- detail/PJK-CHEAP-NON-PRISM-TOTAL- STATION_60297734758.html
  • 7.
    Additional Features • Co-ordinateCalculation • Remote Elevation Measurement • Missing Line Measurement • Recording of data 7 Source: http://www.topcon.co.jp/en/positioning/produ cts/product/ts00/GTS-250_E.html Source: http://www.usouthal.edu/geography /allison/GY301/Total%20Station%20S etup%20and%20Operation.pdf
  • 8.
    Applications • Mining/Tunnelling • Metrology •Civil Engineering • Control Surveying • Topographical surveying 8 Source: http://www.sudburyminingsolutions.com/new- total-station-offers-scanning-capability.html Source: https://www.zenithsurvey.co.uk/category/leica-builder/
  • 9.
    References • Punimia, D.B., Jain, K. A., & Jain, K. A. (2005). SURVEYING VOL. I. Jodhpur: Laxmi Publications (P) LTD • Hoffman, A. (2013, March 22). The Total Station & Land Surveys: A Background Story. Retrieved October 13, 2016, from GODFREY HOFFMAN ASSOCIATES: http://www.godfreyhoffman.com/civil- engineering-blog/bid/278047/the-total-station-land-surveys-a- background-story • surveyhistory.org. (n.d.). The Surveyor's Basic Tools. Retrieved January 20, 2017, from Survey History: http://www.surveyhistory.org/the_surveyor's_basic_tools.htm 9
  • 10.