SlideShare a Scribd company logo
1 of 70
Kite Hill Stormwater
Management
C. Bury, J. Davis, A. Hough, R. Middlewarth, J. Ossorio
Clemson University - Biosystems Engineering
BE 4750 Fall 2015 Senior Design Presentation
November 23, 2015
Table of Contents
1. Introducing the Problem
a. Kite Hill Impact on Hunnicutt Creek
2. Project Assessment
a. Defining problem, goals, constraints, considerations, and design
elements
3. Design Elements
a. Area of Interest
b. Existing Conditions
c. Design and Methodology
d. Cost Estimation
e. Design Comparisons
4. Sustainability Measures
5. Conclusion
Introduction
http://www.clemson.edu/public/hunnicutt/about.html
Google Maps
Clemson Subdrainage Exhibit
Recognition of Problem
Stormwater runoff results in
● Heavy peak flows
Sediment transport / erosion
● Pollution transportation
● Destruction of downstream ecology of Hunnicutt Creek
watershed
C. Bury
C. Bury
C. BuryC. BuryC. Bury
C. Bury C. Bury
C. Bury
Project Assessment
Define Problem
Lack of infiltration
Pollution runoff
Damage to Hunnicutt Creek
Goals of the Project
Biological: Treat stormwater pollutants
before entering Hunnicutt Creek
Structural: Reduce peak flows and
runoff velocity of stormwater for a 10 yr
- 24 hr storm event
http://www.cnyhiking.com/NCTinPA-MinisterCreekTrail892.jpg
Constraints and Considerations
Constraints
Existing Infrastructure
Future Construction
http://fisheyestudios.com/gallery-categories/aerial/
Considerations
Safety
Entering for maintenance
Safety around the area
Sustainability
Minimal maintenance
Durable design options
Aesthetics
Budget
3 Questions
User - Clemson University
1. Is this going to limit where people can park on campus?
2. How much maintenance is required? What does this entail?
3. Will the design be aesthetically pleasing?
Client - Clemson University Facilities, Subcontractor/Developer
1. Can the design system elements be implemented at different times?
2. What is the approximate cost of the design and installation of the project?
3. What is the expected lifetime of the structures and systems being proposed?
Designer - Stormwater Project Team
1. What regulations must we work within?
2. Is the design system resilient?
3. What funding is available for this project? What requirements would need to be met for this design to be implemented?
http://www.sciway.net/sc-photos/wp-content/uploads/tillman-hall-clemson1.jpg
Elements of Design
● Kite Hill Erosion Control
● Parking Lot Median
BMPs
● Enhanced Swale
● End of Pipe BMPs
Basemap: Google Maps; Highlighted Areas: J. Davis
Kite Hill Erosion Control
Area
Section
Area of
Section
(ft2)
Slope
Percent
1 4239 12.9 %
2 2922 22.4 %
3 6033 10.6 %
4 8908 10.5 %
5 11325 3 %
6 5097 19 %
7 11848 5.6 %
8 6938 17 %
Source: Basemap: Google Maps; Area Analysis: J. Ossorio
Hill Redesign:Sub-Goals and Area of Interest
Area
Section
Area of
Section
(ft2)
Slope
Percent
9 4557 8.9 %
10 3236 18 %
11 3589 8 %
12 4642 15.1 %
13 3819 26.8 %
14 4729 9.6 %
15 5309 20.4%
16 4722 18.22 %
Goals:
1. Reduce Erosion from Kite Hill by 75% per yr
2. Safe Driving Option: Gameday parking
3. Reduce Runoff Rate by 25 % for a 25 yr- 24 hr storm
Existing Conditions
Universal Soil Loss Equation
(RUSLE): T= R*K*LS*VM
R- Rain factor = 250 (Pickens, SC)
K- Soil Erodibility Factor = 0.17 (Web Soil Survey)
VM- Vegetative Mulch
LS- Length Slope Factor = (Calculated separately for each area)
Estimated Soil Loss
T=(250)*(.17)*(.34)*(2.12) = 9.37 tons/ acre/ year
9.37 tons/ acre/ yr *2.601 acres = 24.39 tons =
22.13 tonnes of SOIL LOSS per
year
Erosion Estimation Runoff Volume Estimates
Soil-Cover Complex Method
CN- Weighted Curve Number = 62.8 for Sod and Mulch
P- Rainfall for 25 yr -24 hr storm = 6.77 in (Rain Data obtained
from Tony Putnam)
S- Surface Storage
Q- Runoff
Vr- Volume of Runoff
S = (1000/CN)-10 = 5.92 in
Q= (P - 0.2S)2/(P + 0.8S) = 2.95 in of runoff
Vr = 2.95 in * (2.60 acres) = 27335 ft3 =
774 m3 of Runoff during a 25 yr
- 24 hr storm
Existing Conditions
Photo Credit: Conor Bury, 2015
Runoff Flow Rate Estimates
Peak Runoff Rate
Qp = qp*A*Q
Q = 2.95 in
S = 5.92 in
tL= L0.8(S +1) 0.7/(1900γ0.5)
tc = tL/0.6
Weighted qp = 1.543 (cfs/ac-in)
Qp= (1.543 cfs/ac-in *2.95 in *2.60 ac = 11.6cfs
= 0.329 m3/s is the FLOW
RATE of Runoff during a 25 yr
-24 hr Storm
Design 1 - Hillside Terrace
Benches are covered with grass (9600 ft2) and the Risers
are covered with liriope and straw mulch (1790 ft2 = 1020
plants). The Cut and Fill Volume is 385 cu. yd
Erosion Reduction:
Soil Delivery Ratio Method for Slope 14-16%
Reduce Soil Loss per year from 24.39 tons to 1.95 tons
92 % reduction in erosion for overall AOI.
Runoff Volume:
Soil Cover Complex Method Weighted CN 65.2 to 61
Reduce Runoff Volume for a 25 yr- 24 yr storm from 7173 ft3
to 6171 ft3,
13.96 % reduce volume for the hillside area and 3.4 % for total
AOI.
Runoff Peak Flow Rate:
Peak Runoff Rate
Reduce Flow Rate from 3.48 cfs to 2.61 cfs for the hillside
area
25.18 % reduction in Peak Flow Rate.
Design Specs (Determined using Agricultural Terrace Design)
Direction 1: Length 49 ft, 14 %, 0.44 ac
Direction 2: Length 60 ft, 16.5 %, 0.2 ac
Terraces include: 2 benches (14.76 ft),
3 risers (1:1) 2.83 ft depth
Source: Basemap: Google Maps; Area Analysis: J. Ossorio
Source: Chap. 5 Physical Methods for
Erosion Control
Design 2 - Hillside Vegetative Cover
Hillside is covered with juniper plants and straw mulch,
but any shrub-like plants can be used for hillside cover.
Erosion Reduction:
Revised Universal Soil Loss Equation Weighted VM from 0.12 to
0.012 (Canopy of Bushes 25% and 80% grass cover)
Reduce Soil Loss per year from 7.5 tons to 1.27 tons
88.6 % reduction in erosion for the hillside area and 27%
reduction for ENTIRE AOI.
Runoff Volume:
Soil Cover Complex Method for Weighted CN from 65.2 to 48
Reduce Runoff Volume for a 25 yr- 24 yr storm from 7173 ft3 to
3339 ft3
53.4% reduce volume for the hillside area and 12.9 % for total
AOI.
Runoff Peak Flow Rate:
Peak Runoff Rate
Reduce Flow Rate from 3.48 cfs to 1.38 cfs for the hillside area
60.44% reduction in Peak Flow Rate.
Source: Basemap: Google Maps; Area Analysis: J. Ossorio
Design Specs:
Direction 1: Length 49 ft, 14 %, 0.44 ac
Direction 2: Length 60 ft, 16.5 %, 0.2 ac
Juniper Spacing: 6 ft (~1030 plants)
http://2minutegardener.blogspot.com/2011/12/p
hoto-creeping-myoporum-myoporum.html
Curb and sidewalk removal to add ramp
way (located 425 ft from Perimeter Road
corner)
Area: 1,588 ft2
Width of 60 ft by 25 ft
Design Driving Options
Source: Basemap: Google Maps; Area Analysis: J. Ossorio
Driveway already exists, but the proposal is to allow
access to this entrance after hours by changing
Recycling Center enclosure
New Fencing: 500 ft
Gate Removal: 53 ft
Existing Driveway at Recycling Center Semi-Driveway on Highway 76
Source: Basemap: Google Maps; Area Analysis: J. Ossorio
Kite Hill Erosion Control Budget
Kite Hill Erosion Control Budget
Kite Hill Erosion Reduction: Design Comparison
Hillside Redesign
Terraced Side ($25,630.00)
Pros
-Reduce erosion by 92 %
-Reduce Runoff Volume by 14%
-Reduce Runoff Velocity by 26 %
- Discourages driving on the hillside
-Instant functionality
Cons
-Has some maintenance once established (mulch and cut grass)
-Heavy Construction
Driving Options
Existing Drive at Recycling Center ($7,657.00)
Pros
- Fence is already needed for area
-Already developed Drive
Cons
-Heavy traffic around Recycling Center
Vegetative Cover ($27,542.00)
Pros
-Reduce erosion by 27% overall and 89% for the Area
-Reduce Runoff Volume by 13 % overall and 54 % for Area
-Reduce Runoff Velocity by 61%
- Discourages driving on the hillside
- Low maintenance after establishment
Cons
-3 year establishment
-Cannot Handle foot or car traffic slow recovery
Semi Drive on Highway 76 ($6,811.00)
Pros
-Allows for safer option for drivers who ride of curb on gameday
-Minimal space to preserve Green Space
-Two Entrances and Exits
Cons
-Additional Traffic on game day
Parking Lot Median BMPs
