SlideShare a Scribd company logo
1 of 4
Download to read offline
Design of Roof Drainage System By: Ayaz Malik
Length of the Roof Panel, L = 292 ft
Plan Width of the Roof Panel, W = 124 ft
Pitch of the Roof, x = 1 in 12
Design Area for Pitched Roofs
When a roof is pitched, its plan area is less than its true area. However, using the true area in the
calculations has typically resulted in oversized gutters, downspouts and drains. Table below shows
the factors that should be used to determine the design area for pitched roofs. The plan roof area
should be multiplied by this factor. The result is the design roof area that is used to calculate the
required sizes of downspouts.
from upto
0 3 1.00
4 5 1.05
6 8 1.10
9 11 1.20
12 > 12 1.30
Roof-pitch factor, F = 1.00
Down Spout and Gutter Design
Roof drainage systems are designed to carry off rainwater from the most intense rainfall that is likely
to occur. A certain amount of time is required for the rainwater to flow across and down the roof
before it enters the gutter or drainage system. This resulst in the smoothing out of the most rapid
changes in rainfall intensity. The drainage system, therefore, need only cope with the flow of
rainwater produced by the average rainfall intensity over a period of few minutes, which can be
called the concentration time.
As per NBC 2010, Division B, Appendix C, it has been customoary in Canada to use the 15-minute
rainfall that will probably be exceeded on an average of once in 10 years.
Area
Factor
Pitch, in. /12 in.
x
Assumption:
· Rainfall intensity is measured over a 15-minute period. It is recorded in mm/hour as the resulting
accumulation, as if the intensity remained constant for a full hour.
· It is assumed that during a rainfall with an intensity of 1 in. per hour, each in 2
of downspout can
drain 1200 ft2
of roof. If the intensity is doubled, the downspout capacity is halved, or 600 ft 2
, if it is
tripled the capacity is one-third, and so on.
Downspout Design:
Length of gutter per downspout = 40 ft
(Note: each downspout should drain a maximum of 50 ft. of gutter)
Plan Area of Roof, A = 4960 ft2
Roof Area to be drained, A x F = 4960 ft2
As per NBC 2010, Division B, Appendix C, Table C-2, for Fort McMurray,
Rainfall intensity = 13.00 mm/15 min.
= 52.00 mm/ hour
= 2.05 in./hour
For rainfall intensity of 2.05 in./hour, we have
Area drained per in2
of downspout = 586.15 ft2
/in2
Required area of each downspout = 8.46 in2
(Governs)
Minimum recommended area of each downspout = 7.00 in2
From the table provided in the end, we have following design choices:
1- 4 in. Dia. Plain Round
2- 4 in. Corrugated Round
3- 4 in. Plain Rectangular
4- 4 in. Corrugated Rectangular
Gutter Design
Ratio of Gutter depth to width, M = 0.50
Area to be drained, A = 4960.00 ft2
Rainfall intensity,I = 2.05 in./hour
Length of the Gutter, L = 40 ft
I x A = 10154 ft2
. in./hour
In the chart provided in the end, find the vertical line representing L, proceed
vertically along this line to its intersection with the oblique line representing M, then move horizontally
to intersect the vertical line representing IA. The point of intersection gives the required width of
the gutter.
Width of the gutter (from chart) = 8 in.
Depth of the gutter = 4 in.
Dimensions of Standard Downspouts

More Related Content

What's hot

Bridge architecture and economic sapn 1
Bridge architecture and economic sapn 1Bridge architecture and economic sapn 1
Bridge architecture and economic sapn 1SaadKhot1
 
variation in demand of water
variation in demand of water variation in demand of water
variation in demand of water Hayat khan
 
Cement stabilization of soils ppt
Cement stabilization of soils pptCement stabilization of soils ppt
Cement stabilization of soils pptVeluppillai Mohan
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavementBhavik A Shah
 
Concrete mcq with ans.pdf
Concrete mcq with ans.pdfConcrete mcq with ans.pdf
Concrete mcq with ans.pdfRoshani Shahi
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement TechniquesNilesh Bhosale
 
Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibrationAnjana R Menon
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavementspradip dangar
 