Median BMPs: Sub-Goals and Area of Interest
1. Reduce the Velocity of Runoff
2. Allow Infiltration into Medians
3. Prevent Sediment Loss
7
7
123
4
5
6
7
Source: Google Maps
Area
(ft2)
Slope (%)
H.
Slope (%)
V.
1 4145 10.8 1.0
2 6603 4.2 0.9
3 9944 6.7 0.8
4 10,008 6.1 1.0
5 7917 6.4 1.2
6 7491 5.9 1.4
7 6469 5.0 1.6
Runoff Volume Parking Lot Estimates
Soil-Cover Complex Method
CN - Curve Number = 92 (Commercial Parking Lot, HSG B, 85% Impervious Area)
P- Rainfall for 25 yr -24 hr storm = 6.77 in (Rain Data obtained from Tony Putnam)
S = (1000/CN)-10 = 0.87 in
Q= (P - 0.2S)2/(P + 0.8S) = 5.83 in of runoff
Vr = 5.83 in * (1.21 acres) = 25,534 ft3
723 m3 of runoff during a 25 yr - 24 hr storm
Peak Runoff Rate
Qp = qp*A*Q
Q = 5.83 in
S = 0.87 in
tL= L0.8(S +1) 0.7/(1900γ0.5)
tc = tL/0.6
Average qp = 0.86 (cfs/ac-in)
Qp= (1.2 cfs/ac-in * 5.83 in * 0.41 ac) = 2.88 cfs
0.546 m3/s flow rate of runoff during a 25 yr -
24 hr storm
Photo credit: Conor Bury
Design 1 - Vegetated Filter Strip
Area
(ft2)
Slope
(%)
Q
(cfs)
Bottom
Width (ft)
Top
Width (ft)
y (ft)
Velocity
(ft/s)
1 17,966 1 2.88 1.67 2.51 0.83 1.01
2 26,107 0.9 2.96 1.72 2.59 0.86 0.98
3 34,173 0.8 3.88 1.95 2.92 0.97 1.00
4 30,072 1 2.01 1.46 2.19 0.73 0.93
5 23,298 1.2 2.80 1.60 2.40 0.80 1.08
6 20,170 1.4 2.42 1.47 2.21 0.73 1.10
7 18,212 1.6 1.94 1.32 1.98 0.66 1.09
Q = (k/n)*Rh
(⅔)*A*So
(½)
n: Gauckler-Manning’s coefficient
tall vegetation - 12 to 24 inches: 0.08
trapezoidal channel design
0.25 (H:V - 4:1)
height of trapezoid is equal to bottom width
tree removal
curb stops
retaining wall pavers
fill dirt, soil and compost mixture,
plant with liriope and
bermuda
create berm
gravel, compost, soil and mulch layer
with native plants
Source: http://www.watershedmanagement.vt.gov/stormwater/htm/sw_gi_bmp_bioretention.htmSource: Ashleigh Hough
Design 2 - Erosion Mat
T= R*K*LS*VM
R - Rain factor = 250 (Pickens, SC)
K - Soil Erodibility Factor = 0.17 (Web Soil Survey)
LS - Length Slope Factor
VM (before) =0.9 (rough, irregular bare soil)
VM (after) = 0.08 (coconut mat)
Before After
VM factor - 0.9 VM factor - 0.08
29.7 tonnes/year 2.6 tonnes/year
● curb stops
● seeding (bermuda grass)
live stakes (Miscanthus)
source: http://www.in.gov/legislative/iac/20120404-IR-312120154NRA.xml.html
source: http://www.hgtvgardens.com/flowers-and-
plants/maiden-grass-miscanthus-sinensis-morning-
light
Medians Budget
Medians
Design Comparison
Vegetative Strip with Rain Garden
Pros
- Nearly all runoff that enters swale infiltrates
back into the ground
- Greatly reduces erosion
- Slows down velocity of stormwater
- Removes pollutants
- More permanent solution
Cons
- Eliminates most trees
- Failure issues of pavers
- Maintenance
- Expensive
Coconut Mat
Pros
- Slows down the velocity of stormwater
- Reduces erosion by 91%
- Allows for trees to stay
- Biodegradable mats
- Less expensive
Cons
- Temporary solution (possibly)
- Maintenance
- Less pollutant removal
Flow Diversion and
Enhanced Swale
Flow Diversion Techniques
Flow Diversion Options:
Concrete cut with apron & stabilization
Grated Trench Drain
Photo Credit: Conor Bury, 2015 Source: Basemap: Google Maps; Area Analysis: R. Middleswarth
Curb Cut with Apron
Divert flow into swale
Must set stabilizers and apron
Concrete
GCL
Erosion Mat
Source: www.lastreetblog.org
source: http://www.beinginplace.org
Grated Trench Drain
Source: www.trenchdrainsupply.com
Hill Area
Section
Area of
Section (A)
[m2]
Coefficient of
runoff (C )
Rainfall
Intensity (I)
[m/s]
Volumetric
Flowrate (Qreq)
[m3/s]
1 393.8 ..35 5.6E-05 0.1332
2 271.5
3 560.5
4 827.6
Driveway 432.0 .95
Total 2485.3
Grated Trench Drain
Qreq=(k*A*R2/3*S1/2)/n
Qreq - volumetric flowrate
k - conversion from Eng to SI
A - cross sectional area of drain
R - Hydraulic Radius
S- Slope
n - coefficient of friction
Solve for WIDTH
Cross
Sectional
Area (m2)
Hydraulic
Radius (R )
[m]
Slope
Volumetric
Flowrate (Q)
[m3/s]
Coefficient
of Friction
(n)
Base Width (b)
[m]
Peak
Capacity
Depth (h) [m]
0.062 0.198 0.020 0.133 0.013 0.352 0.176
Finding Peak Flowrate and Volume
Peak Runoff Rate
Qn = qp*A*Qx
Qx = runoff depth
qp - peak discharge coefficient
S = (1000/CN)-10
tL= L0.8(S +1) 0.7/(1900γ0.5)
tc = tL/0.6
L - Hydraulic Length
y - slope
Soil-Cover Complex Method
S = (1000/CN)-10
CN - Curve Number
P- Rainfall for 25 yr -24 hr storm = 6.77 in (Rain Data
obtained from Tony Putnam)
Qx = (P - 0.2Sn)2/(P + 0.8Sn)
∑Q*Area = total volume of runoff
43,847 ft3 of runoff during a 25 yr - 24
hr storm
Peak Runoff Average
Qdesign =∑(Qn*(Vn/VTOTAL))
V - Volume of basin
Q - Peak Runoff Rate of Basin
7.95 cfs flow rate of runoff during a 25
yr - 24 hr storm
Enhanced Swale Design
500ft stretch options:
Grassy Swale
Check Dam Swale
Must Handle a Peak Storm of:
7.95 ft3/s flow rate
43,848 ft3 volume
Source: Basemap: Google Maps; Area Analysis: R. Middleswarth
Peak Runoff Rate
A = b*y + z*y2
A = b*0.1 + 0.25*0.12
R = A/(b + 2*0.1*0.25)
Q = 1/n * A * S1/2 * R2/3
Q- volumetric flowrate
A- cross sectional area of drain
R - Hydraulic Radius
S- Slope
n - coefficient of friction
Trapezoidal Grass Swale
Used for channels because of side slope
stability
Easy to maintain
Large surface area for infiltration
Q = 0.225 m3/s
S = 0.06
0.225 = 1/0.033 * (b*0.1 + 0.25*0.12) *
((b*0.1 + 0.25*0.12)/(b + 2*0.1*0.25))⅔ *
0.061/2
b = 1.405 [m]
Source: www.bae.ncsu.edu
Solved Geometries
Hydraulic
Radius (R )
[m]
Crossectional
Area (m^2)
Slope
Volumetric Flowrate (Q)
[m^3/s]
Coefficient of
Friction (n)
0.098 0.143 0.06 0.225 0.033
Base
Length (b)
[m]
Peak Capacity
Depth (y) [m]
Side Slope Swale Height (H) [m]
Top Width (wt)
[m]
1.405 0.100 0.250 1 1.91
(4.6 ft) (3.94 in) (3.28 ft) (6.25 ft)
Enhanced Grass Swale
V=Q/A
V - velocity (m/s)
Q - Peak Flow rate (m3/s)
A - Cross-sectional area (m2)
V = 0.225/.143 = 1.57m/s [5.2 fps]
Factors affecting velocity include:
- Manning’s coefficient n
- Cross-sectional area
- Slope
- designed hydraulic radius
Source: www.scdot.org
Enhanced Rock Swale
Rip-rap lined swales have varying n values
Source: www.bae.ncsu.edu
0.1m flow depth = 0.32ft = 3.8in
n = 0.0395*(D50)⅙
(D50) = 3in
n = 0.047
V = 1.09 m/s
(3.2 ft/s)
Source: www.bae.ncsu.edu
Check Dam Design
Primary Design Benefits:
Soil Erosion
Sediment Control
Total Suspended Solids (TSS)
Flow Attenuation
Source: www.riverlink.org
Flow Through a dam
Q = h1.5/(L/D + 2.5 + L2)0.5
L = (ss)*(2d - h)
Q- flow rate exiting check dam
h - flow depth
L - length of flow
D - average stone diameter in feet
ss - check dam side slope (maximum 2:1)
d = height of dam
Secondary Benefits:
Runoff Volume Reduction
Phosphorous
Nitrogen
Heavy Metals
Floatables
BOD
Check Dam Design
33 ft intervals @ 6% slope
⅓ - ⅔ of the swale depth
~66% slope on upstream side of dam
Acts as terracing to reduce sedimentation and velocity
Dam Depth ft (d) Number of Dams
2.19 15.00
Flowrate through Dam (Q) [ft^3/s] 0.83
Flow depth (h) [ft] 1.46
Length of Flow (L) [ft] 0.73
Stone Diameter (D) [ft] 0.50
Check Dam Slope (ss) 0.25
Exit Velocity (ft/s) 0.54
Check Dam Design
Max Retainage
Volume (ft^3)
3388.6
Max Volume
From 25 yr - 24
hr Storm (ft^3)
43847.4
VMAX = N*VDAM
VDAM = ½*d*L*w + 2*(½)*d*x*L
N = number of dams
d = dam height (ft)
L = distance between dams (ft)
w = bottom width
x = x distance of side slope
Source: http://chesapeakestormwater.net/wp-
content/uploads/2014/07/swale_checkdam.jpg
Construction Budget
Maintenance Budget
Total yearly cost = $375/year
McMillan Road Enhanced Swale
Design Comparison
Check Dams
Pros
- Inexpensive
- Reduces erosion and sediment transport
- Allows infiltration
- Some physical filtration
- May discourage illegal parking
Cons
- Requires periodic repair and sediment
removal
- Doesn’t treat oils
- Expensive vs Grass Swale
- Maintenance
- Chance of breach
- Temporary
Grassy / Riprap Swale (dry)
Pros
- Simple Installation
- Easy Maintenance
- Aesthetically Pleasing
Cons
- May form rills (grassy)
- Higher velocity (grassy)
- Less treatment and infiltration than other
methods
- Expensive (riprap)
End of Pipe BMPs
End of Pipe “Solutions”
Upstream reductions are not enough
Most common designs are:
Detention basin
Retention basin
Submerged gravel wetland
Goals:
Reduce peak flow
Reduce pollutant runoff http://farm5.static.flickr.com/4093/4908685081_fdcd1f7966_z.jpg
Detention Basins
Good at removing sediment, poor at
removing dissolved pollutants
Detention basin size for our area:
200’ x 100’ x 8’
Treats 100 year, 24-hour storm
Submerged Gravel Wetland
http://www.neiwpcc.org/neiwpcc_docs/GravelWetlandNutrientCyclingFinalReport3-31-10.pdf
Sedimentation Basin Sizing
Settling velocity for sizing
Stokes Law:
SCDOT Simplified Stokes:
Vs = 2.81·d2
Vs = 2.81·(0.01mm)2 ≈ 2.81∙10-4
ft/s
≈ 8.565∙10-5 m/s
Qout= c∙i∙A = (0.8)(0.15916̅ in/hr)(4.15 acres
= 0.528433ft3s-1
From SWRCB at 90% effectiveness,
Gravel Wetland Sizing
“First flush” = 0.2 in · 4.15 ac ≅3000 ft3
Water Quality Volume (WQV) = 4.15 acre-inch ≅ 15,000 ft3
Hydraulic Retention Time ( ) = V / Q
= 4∙V / 4∙Q = 1~2 days
Reduces peak flow of a ten year design storm (3.7” in 6
hours) by ~90%
Wetland dimensions (each cell): L = 110 ft, W = 55 ft
Submerged Gravel Wetland
Basemap: Google Maps; Subsurface drains: Clemson University; Basin and Service Road Drawing: J. Davis
Gravel Wetland Hydraulic Performance
http://www.neiwpcc.org/neiwpcc_docs/GravelWetlandNutrientCyclingFinalReport3-31-10.pdf
Rational Method for peak
discharge
Q = ciA, where
Q = peak discharge volume [cfs]
c = runoff coefficient
i = rainfall intensity [in/hour]
A = area [acres]
Five year design storm
Q = 0.654cfs = 295 GPM
Gravel Wetland Biological Performance
http://www.neiwpcc.org/neiwpcc_docs/GravelWetlandNutrientCyclingFinalReport3-31-10.pdf
Wetland Maintenance
Every six months:
Check for complete plant coverage and revegetate as
necessary
Ensure cells drain within 24-48 hours
Remove decaying vegetation, litter and debris
Sedimentation forebay - Remove sediment after 12” of
accumulation
Gravel treatment cells - Remove sediment after 4” of
Gravel Wetland vs Detention Costs
Item Cost Coverage Total
Grading $ 50,000.00 per acre 0.301 acres $ 15,050.00
Piping $ 23.00 per L-ft 36 L-ft $ 828.00
Pipe Labor $ 25.00 per hour 22 hours $ 550.00
Pumped concrete $ 100.00 per cu. yd. 18 cu. yds. $ 1,800.00
Pump Truck Rental $ 130.00 per hour 8 hours $ 1,040.00
Wetland Materials
& Installation
$ 22,300.00 per acre 0.301 acres $ 6,712.30
Total $ 25,980.30
Adjusting for 15% contingency $ ~ 30,000.00
Detention Pond cost $ 40,000.00 per acre 0.5 acres $ ~20,000.00
Basins
Design Comparison
Detention Pond
Pros
- Reduces peak flows
- Slows down velocity of stormwater
- Removes some sediments
- Lower installation cost
Cons
- Doesn’t remove pollutants
- Expensive dredge maintenance
Submerged Gravel Wetland
Pros
- Reduces peak flows
- Slows down the velocity of stormwater
- Significantly removes pollutants
- Removes sediments
Cons
- Higher installation cost
- Expensive dredge maintenance
Project Wrap Up
Sustainability Measures
● Economical
○ Installation
○ Maintenance
● Ecological
○ Improving Stream Health
● Social
○ Preserve natural resources
for future generations
○ Educational
● Ethical Considerations
○ Solving the problem without
damage to downstream
http://cantov.deviantart.com/art/Clemson-University-Still-Water-145243984
Kite Hill Erosion Control
- Terraced Hillside
- Cost: $25,000
- Vegetative Covered Hillside
- Cost: $27,000
Parking Lot Medians
- Vegetative Filter Strip w/ Rain Garden
- $350,000
- Coconut Mat
- $30,000
Project Cost Summary
McMillan Road Swale
- Grassy Swale
- Cost: $6,100
- Riprap Swale
- Cost: $11,000
- Check Dams
- Cost: $15,000
End of Pipe
- Detention Pond
- $20,000
- Submerged Gravel Wetland
- $30,000
Total Cost of All Designs = $92,000 ~ $415,000
3 Questions Answered
User - Clemson University
1. Is this going to limit where people can park on campus?
2. How much maintenance is required? What does this entail?
3. Will the design be aesthetically pleasing?
Client - Clemson University Facilities, Subcontractor/Developer
1. Can the design system elements be implemented at different times?
2. What is the approximate cost of the design and installation of the project?
3. What is the expected lifetime of the structures and systems being proposed?
Designer - Stormwater Project Team
1. What regulations must we work within?
2. Is the design system resilient?
3. What funding is available for this project?
Time Line
References
Jurries, Dennis, P.E. “Biofilters For Storm Water Discharge Pollution Removal”. Department of Environmental Quality.
State of Oregon. 2003. PDF. <.http://www.deq.state.or.us/wq/stormwater/docs/nwr/biofilters.pdf> Accessed 7 August
2015.
Mey, Gerald Vander. et. al. “Riparian Corridor Master Plan”. Campus Planning Services. Clemson University. December
2006. PDF. <http://www.clemson.edu/public/hunnicutt/documents/riparian_corridor_master_plan.pdf>
Google Maps. Accessed 13 August 2015.
Ruhlman, Melanie. President, Save Our Saluda. Personal communication. 12 August 2015.
Murphree, Brian Frank, P.E. et. al. MS 4 Outfall Inspections and Evaluation, Clemson University. Project No. 1505.
Design South Professionals, Inc. July 2015.
Dorren, Luuk, and Freddy Rey. "A Review of the Effect of Terracing on Erosion." SCAPE: Soil Conseveration and
Protection for Europe (n.d.): 97-108. Web. 15 Oct. 2015.
Watershed Hydrology and Small Catchments, BE3220. Owino, T, PhD. Clemson University. Spring 2015.
http://www.erosionpollution.com/support-files/coir_geotextiles_specification.pdf
References
http://water.epa.gov/scitech/wastetech/upload/2002_06_28_mtb_wetdtnpn.pdf
http://www.unh.edu/unhsc/sites/unh.edu.unhsc/files/pubs_specs_info/unhsc_gravel_wetland_specs_6_09.pdf
http://www.unh.edu/unhsc/sites/unh.edu.unhsc/files/presentations/NJASLA%20subsurface%20gravel%20wetland.pdf
http://sfrc.ifas.ufl.edu/urbanforestry/Resources/PDF%20downloads/Rushton_2001.pdf
State Water Resources Control Board: EPA, California. Attachment D: Sediment Basin Sizing. Draft, 18 March 2008.
Online. PDF. Accessed 11 November 2015.
<http://www.swrcb.ca.gov/water_issues/programs/stormwater/docs/constpermits/draft/draftconst_att_d_sed_basin.pdf
>
Jones. Tom. Personal Interview. Fall 2015.
Widomski, Marcin K. "Terracing as a Measure of Soil Erosion Control and Its Effect on Improvement of Infiltration in
Eroded Environment." Ed. Danilo Godone. Soil Erosion Issues in Agriculture (2011): 315-34. InTech. Web. 15 Oct.
2015. <http://www.intechopen.com/books/soil-erosion-issues-inagriculture/ terracing-as-a-measure-of-soil-erosion-
control-and-its-effect-on-improvement-of-infiltration-in-erod>.
References
Pitt, R. Detention Pond Design and Analysis. CE 378 Water Resources Engineering. University of Alabama. April
2004.
<http://rpitt.eng.ua.edu/Class/Water%20Resources%20Engineering/M9c2%20WinTR55%20ponds%20docs.pdf>
Northern Concrete Pipe, Inc. Price List: Reinforced Concrete Pipe. Online. Accessed 18 November 2015.
<http://www.ncp-inc.com/price1.html>
TigerDroppings. Thread: “Price per cubic yard for concrete?”. Louisiana State University-community discussion forum.
Online. Accessed 18 November 2015. <http://www.tigerdroppings.com/rant/outdoor/price-per-cubic-yard-for-
concrete/40127861/>
http://www.energy.ca.gov/sitingcases/sangabriel/documents/applicant/afc-cd/AFC_Volume-2/G%20-
%20Preliminary%20Detention%20Basin%20Calculations.pdf
Jarrett, A.R. Water Management. Kendall/Hunt Publishing. 1995.
http://nurcar.com/wholesale_catalog.pdf
http://www.homewyse.com/services/cost_to_install_sod.html
Sheng, T. Bench Terrace Design Made SImple. Department of Earth Resources. Colorado State University. 2002.
Acknowledgements
We would like to thank the following for all their help, guidance, patience, and
contribution to literature:
● Dr. Caye Drapcho
● Dr. Tom Owino
● Barrett Anderson
● Tom Jones
● Tony Putnam
● John Gambrel
● Dr. Cal Sawyer
● Dr. Ellen Vincent
● Dr. Paul Russell
● Melanie Rhulman
● Dr. Abdul Khan
● University of New Hampshire Stormwater Center