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Make Mannan
 
Water resources planning and development m5
Water resources planning and development m5Water resources planning and development m5
Water resources planning and development m5Bibhabasu Mohanty
 
ppt on pavement design
ppt on pavement designppt on pavement design
ppt on pavement designRohit Ranjan
 
Soil compaction and effects on soil properties
Soil compaction and effects on soil propertiesSoil compaction and effects on soil properties
Soil compaction and effects on soil propertiespremsai05
 
Design of Lift Irrigation System- Angar as A Case Study
Design of Lift Irrigation System- Angar as A Case StudyDesign of Lift Irrigation System- Angar as A Case Study
Design of Lift Irrigation System- Angar as A Case StudyIRJET Journal
 

What's hot (20)

Embankment
EmbankmentEmbankment
Embankment
 
Road Aggregates
Road AggregatesRoad Aggregates
Road Aggregates
 
Bridge architecture and economic sapn 1
Bridge architecture and economic sapn 1Bridge architecture and economic sapn 1
Bridge architecture and economic sapn 1
 
variation in demand of water
variation in demand of water variation in demand of water
variation in demand of water
 
Cement stabilization of soils ppt
Cement stabilization of soils pptCement stabilization of soils ppt
Cement stabilization of soils ppt
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
 
Concrete mcq with ans.pdf
Concrete mcq with ans.pdfConcrete mcq with ans.pdf
Concrete mcq with ans.pdf
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement Techniques
 
Ground improvement techniques compaction vibration
Ground improvement techniques  compaction vibrationGround improvement techniques  compaction vibration
Ground improvement techniques compaction vibration
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
 
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
 
6. road & highways
6. road & highways6. road & highways
6. road & highways
 
Water resources planning and development m5
Water resources planning and development m5Water resources planning and development m5
Water resources planning and development m5
 
water demand Problems and solutions
water demand Problems and solutionswater demand Problems and solutions
water demand Problems and solutions
 
ppt on pavement design
ppt on pavement designppt on pavement design
ppt on pavement design
 
Soil compaction and effects on soil properties
Soil compaction and effects on soil propertiesSoil compaction and effects on soil properties
Soil compaction and effects on soil properties
 
Design of Lift Irrigation System- Angar as A Case Study
Design of Lift Irrigation System- Angar as A Case StudyDesign of Lift Irrigation System- Angar as A Case Study
Design of Lift Irrigation System- Angar as A Case Study
 
Reservior planning
Reservior    planningReservior    planning
Reservior planning
 
Sub grade preperation
Sub grade preperationSub grade preperation
Sub grade preperation
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 

Viewers also liked

Stormwater management presentation slides
Stormwater management presentation slidesStormwater management presentation slides
Stormwater management presentation slidesDoreen Yeo
 
Drainage system
Drainage systemDrainage system
Drainage systemNikhil Jp
 
Roof drain Systems
Roof drain SystemsRoof drain Systems
Roof drain Systemsatecotanks
 
CV (KYUYOUNG, HAN)(DMEC)
CV (KYUYOUNG, HAN)(DMEC)CV (KYUYOUNG, HAN)(DMEC)
CV (KYUYOUNG, HAN)(DMEC)KYUYOUNG HAN
 
DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...
DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...
DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...IAEME Publication
 
Denver, Colorado's Flood Control District Reflection on the Floods of 2013 - ...
Denver, Colorado's Flood Control District Reflection on the Floods of 2013 - ...Denver, Colorado's Flood Control District Reflection on the Floods of 2013 - ...
Denver, Colorado's Flood Control District Reflection on the Floods of 2013 - ...rshimoda2014
 
Designing Sustainable Drainage Systems
Designing Sustainable Drainage SystemsDesigning Sustainable Drainage Systems
Designing Sustainable Drainage SystemsJo-fai Chow
 
Towards A Sustainable Drainage Solution
Towards A Sustainable Drainage SolutionTowards A Sustainable Drainage Solution
Towards A Sustainable Drainage Solutionceal2005
 
Analysis and design of an efficient drainage system in Chittagong city
Analysis and design of an efficient  drainage system in Chittagong cityAnalysis and design of an efficient  drainage system in Chittagong city
Analysis and design of an efficient drainage system in Chittagong citySabbir . Ahmmed
 