More Related Content

What's hot

Af sis midterm_review_consortium_presentation_v3
Af sis midterm_review_consortium_presentation_v3Af sis midterm_review_consortium_presentation_v3
Af sis midterm_review_consortium_presentation_v3Bob MacMillan
 
SA_SciTech_2014_Weiyang
SA_SciTech_2014_WeiyangSA_SciTech_2014_Weiyang
SA_SciTech_2014_WeiyangMDO_Lab
 
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 2: h...
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 2: h...Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 2: h...
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 2: h...Alireza Babaee
 
4 modellers guide – vejledning fra dhi
4 modellers guide – vejledning fra dhi4 modellers guide – vejledning fra dhi
4 modellers guide – vejledning fra dhiEVAnetDenmark
 
GeoTool_2015_Coastal_Data_Application_BWang_Final
GeoTool_2015_Coastal_Data_Application_BWang_FinalGeoTool_2015_Coastal_Data_Application_BWang_Final
GeoTool_2015_Coastal_Data_Application_BWang_FinalBin Wang
 
On the channel head location using DEM
On the channel head location using DEMOn the channel head location using DEM
On the channel head location using DEMLia Romano
 
Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINALBenjamin Kramka
 
Martin Seaton - DMUG 2014
Martin Seaton - DMUG 2014Martin Seaton - DMUG 2014
Martin Seaton - DMUG 2014IES / IAQM
 
Monitoring measuring and verification, Gonzalo Zambrano, University of Alberta
Monitoring measuring and verification, Gonzalo Zambrano, University of AlbertaMonitoring measuring and verification, Gonzalo Zambrano, University of Alberta
Monitoring measuring and verification, Gonzalo Zambrano, University of AlbertaGlobal CCS Institute
 
Analysis of Stormwater System for Urban Development Project in North Louisiana
Analysis of Stormwater System for Urban Development Project in North LouisianaAnalysis of Stormwater System for Urban Development Project in North Louisiana
Analysis of Stormwater System for Urban Development Project in North LouisianaBrian Elkins
 
Contaminated Soil Volume calculation
Contaminated Soil Volume calculationContaminated Soil Volume calculation
Contaminated Soil Volume calculationSalah Bakry
 
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 1: g...
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 1: g...Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 1: g...
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 1: g...Alireza Babaee
 
Seismic attributes and acoustic impedance,3D reservoir modelling ras fanar
Seismic attributes and acoustic impedance,3D reservoir modelling ras fanarSeismic attributes and acoustic impedance,3D reservoir modelling ras fanar
Seismic attributes and acoustic impedance,3D reservoir modelling ras fanarRichard Vaughan
 
Presentation of GIS Works by Adil Latif
Presentation of GIS Works by Adil LatifPresentation of GIS Works by Adil Latif
Presentation of GIS Works by Adil LatifAdil Latif
 
Truckee Tahoe Airport Master Plan Public Meeting Nov 13
Truckee Tahoe Airport Master Plan Public Meeting Nov 13Truckee Tahoe Airport Master Plan Public Meeting Nov 13
Truckee Tahoe Airport Master Plan Public Meeting Nov 13freshtrackscommunications
 
Sachpazis: Geomorphological investigation of the drainage networks and calcul...
Sachpazis: Geomorphological investigation of the drainage networks and calcul...Sachpazis: Geomorphological investigation of the drainage networks and calcul...
Sachpazis: Geomorphological investigation of the drainage networks and calcul...Dr.Costas Sachpazis
 

What's hot (20)

Af sis midterm_review_consortium_presentation_v3
Af sis midterm_review_consortium_presentation_v3Af sis midterm_review_consortium_presentation_v3
Af sis midterm_review_consortium_presentation_v3
 
SA_SciTech_2014_Weiyang
SA_SciTech_2014_WeiyangSA_SciTech_2014_Weiyang
SA_SciTech_2014_Weiyang
 
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 2: h...
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 2: h...Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 2: h...
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 2: h...
 
SOTC_2016_RMJ_SurveyingChallenges
SOTC_2016_RMJ_SurveyingChallengesSOTC_2016_RMJ_SurveyingChallenges
SOTC_2016_RMJ_SurveyingChallenges
 
4 modellers guide – vejledning fra dhi
4 modellers guide – vejledning fra dhi4 modellers guide – vejledning fra dhi
4 modellers guide – vejledning fra dhi
 
GeoTool_2015_Coastal_Data_Application_BWang_Final
GeoTool_2015_Coastal_Data_Application_BWang_FinalGeoTool_2015_Coastal_Data_Application_BWang_Final
GeoTool_2015_Coastal_Data_Application_BWang_Final
 
On the channel head location using DEM
On the channel head location using DEMOn the channel head location using DEM
On the channel head location using DEM
 
Prasari
PrasariPrasari
Prasari
 
Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINAL
 
Martin Seaton - DMUG 2014
Martin Seaton - DMUG 2014Martin Seaton - DMUG 2014
Martin Seaton - DMUG 2014
 
Monitoring measuring and verification, Gonzalo Zambrano, University of Alberta
Monitoring measuring and verification, Gonzalo Zambrano, University of AlbertaMonitoring measuring and verification, Gonzalo Zambrano, University of Alberta
Monitoring measuring and verification, Gonzalo Zambrano, University of Alberta
 
Analysis of Stormwater System for Urban Development Project in North Louisiana
Analysis of Stormwater System for Urban Development Project in North LouisianaAnalysis of Stormwater System for Urban Development Project in North Louisiana
Analysis of Stormwater System for Urban Development Project in North Louisiana
 
Gomez tagle chavez et al 2002 patzcuaro
Gomez tagle chavez et al 2002 patzcuaroGomez tagle chavez et al 2002 patzcuaro
Gomez tagle chavez et al 2002 patzcuaro
 
Contaminated Soil Volume calculation
Contaminated Soil Volume calculationContaminated Soil Volume calculation
Contaminated Soil Volume calculation
 
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 1: g...
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 1: g...Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 1: g...
Integrated hydro-geological risk for Mallero basin (Alpine Italy) – part 1: g...
 
Seismic attributes and acoustic impedance,3D reservoir modelling ras fanar
Seismic attributes and acoustic impedance,3D reservoir modelling ras fanarSeismic attributes and acoustic impedance,3D reservoir modelling ras fanar
Seismic attributes and acoustic impedance,3D reservoir modelling ras fanar
 
Presentation of GIS Works by Adil Latif
Presentation of GIS Works by Adil LatifPresentation of GIS Works by Adil Latif
Presentation of GIS Works by Adil Latif
 
Truckee Tahoe Airport Master Plan Public Meeting Nov 13
Truckee Tahoe Airport Master Plan Public Meeting Nov 13Truckee Tahoe Airport Master Plan Public Meeting Nov 13
Truckee Tahoe Airport Master Plan Public Meeting Nov 13
 
RAB NASA Update
RAB NASA UpdateRAB NASA Update
RAB NASA Update
 
Sachpazis: Geomorphological investigation of the drainage networks and calcul...
Sachpazis: Geomorphological investigation of the drainage networks and calcul...Sachpazis: Geomorphological investigation of the drainage networks and calcul...
Sachpazis: Geomorphological investigation of the drainage networks and calcul...
 

Similar to Kite Hill Senior Design Final Presentation Fall 2015

Charleston presentation final
Charleston presentation finalCharleston presentation final
Charleston presentation finalkcreswell
 
Stormwater Asset Management Using Gis V5
Stormwater Asset Management Using Gis V5Stormwater Asset Management Using Gis V5
Stormwater Asset Management Using Gis V5Vithal Deshpande
 
2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design Introduction2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design IntroductionTheodore Scott
 
Final poster final
Final poster finalFinal poster final
Final poster finalRachelCron1
 
Hydrology Final Poster
Hydrology Final PosterHydrology Final Poster
Hydrology Final PosterPatrick Cusack
 
Capstone Midterm
Capstone MidtermCapstone Midterm
Capstone Midtermdchewni
 
Cold In-Place Recycling (Foamed Asphalt) PowerPoint
Cold In-Place Recycling (Foamed Asphalt) PowerPointCold In-Place Recycling (Foamed Asphalt) PowerPoint
Cold In-Place Recycling (Foamed Asphalt) PowerPointDennis McElroy
 
Permitting potable water from rainwater- AIA Houston- September 2014
Permitting potable water from rainwater- AIA Houston- September 2014Permitting potable water from rainwater- AIA Houston- September 2014
Permitting potable water from rainwater- AIA Houston- September 2014GreeNexus Consulting, LLC
 
Green infrastructure policy for stormwater infiltration
Green infrastructure policy for stormwater infiltrationGreen infrastructure policy for stormwater infiltration
Green infrastructure policy for stormwater infiltrationEvan Pratt
 
GIS Presentation_BDH
GIS Presentation_BDHGIS Presentation_BDH
GIS Presentation_BDHBenjamin Hamm
 
Modelling the effect of Conservation Agriculture on soil loss in Madagascar, ...
Modelling the effect of Conservation Agriculture on soil loss in Madagascar, ...Modelling the effect of Conservation Agriculture on soil loss in Madagascar, ...
Modelling the effect of Conservation Agriculture on soil loss in Madagascar, ...FreddyVHulst
 
Hunnicutt Creak Stream Restoration Design
Hunnicutt Creak Stream Restoration Design Hunnicutt Creak Stream Restoration Design
Hunnicutt Creak Stream Restoration Design Grace Wachowski
 
Storm drainage design
Storm drainage designStorm drainage design
Storm drainage designdobariya axit
 
NJ Future Redevelopment Forum 2017 Cammarata
NJ Future Redevelopment Forum 2017 CammarataNJ Future Redevelopment Forum 2017 Cammarata
NJ Future Redevelopment Forum 2017 CammarataNew Jersey Future
 
Retrofitting of road gutters with an infiltration-exfiltration system for sto...
Retrofitting of road gutters with an infiltration-exfiltration system for sto...Retrofitting of road gutters with an infiltration-exfiltration system for sto...
Retrofitting of road gutters with an infiltration-exfiltration system for sto...Mariana Marchioni
 
Terrace effects on soil erosion processes
Terrace effects on soil erosion processesTerrace effects on soil erosion processes
Terrace effects on soil erosion processesHui Shao
 
Charleston midterm
Charleston midtermCharleston midterm
Charleston midtermbtdubos
 
Maryland Environmental Site Design Presentation
Maryland Environmental Site Design PresentationMaryland Environmental Site Design Presentation
Maryland Environmental Site Design PresentationTheodore Scott
 

Similar to Kite Hill Senior Design Final Presentation Fall 2015 (20)

Charleston presentation final
Charleston presentation finalCharleston presentation final
Charleston presentation final
 
Stormwater Asset Management Using Gis V5
Stormwater Asset Management Using Gis V5Stormwater Asset Management Using Gis V5
Stormwater Asset Management Using Gis V5
 
2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design Introduction2011 6 14 Home Builders of MD Environmental Site Design Introduction
2011 6 14 Home Builders of MD Environmental Site Design Introduction
 
Los Angeles County's Sustainable Roadway Improvement Program
Los Angeles County's Sustainable Roadway Improvement ProgramLos Angeles County's Sustainable Roadway Improvement Program
Los Angeles County's Sustainable Roadway Improvement Program
 
Final poster final
Final poster finalFinal poster final
Final poster final
 
Hydrology Final Poster
Hydrology Final PosterHydrology Final Poster
Hydrology Final Poster
 
Capstone Midterm
Capstone MidtermCapstone Midterm
Capstone Midterm
 
Cold In-Place Recycling (Foamed Asphalt) PowerPoint
Cold In-Place Recycling (Foamed Asphalt) PowerPointCold In-Place Recycling (Foamed Asphalt) PowerPoint
Cold In-Place Recycling (Foamed Asphalt) PowerPoint
 
Permitting potable water from rainwater- AIA Houston- September 2014
Permitting potable water from rainwater- AIA Houston- September 2014Permitting potable water from rainwater- AIA Houston- September 2014
Permitting potable water from rainwater- AIA Houston- September 2014
 
Green infrastructure policy for stormwater infiltration
Green infrastructure policy for stormwater infiltrationGreen infrastructure policy for stormwater infiltration
Green infrastructure policy for stormwater infiltration
 
GIS Presentation_BDH
GIS Presentation_BDHGIS Presentation_BDH
GIS Presentation_BDH
 
Modelling the effect of Conservation Agriculture on soil loss in Madagascar, ...
Modelling the effect of Conservation Agriculture on soil loss in Madagascar, ...Modelling the effect of Conservation Agriculture on soil loss in Madagascar, ...
Modelling the effect of Conservation Agriculture on soil loss in Madagascar, ...
 
Hunnicutt Creak Stream Restoration Design
Hunnicutt Creak Stream Restoration Design Hunnicutt Creak Stream Restoration Design
Hunnicutt Creak Stream Restoration Design
 
Storm drainage design
Storm drainage designStorm drainage design
Storm drainage design
 
NJ Future Redevelopment Forum 2017 Cammarata
NJ Future Redevelopment Forum 2017 CammarataNJ Future Redevelopment Forum 2017 Cammarata
NJ Future Redevelopment Forum 2017 Cammarata
 
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
Using Weep Berms to Control Water Quality by Richard Warner and Greg Higgins
 
Retrofitting of road gutters with an infiltration-exfiltration system for sto...
Retrofitting of road gutters with an infiltration-exfiltration system for sto...Retrofitting of road gutters with an infiltration-exfiltration system for sto...
Retrofitting of road gutters with an infiltration-exfiltration system for sto...
 