CIVIL KNOWLEDGE_HUB-MITS
CIVIL KNOWLEDGE_HUB-MITSCIVIL KNOWLEDGE_HUB-MITS
CIVIL KNOWLEDGE_HUB-MITSRavi Rao
 
Sewer appurtenances
Sewer appurtenancesSewer appurtenances
Sewer appurtenancesgrangdenn
 
Basics hydraulics
Basics hydraulicsBasics hydraulics
Basics hydraulicsGovind Samy
 
Water Supply and Sewerage Design
Water Supply and Sewerage DesignWater Supply and Sewerage Design
Water Supply and Sewerage DesignJeremy Molayem
 
Hydrology and hydraulics for design design
Hydrology and hydraulics for design designHydrology and hydraulics for design design
Hydrology and hydraulics for design designavirup naskar
 
Sem 2 bs1 storm water system
Sem 2 bs1 storm water systemSem 2 bs1 storm water system
Sem 2 bs1 storm water systemEst
 
Estimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage dischargeEstimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage dischargeAnkit Gola
 

Viewers also liked (20)

Stormwater management presentation slides
Stormwater management presentation slidesStormwater management presentation slides
Stormwater management presentation slides
 
Drainage system
Drainage systemDrainage system
Drainage system
 
Roof drain Systems
Roof drain SystemsRoof drain Systems
Roof drain Systems
 
CV (KYUYOUNG, HAN)(DMEC)
CV (KYUYOUNG, HAN)(DMEC)CV (KYUYOUNG, HAN)(DMEC)
CV (KYUYOUNG, HAN)(DMEC)
 
DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...
DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...
DESIGN A HYDRAULIC STRUCTURE USING THE RAINFALL INTENSITY- DURATION- FREQUENC...
 
Sewerage network
Sewerage networkSewerage network
Sewerage network
 
Denver, Colorado's Flood Control District Reflection on the Floods of 2013 - ...
Denver, Colorado's Flood Control District Reflection on the Floods of 2013 - ...Denver, Colorado's Flood Control District Reflection on the Floods of 2013 - ...
Denver, Colorado's Flood Control District Reflection on the Floods of 2013 - ...
 
Designing Sustainable Drainage Systems
Designing Sustainable Drainage SystemsDesigning Sustainable Drainage Systems
Designing Sustainable Drainage Systems
 
Towards A Sustainable Drainage Solution
Towards A Sustainable Drainage SolutionTowards A Sustainable Drainage Solution
Towards A Sustainable Drainage Solution
 
Sewrage
Sewrage Sewrage
Sewrage
 
Analysis and design of an efficient drainage system in Chittagong city
Analysis and design of an efficient  drainage system in Chittagong cityAnalysis and design of an efficient  drainage system in Chittagong city
Analysis and design of an efficient drainage system in Chittagong city
 
CIVIL KNOWLEDGE_HUB-MITS
CIVIL KNOWLEDGE_HUB-MITSCIVIL KNOWLEDGE_HUB-MITS
CIVIL KNOWLEDGE_HUB-MITS
 
Sewer appurtenances
Sewer appurtenancesSewer appurtenances
Sewer appurtenances
 
L 5and l-6 sewer design
L 5and l-6 sewer designL 5and l-6 sewer design
L 5and l-6 sewer design
 
Basics hydraulics
Basics hydraulicsBasics hydraulics
Basics hydraulics
 
Water Supply and Sewerage Design
Water Supply and Sewerage DesignWater Supply and Sewerage Design
Water Supply and Sewerage Design
 
Hydrology and hydraulics for design design
Hydrology and hydraulics for design designHydrology and hydraulics for design design
Hydrology and hydraulics for design design
 
Sewer Appurtanances
Sewer AppurtanancesSewer Appurtanances
Sewer Appurtanances
 
Sem 2 bs1 storm water system
Sem 2 bs1 storm water systemSem 2 bs1 storm water system
Sem 2 bs1 storm water system
 
Estimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage dischargeEstimating sewage discharge and peak drainage discharge
Estimating sewage discharge and peak drainage discharge
 