Terrace effects on soil erosion processes
Terrace effects on soil erosion processesTerrace effects on soil erosion processes
Terrace effects on soil erosion processes
 
Charleston midterm
Charleston midtermCharleston midterm
Charleston midterm
 
Maryland Environmental Site Design Presentation
Maryland Environmental Site Design PresentationMaryland Environmental Site Design Presentation
Maryland Environmental Site Design Presentation
 

More from Ashleigh Hough

Brewery Process Design
Brewery Process DesignBrewery Process Design
Brewery Process DesignAshleigh Hough
 
Roof Radiation PowerPoint
Roof Radiation PowerPointRoof Radiation PowerPoint
Roof Radiation PowerPointAshleigh Hough
 
MIcrobial Fuel Cell Presentation
MIcrobial Fuel Cell PresentationMIcrobial Fuel Cell Presentation
MIcrobial Fuel Cell PresentationAshleigh Hough
 
Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015Ashleigh Hough
 
Hough - SNA Powerpoint
Hough - SNA PowerpointHough - SNA Powerpoint
Hough - SNA PowerpointAshleigh Hough
 
End of Summer UPIC Powerpoint 2014
End of Summer UPIC Powerpoint 2014End of Summer UPIC Powerpoint 2014
End of Summer UPIC Powerpoint 2014Ashleigh Hough
 

More from Ashleigh Hough (9)

Brewery Process Design
Brewery Process DesignBrewery Process Design
Brewery Process Design
 
Roof Radiation PowerPoint
Roof Radiation PowerPointRoof Radiation PowerPoint
Roof Radiation PowerPoint
 
Hydrology Design
Hydrology Design Hydrology Design
Hydrology Design
 
MIcrobial Fuel Cell Presentation
MIcrobial Fuel Cell PresentationMIcrobial Fuel Cell Presentation
MIcrobial Fuel Cell Presentation
 
Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015Kite Hill Senior Design Final Presentation Fall 2015
Kite Hill Senior Design Final Presentation Fall 2015
 
AEES - ELC Poster
AEES - ELC PosterAEES - ELC Poster
AEES - ELC Poster
 
Hough - SNA Powerpoint
Hough - SNA PowerpointHough - SNA Powerpoint
Hough - SNA Powerpoint
 
End of Summer UPIC Powerpoint 2014
End of Summer UPIC Powerpoint 2014End of Summer UPIC Powerpoint 2014
End of Summer UPIC Powerpoint 2014
 
UPIC Internship 2015
UPIC Internship 2015UPIC Internship 2015
UPIC Internship 2015
 

Recently uploaded

Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
Measures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped dataMeasures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped dataBabyAnnMotar
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
EmpTech Lesson 18 - ICT Project for Website Traffic Statistics and Performanc...
EmpTech Lesson 18 - ICT Project for Website Traffic Statistics and Performanc...EmpTech Lesson 18 - ICT Project for Website Traffic Statistics and Performanc...
EmpTech Lesson 18 - ICT Project for Website Traffic Statistics and Performanc...liera silvan
 
Presentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxPresentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxRosabel UA
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSMae Pangan
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationdeepaannamalai16
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...JojoEDelaCruz
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Dust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSEDust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSEaurabinda banchhor
 

Recently uploaded (20)

Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
Measures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped dataMeasures of Position DECILES for ungrouped data
Measures of Position DECILES for ungrouped data
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
EmpTech Lesson 18 - ICT Project for Website Traffic Statistics and Performanc...
EmpTech Lesson 18 - ICT Project for Website Traffic Statistics and Performanc...EmpTech Lesson 18 - ICT Project for Website Traffic Statistics and Performanc...
EmpTech Lesson 18 - ICT Project for Website Traffic Statistics and Performanc...
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
Presentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxPresentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptx
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHS
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentation
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Dust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSEDust Of Snow By Robert Frost Class-X English CBSE
Dust Of Snow By Robert Frost Class-X English CBSE
 

Kite Hill Senior Design Final Presentation Fall 2015

  • 1. Kite Hill Stormwater Management C. Bury, J. Davis, A. Hough, R. Middlewarth, J. Ossorio Clemson University - Biosystems Engineering BE 4750 Fall 2015 Senior Design Presentation November 23, 2015
  • 2. Table of Contents 1. Introducing the Problem a. Kite Hill Impact on Hunnicutt Creek 2. Project Assessment a. Defining problem, goals, constraints, considerations, and design elements 3. Design Elements a. Area of Interest b. Existing Conditions c. Design and Methodology d. Cost Estimation e. Design Comparisons 4. Sustainability Measures 5. Conclusion
  • 6. Recognition of Problem Stormwater runoff results in ● Heavy peak flows Sediment transport / erosion ● Pollution transportation ● Destruction of downstream ecology of Hunnicutt Creek watershed
  • 9. C. Bury C. Bury
  • 12. Define Problem Lack of infiltration Pollution runoff Damage to Hunnicutt Creek Goals of the Project Biological: Treat stormwater pollutants before entering Hunnicutt Creek Structural: Reduce peak flows and runoff velocity of stormwater for a 10 yr - 24 hr storm event http://www.cnyhiking.com/NCTinPA-MinisterCreekTrail892.jpg
  • 13. Constraints and Considerations Constraints Existing Infrastructure Future Construction http://fisheyestudios.com/gallery-categories/aerial/ Considerations Safety Entering for maintenance Safety around the area Sustainability Minimal maintenance Durable design options Aesthetics Budget
  • 14. 3 Questions User - Clemson University 1. Is this going to limit where people can park on campus? 2. How much maintenance is required? What does this entail? 3. Will the design be aesthetically pleasing? Client - Clemson University Facilities, Subcontractor/Developer 1. Can the design system elements be implemented at different times? 2. What is the approximate cost of the design and installation of the project? 3. What is the expected lifetime of the structures and systems being proposed? Designer - Stormwater Project Team 1. What regulations must we work within? 2. Is the design system resilient? 3. What funding is available for this project? What requirements would need to be met for this design to be implemented? http://www.sciway.net/sc-photos/wp-content/uploads/tillman-hall-clemson1.jpg
  • 15. Elements of Design ● Kite Hill Erosion Control ● Parking Lot Median BMPs ● Enhanced Swale ● End of Pipe BMPs Basemap: Google Maps; Highlighted Areas: J. Davis
  • 16. Kite Hill Erosion Control
  • 17. Area Section Area of Section (ft2) Slope Percent 1 4239 12.9 % 2 2922 22.4 % 3 6033 10.6 % 4 8908 10.5 % 5 11325 3 % 6 5097 19 % 7 11848 5.6 % 8 6938 17 % Source: Basemap: Google Maps; Area Analysis: J. Ossorio Hill Redesign:Sub-Goals and Area of Interest Area Section Area of Section (ft2) Slope Percent 9 4557 8.9 % 10 3236 18 % 11 3589 8 % 12 4642 15.1 % 13 3819 26.8 % 14 4729 9.6 % 15 5309 20.4% 16 4722 18.22 % Goals: 1. Reduce Erosion from Kite Hill by 75% per yr 2. Safe Driving Option: Gameday parking 3. Reduce Runoff Rate by 25 % for a 25 yr- 24 hr storm
  • 18. Existing Conditions Universal Soil Loss Equation (RUSLE): T= R*K*LS*VM R- Rain factor = 250 (Pickens, SC) K- Soil Erodibility Factor = 0.17 (Web Soil Survey) VM- Vegetative Mulch LS- Length Slope Factor = (Calculated separately for each area) Estimated Soil Loss T=(250)*(.17)*(.34)*(2.12) = 9.37 tons/ acre/ year 9.37 tons/ acre/ yr *2.601 acres = 24.39 tons = 22.13 tonnes of SOIL LOSS per year Erosion Estimation Runoff Volume Estimates Soil-Cover Complex Method CN- Weighted Curve Number = 62.8 for Sod and Mulch P- Rainfall for 25 yr -24 hr storm = 6.77 in (Rain Data obtained from Tony Putnam) S- Surface Storage Q- Runoff Vr- Volume of Runoff S = (1000/CN)-10 = 5.92 in Q= (P - 0.2S)2/(P + 0.8S) = 2.95 in of runoff Vr = 2.95 in * (2.60 acres) = 27335 ft3 = 774 m3 of Runoff during a 25 yr - 24 hr storm
  • 19. Existing Conditions Photo Credit: Conor Bury, 2015 Runoff Flow Rate Estimates Peak Runoff Rate Qp = qp*A*Q Q = 2.95 in S = 5.92 in tL= L0.8(S +1) 0.7/(1900γ0.5) tc = tL/0.6 Weighted qp = 1.543 (cfs/ac-in) Qp= (1.543 cfs/ac-in *2.95 in *2.60 ac = 11.6cfs = 0.329 m3/s is the FLOW RATE of Runoff during a 25 yr -24 hr Storm
  • 20. Design 1 - Hillside Terrace Benches are covered with grass (9600 ft2) and the Risers are covered with liriope and straw mulch (1790 ft2 = 1020 plants). The Cut and Fill Volume is 385 cu. yd Erosion Reduction: Soil Delivery Ratio Method for Slope 14-16% Reduce Soil Loss per year from 24.39 tons to 1.95 tons 92 % reduction in erosion for overall AOI. Runoff Volume: Soil Cover Complex Method Weighted CN 65.2 to 61 Reduce Runoff Volume for a 25 yr- 24 yr storm from 7173 ft3 to 6171 ft3, 13.96 % reduce volume for the hillside area and 3.4 % for total AOI. Runoff Peak Flow Rate: Peak Runoff Rate Reduce Flow Rate from 3.48 cfs to 2.61 cfs for the hillside area 25.18 % reduction in Peak Flow Rate. Design Specs (Determined using Agricultural Terrace Design) Direction 1: Length 49 ft, 14 %, 0.44 ac Direction 2: Length 60 ft, 16.5 %, 0.2 ac Terraces include: 2 benches (14.76 ft), 3 risers (1:1) 2.83 ft depth Source: Basemap: Google Maps; Area Analysis: J. Ossorio Source: Chap. 5 Physical Methods for Erosion Control
  • 21. Design 2 - Hillside Vegetative Cover Hillside is covered with juniper plants and straw mulch, but any shrub-like plants can be used for hillside cover. Erosion Reduction: Revised Universal Soil Loss Equation Weighted VM from 0.12 to 0.012 (Canopy of Bushes 25% and 80% grass cover) Reduce Soil Loss per year from 7.5 tons to 1.27 tons 88.6 % reduction in erosion for the hillside area and 27% reduction for ENTIRE AOI. Runoff Volume: Soil Cover Complex Method for Weighted CN from 65.2 to 48 Reduce Runoff Volume for a 25 yr- 24 yr storm from 7173 ft3 to 3339 ft3 53.4% reduce volume for the hillside area and 12.9 % for total AOI. Runoff Peak Flow Rate: Peak Runoff Rate Reduce Flow Rate from 3.48 cfs to 1.38 cfs for the hillside area 60.44% reduction in Peak Flow Rate. Source: Basemap: Google Maps; Area Analysis: J. Ossorio Design Specs: Direction 1: Length 49 ft, 14 %, 0.44 ac Direction 2: Length 60 ft, 16.5 %, 0.2 ac Juniper Spacing: 6 ft (~1030 plants) http://2minutegardener.blogspot.com/2011/12/p hoto-creeping-myoporum-myoporum.html
  • 22. Curb and sidewalk removal to add ramp way (located 425 ft from Perimeter Road corner) Area: 1,588 ft2 Width of 60 ft by 25 ft Design Driving Options Source: Basemap: Google Maps; Area Analysis: J. Ossorio Driveway already exists, but the proposal is to allow access to this entrance after hours by changing Recycling Center enclosure New Fencing: 500 ft Gate Removal: 53 ft Existing Driveway at Recycling Center Semi-Driveway on Highway 76 Source: Basemap: Google Maps; Area Analysis: J. Ossorio
  • 23. Kite Hill Erosion Control Budget
  • 24. Kite Hill Erosion Control Budget
  • 25. Kite Hill Erosion Reduction: Design Comparison Hillside Redesign Terraced Side ($25,630.00) Pros -Reduce erosion by 92 % -Reduce Runoff Volume by 14% -Reduce Runoff Velocity by 26 % - Discourages driving on the hillside -Instant functionality Cons -Has some maintenance once established (mulch and cut grass) -Heavy Construction Driving Options Existing Drive at Recycling Center ($7,657.00) Pros - Fence is already needed for area -Already developed Drive Cons -Heavy traffic around Recycling Center Vegetative Cover ($27,542.00) Pros -Reduce erosion by 27% overall and 89% for the Area -Reduce Runoff Volume by 13 % overall and 54 % for Area -Reduce Runoff Velocity by 61% - Discourages driving on the hillside - Low maintenance after establishment Cons -3 year establishment -Cannot Handle foot or car traffic slow recovery Semi Drive on Highway 76 ($6,811.00) Pros -Allows for safer option for drivers who ride of curb on gameday -Minimal space to preserve Green Space -Two Entrances and Exits Cons -Additional Traffic on game day
  • 27. Median BMPs: Sub-Goals and Area of Interest 1. Reduce the Velocity of Runoff 2. Allow Infiltration into Medians 3. Prevent Sediment Loss 7 7 123 4 5 6 7 Source: Google Maps Area (ft2) Slope (%) H. Slope (%) V. 1 4145 10.8 1.0 2 6603 4.2 0.9 3 9944 6.7 0.8 4 10,008 6.1 1.0 5 7917 6.4 1.2 6 7491 5.9 1.4 7 6469 5.0 1.6
  • 28. Runoff Volume Parking Lot Estimates Soil-Cover Complex Method CN - Curve Number = 92 (Commercial Parking Lot, HSG B, 85% Impervious Area) P- Rainfall for 25 yr -24 hr storm = 6.77 in (Rain Data obtained from Tony Putnam) S = (1000/CN)-10 = 0.87 in Q= (P - 0.2S)2/(P + 0.8S) = 5.83 in of runoff Vr = 5.83 in * (1.21 acres) = 25,534 ft3 723 m3 of runoff during a 25 yr - 24 hr storm Peak Runoff Rate Qp = qp*A*Q Q = 5.83 in S = 0.87 in tL= L0.8(S +1) 0.7/(1900γ0.5) tc = tL/0.6 Average qp = 0.86 (cfs/ac-in) Qp= (1.2 cfs/ac-in * 5.83 in * 0.41 ac) = 2.88 cfs 0.546 m3/s flow rate of runoff during a 25 yr - 24 hr storm Photo credit: Conor Bury
  • 29. Design 1 - Vegetated Filter Strip Area (ft2) Slope (%) Q (cfs) Bottom Width (ft) Top Width (ft) y (ft) Velocity (ft/s) 1 17,966 1 2.88 1.67 2.51 0.83 1.01 2 26,107 0.9 2.96 1.72 2.59 0.86 0.98 3 34,173 0.8 3.88 1.95 2.92 0.97 1.00 4 30,072 1 2.01 1.46 2.19 0.73 0.93 5 23,298 1.2 2.80 1.60 2.40 0.80 1.08 6 20,170 1.4 2.42 1.47 2.21 0.73 1.10 7 18,212 1.6 1.94 1.32 1.98 0.66 1.09 Q = (k/n)*Rh (⅔)*A*So (½) n: Gauckler-Manning’s coefficient tall vegetation - 12 to 24 inches: 0.08 trapezoidal channel design 0.25 (H:V - 4:1) height of trapezoid is equal to bottom width tree removal curb stops retaining wall pavers fill dirt, soil and compost mixture, plant with liriope and bermuda create berm gravel, compost, soil and mulch layer with native plants Source: http://www.watershedmanagement.vt.gov/stormwater/htm/sw_gi_bmp_bioretention.htmSource: Ashleigh Hough