Similar to Roof Drainage Design for 292 ft by 124 ft Pitch Roof

Storm drainage design
Storm drainage designStorm drainage design
Storm drainage designdobariya axit
 
Airport drainage
Airport drainageAirport drainage
Airport drainagejagadish108
 
Pump station design manual
Pump station design manualPump station design manual
Pump station design manualFrancis Mitchell
 
Drainage Engineering (Drainage and design of drainage systems)
Drainage Engineering (Drainage and design of drainage systems)Drainage Engineering (Drainage and design of drainage systems)
Drainage Engineering (Drainage and design of drainage systems)Latif Hyder Wadho
 
drainage-engineering-ppt.pdf
drainage-engineering-ppt.pdfdrainage-engineering-ppt.pdf
drainage-engineering-ppt.pdfPkSong
 
Deck drainage design
Deck drainage designDeck drainage design
Deck drainage designSarita Joshi
 
5-Runoff computation (2).ppt
5-Runoff computation (2).ppt5-Runoff computation (2).ppt
5-Runoff computation (2).pptJohnAyele
 
PBL on Energy Conservation with Rainwater Harvesting
PBL on Energy Conservation with Rainwater HarvestingPBL on Energy Conservation with Rainwater Harvesting
PBL on Energy Conservation with Rainwater HarvestingS K
 
Machine Routing And Channel Design Assignment
Machine Routing And Channel Design AssignmentMachine Routing And Channel Design Assignment
Machine Routing And Channel Design AssignmentBHAGCHAND MEENA
 
Presentation 7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...
Presentation  7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...Presentation  7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...
Presentation 7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...World University of Bangladesh
 
DUCT FORMULA Design-2006.pptx
DUCT FORMULA Design-2006.pptxDUCT FORMULA Design-2006.pptx
DUCT FORMULA Design-2006.pptxPraveenMGowdru
 
sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenanceManish Goyal
 
HEAT LOAD EDITED.pdf
HEAT LOAD EDITED.pdfHEAT LOAD EDITED.pdf
HEAT LOAD EDITED.pdfTushar931051
 

Similar to Roof Drainage Design for 292 ft by 124 ft Pitch Roof (20)

Storm drainage design
Storm drainage designStorm drainage design
Storm drainage design
 
Airport drainage
Airport drainageAirport drainage
Airport drainage
 
Airport drainage
Airport drainageAirport drainage
Airport drainage
 
WATERSHED CATCHMENT.pdf
WATERSHED CATCHMENT.pdfWATERSHED CATCHMENT.pdf
WATERSHED CATCHMENT.pdf
 
Pump station design manual
Pump station design manualPump station design manual
Pump station design manual
 
Poster
PosterPoster
Poster
 
Drainage Engineering (Drainage and design of drainage systems)
Drainage Engineering (Drainage and design of drainage systems)Drainage Engineering (Drainage and design of drainage systems)
Drainage Engineering (Drainage and design of drainage systems)
 
drainage-engineering-ppt.pdf
drainage-engineering-ppt.pdfdrainage-engineering-ppt.pdf
drainage-engineering-ppt.pdf
 
Deck drainage design
Deck drainage designDeck drainage design
Deck drainage design
 
5-Runoff computation (2).ppt
5-Runoff computation (2).ppt5-Runoff computation (2).ppt
5-Runoff computation (2).ppt
 
PBL on Energy Conservation with Rainwater Harvesting
PBL on Energy Conservation with Rainwater HarvestingPBL on Energy Conservation with Rainwater Harvesting
PBL on Energy Conservation with Rainwater Harvesting
 
Drainage design
Drainage designDrainage design
Drainage design
 
Machine Routing And Channel Design Assignment
Machine Routing And Channel Design AssignmentMachine Routing And Channel Design Assignment
Machine Routing And Channel Design Assignment
 
WATERSHED CATCHMENT.pptx
WATERSHED CATCHMENT.pptxWATERSHED CATCHMENT.pptx
WATERSHED CATCHMENT.pptx
 
Presentation 7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...
Presentation  7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...Presentation  7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...
Presentation 7 a ce 904 Hydrology by Rabindra Ranjan Saha, PEng, Associate P...
 
DUCT FORMULA Design-2006.pptx
DUCT FORMULA Design-2006.pptxDUCT FORMULA Design-2006.pptx
DUCT FORMULA Design-2006.pptx
 
sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenance
 
HEAT LOAD EDITED.pdf
HEAT LOAD EDITED.pdfHEAT LOAD EDITED.pdf
HEAT LOAD EDITED.pdf
 
M.i tank
M.i  tankM.i  tank
M.i tank
 
RP-BRIDGE HYDRAULICS.pptx
RP-BRIDGE HYDRAULICS.pptxRP-BRIDGE HYDRAULICS.pptx
RP-BRIDGE HYDRAULICS.pptx
 

Recently uploaded

The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsDILIPKUMARMONDAL6
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptxNikhil Raut
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESNarmatha D
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 

Recently uploaded (20)

The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teams
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Steel Structures - Building technology.pptx
Steel Structures - Building technology.pptxSteel Structures - Building technology.pptx
Steel Structures - Building technology.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIES
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 

Roof Drainage Design for 292 ft by 124 ft Pitch Roof

  • 1. Design of Roof Drainage System By: Ayaz Malik Length of the Roof Panel, L = 292 ft Plan Width of the Roof Panel, W = 124 ft Pitch of the Roof, x = 1 in 12 Design Area for Pitched Roofs When a roof is pitched, its plan area is less than its true area. However, using the true area in the calculations has typically resulted in oversized gutters, downspouts and drains. Table below shows the factors that should be used to determine the design area for pitched roofs. The plan roof area should be multiplied by this factor. The result is the design roof area that is used to calculate the required sizes of downspouts. from upto 0 3 1.00 4 5 1.05 6 8 1.10 9 11 1.20 12 > 12 1.30 Roof-pitch factor, F = 1.00 Down Spout and Gutter Design Roof drainage systems are designed to carry off rainwater from the most intense rainfall that is likely to occur. A certain amount of time is required for the rainwater to flow across and down the roof before it enters the gutter or drainage system. This resulst in the smoothing out of the most rapid changes in rainfall intensity. The drainage system, therefore, need only cope with the flow of rainwater produced by the average rainfall intensity over a period of few minutes, which can be called the concentration time. As per NBC 2010, Division B, Appendix C, it has been customoary in Canada to use the 15-minute rainfall that will probably be exceeded on an average of once in 10 years. Area Factor Pitch, in. /12 in. x
  • 2. Assumption: · Rainfall intensity is measured over a 15-minute period. It is recorded in mm/hour as the resulting accumulation, as if the intensity remained constant for a full hour. · It is assumed that during a rainfall with an intensity of 1 in. per hour, each in 2 of downspout can drain 1200 ft2 of roof. If the intensity is doubled, the downspout capacity is halved, or 600 ft 2 , if it is tripled the capacity is one-third, and so on. Downspout Design: Length of gutter per downspout = 40 ft (Note: each downspout should drain a maximum of 50 ft. of gutter) Plan Area of Roof, A = 4960 ft2 Roof Area to be drained, A x F = 4960 ft2 As per NBC 2010, Division B, Appendix C, Table C-2, for Fort McMurray, Rainfall intensity = 13.00 mm/15 min. = 52.00 mm/ hour = 2.05 in./hour For rainfall intensity of 2.05 in./hour, we have Area drained per in2 of downspout = 586.15 ft2 /in2 Required area of each downspout = 8.46 in2 (Governs) Minimum recommended area of each downspout = 7.00 in2 From the table provided in the end, we have following design choices: 1- 4 in. Dia. Plain Round 2- 4 in. Corrugated Round 3- 4 in. Plain Rectangular 4- 4 in. Corrugated Rectangular Gutter Design Ratio of Gutter depth to width, M = 0.50 Area to be drained, A = 4960.00 ft2 Rainfall intensity,I = 2.05 in./hour Length of the Gutter, L = 40 ft I x A = 10154 ft2 . in./hour In the chart provided in the end, find the vertical line representing L, proceed vertically along this line to its intersection with the oblique line representing M, then move horizontally to intersect the vertical line representing IA. The point of intersection gives the required width of the gutter. Width of the gutter (from chart) = 8 in. Depth of the gutter = 4 in.
  • 3.