  • 30. Design 2 - Erosion Mat T= R*K*LS*VM R - Rain factor = 250 (Pickens, SC) K - Soil Erodibility Factor = 0.17 (Web Soil Survey) LS - Length Slope Factor VM (before) =0.9 (rough, irregular bare soil) VM (after) = 0.08 (coconut mat) Before After VM factor - 0.9 VM factor - 0.08 29.7 tonnes/year 2.6 tonnes/year ● curb stops ● seeding (bermuda grass) live stakes (Miscanthus) source: http://www.in.gov/legislative/iac/20120404-IR-312120154NRA.xml.html source: http://www.hgtvgardens.com/flowers-and- plants/maiden-grass-miscanthus-sinensis-morning- light
  • 32. Medians Design Comparison Vegetative Strip with Rain Garden Pros - Nearly all runoff that enters swale infiltrates back into the ground - Greatly reduces erosion - Slows down velocity of stormwater - Removes pollutants - More permanent solution Cons - Eliminates most trees - Failure issues of pavers - Maintenance - Expensive Coconut Mat Pros - Slows down the velocity of stormwater - Reduces erosion by 91% - Allows for trees to stay - Biodegradable mats - Less expensive Cons - Temporary solution (possibly) - Maintenance - Less pollutant removal
  • 34. Flow Diversion Techniques Flow Diversion Options: Concrete cut with apron & stabilization Grated Trench Drain Photo Credit: Conor Bury, 2015 Source: Basemap: Google Maps; Area Analysis: R. Middleswarth
  • 35. Curb Cut with Apron Divert flow into swale Must set stabilizers and apron Concrete GCL Erosion Mat Source: www.lastreetblog.org source: http://www.beinginplace.org
  • 36. Grated Trench Drain Source: www.trenchdrainsupply.com Hill Area Section Area of Section (A) [m2] Coefficient of runoff (C ) Rainfall Intensity (I) [m/s] Volumetric Flowrate (Qreq) [m3/s] 1 393.8 ..35 5.6E-05 0.1332 2 271.5 3 560.5 4 827.6 Driveway 432.0 .95 Total 2485.3
  • 37. Grated Trench Drain Qreq=(k*A*R2/3*S1/2)/n Qreq - volumetric flowrate k - conversion from Eng to SI A - cross sectional area of drain R - Hydraulic Radius S- Slope n - coefficient of friction Solve for WIDTH Cross Sectional Area (m2) Hydraulic Radius (R ) [m] Slope Volumetric Flowrate (Q) [m3/s] Coefficient of Friction (n) Base Width (b) [m] Peak Capacity Depth (h) [m] 0.062 0.198 0.020 0.133 0.013 0.352 0.176
  • 38. Finding Peak Flowrate and Volume Peak Runoff Rate Qn = qp*A*Qx Qx = runoff depth qp - peak discharge coefficient S = (1000/CN)-10 tL= L0.8(S +1) 0.7/(1900γ0.5) tc = tL/0.6 L - Hydraulic Length y - slope Soil-Cover Complex Method S = (1000/CN)-10 CN - Curve Number P- Rainfall for 25 yr -24 hr storm = 6.77 in (Rain Data obtained from Tony Putnam) Qx = (P - 0.2Sn)2/(P + 0.8Sn) ∑Q*Area = total volume of runoff 43,847 ft3 of runoff during a 25 yr - 24 hr storm Peak Runoff Average Qdesign =∑(Qn*(Vn/VTOTAL)) V - Volume of basin Q - Peak Runoff Rate of Basin 7.95 cfs flow rate of runoff during a 25 yr - 24 hr storm
  • 39. Enhanced Swale Design 500ft stretch options: Grassy Swale Check Dam Swale Must Handle a Peak Storm of: 7.95 ft3/s flow rate 43,848 ft3 volume Source: Basemap: Google Maps; Area Analysis: R. Middleswarth
  • 40. Peak Runoff Rate A = b*y + z*y2 A = b*0.1 + 0.25*0.12 R = A/(b + 2*0.1*0.25) Q = 1/n * A * S1/2 * R2/3 Q- volumetric flowrate A- cross sectional area of drain R - Hydraulic Radius S- Slope n - coefficient of friction Trapezoidal Grass Swale Used for channels because of side slope stability Easy to maintain Large surface area for infiltration Q = 0.225 m3/s S = 0.06 0.225 = 1/0.033 * (b*0.1 + 0.25*0.12) * ((b*0.1 + 0.25*0.12)/(b + 2*0.1*0.25))⅔ * 0.061/2 b = 1.405 [m] Source: www.bae.ncsu.edu
  • 41. Solved Geometries Hydraulic Radius (R ) [m] Crossectional Area (m^2) Slope Volumetric Flowrate (Q) [m^3/s] Coefficient of Friction (n) 0.098 0.143 0.06 0.225 0.033 Base Length (b) [m] Peak Capacity Depth (y) [m] Side Slope Swale Height (H) [m] Top Width (wt) [m] 1.405 0.100 0.250 1 1.91 (4.6 ft) (3.94 in) (3.28 ft) (6.25 ft)
  • 42. Enhanced Grass Swale V=Q/A V - velocity (m/s) Q - Peak Flow rate (m3/s) A - Cross-sectional area (m2) V = 0.225/.143 = 1.57m/s [5.2 fps] Factors affecting velocity include: - Manning’s coefficient n - Cross-sectional area - Slope - designed hydraulic radius Source: www.scdot.org
  • 43. Enhanced Rock Swale Rip-rap lined swales have varying n values Source: www.bae.ncsu.edu 0.1m flow depth = 0.32ft = 3.8in n = 0.0395*(D50)⅙ (D50) = 3in n = 0.047 V = 1.09 m/s (3.2 ft/s) Source: www.bae.ncsu.edu
  • 44. Check Dam Design Primary Design Benefits: Soil Erosion Sediment Control Total Suspended Solids (TSS) Flow Attenuation Source: www.riverlink.org Flow Through a dam Q = h1.5/(L/D + 2.5 + L2)0.5 L = (ss)*(2d - h) Q- flow rate exiting check dam h - flow depth L - length of flow D - average stone diameter in feet ss - check dam side slope (maximum 2:1) d = height of dam Secondary Benefits: Runoff Volume Reduction Phosphorous Nitrogen Heavy Metals Floatables BOD
  • 45. Check Dam Design 33 ft intervals @ 6% slope ⅓ - ⅔ of the swale depth ~66% slope on upstream side of dam Acts as terracing to reduce sedimentation and velocity Dam Depth ft (d) Number of Dams 2.19 15.00 Flowrate through Dam (Q) [ft^3/s] 0.83 Flow depth (h) [ft] 1.46 Length of Flow (L) [ft] 0.73 Stone Diameter (D) [ft] 0.50 Check Dam Slope (ss) 0.25 Exit Velocity (ft/s) 0.54
  • 46. Check Dam Design Max Retainage Volume (ft^3) 3388.6 Max Volume From 25 yr - 24 hr Storm (ft^3) 43847.4 VMAX = N*VDAM VDAM = ½*d*L*w + 2*(½)*d*x*L N = number of dams d = dam height (ft) L = distance between dams (ft) w = bottom width x = x distance of side slope Source: http://chesapeakestormwater.net/wp- content/uploads/2014/07/swale_checkdam.jpg
  • 49. McMillan Road Enhanced Swale Design Comparison Check Dams Pros - Inexpensive - Reduces erosion and sediment transport - Allows infiltration - Some physical filtration - May discourage illegal parking Cons - Requires periodic repair and sediment removal - Doesn’t treat oils - Expensive vs Grass Swale - Maintenance - Chance of breach - Temporary Grassy / Riprap Swale (dry) Pros - Simple Installation - Easy Maintenance - Aesthetically Pleasing Cons - May form rills (grassy) - Higher velocity (grassy) - Less treatment and infiltration than other methods - Expensive (riprap)
  • 50. End of Pipe BMPs
  • 51. End of Pipe “Solutions” Upstream reductions are not enough Most common designs are: Detention basin Retention basin Submerged gravel wetland Goals: Reduce peak flow Reduce pollutant runoff http://farm5.static.flickr.com/4093/4908685081_fdcd1f7966_z.jpg
  • 52. Detention Basins Good at removing sediment, poor at removing dissolved pollutants Detention basin size for our area: 200’ x 100’ x 8’ Treats 100 year, 24-hour storm
  • 54. Sedimentation Basin Sizing Settling velocity for sizing Stokes Law: SCDOT Simplified Stokes: Vs = 2.81·d2 Vs = 2.81·(0.01mm)2 ≈ 2.81∙10-4 ft/s ≈ 8.565∙10-5 m/s Qout= c∙i∙A = (0.8)(0.15916̅ in/hr)(4.15 acres = 0.528433ft3s-1 From SWRCB at 90% effectiveness,
  • 55. Gravel Wetland Sizing “First flush” = 0.2 in · 4.15 ac ≅3000 ft3 Water Quality Volume (WQV) = 4.15 acre-inch ≅ 15,000 ft3 Hydraulic Retention Time ( ) = V / Q = 4∙V / 4∙Q = 1~2 days Reduces peak flow of a ten year design storm (3.7” in 6 hours) by ~90% Wetland dimensions (each cell): L = 110 ft, W = 55 ft
  • 56. Submerged Gravel Wetland Basemap: Google Maps; Subsurface drains: Clemson University; Basin and Service Road Drawing: J. Davis
  • 57. Gravel Wetland Hydraulic Performance http://www.neiwpcc.org/neiwpcc_docs/GravelWetlandNutrientCyclingFinalReport3-31-10.pdf Rational Method for peak discharge Q = ciA, where Q = peak discharge volume [cfs] c = runoff coefficient i = rainfall intensity [in/hour] A = area [acres] Five year design storm Q = 0.654cfs = 295 GPM
  • 58. Gravel Wetland Biological Performance http://www.neiwpcc.org/neiwpcc_docs/GravelWetlandNutrientCyclingFinalReport3-31-10.pdf
  • 59. Wetland Maintenance Every six months: Check for complete plant coverage and revegetate as necessary Ensure cells drain within 24-48 hours Remove decaying vegetation, litter and debris Sedimentation forebay - Remove sediment after 12” of accumulation Gravel treatment cells - Remove sediment after 4” of
  • 60. Gravel Wetland vs Detention Costs Item Cost Coverage Total Grading $ 50,000.00 per acre 0.301 acres $ 15,050.00 Piping $ 23.00 per L-ft 36 L-ft $ 828.00 Pipe Labor $ 25.00 per hour 22 hours $ 550.00 Pumped concrete $ 100.00 per cu. yd. 18 cu. yds. $ 1,800.00 Pump Truck Rental $ 130.00 per hour 8 hours $ 1,040.00 Wetland Materials & Installation $ 22,300.00 per acre 0.301 acres $ 6,712.30 Total $ 25,980.30 Adjusting for 15% contingency $ ~ 30,000.00 Detention Pond cost $ 40,000.00 per acre 0.5 acres $ ~20,000.00
  • 61. Basins Design Comparison Detention Pond Pros - Reduces peak flows - Slows down velocity of stormwater - Removes some sediments - Lower installation cost Cons - Doesn’t remove pollutants - Expensive dredge maintenance Submerged Gravel Wetland Pros - Reduces peak flows - Slows down the velocity of stormwater - Significantly removes pollutants - Removes sediments Cons - Higher installation cost - Expensive dredge maintenance
  • 63. Sustainability Measures ● Economical ○ Installation ○ Maintenance ● Ecological ○ Improving Stream Health ● Social ○ Preserve natural resources for future generations ○ Educational ● Ethical Considerations ○ Solving the problem without damage to downstream http://cantov.deviantart.com/art/Clemson-University-Still-Water-145243984
  • 64. Kite Hill Erosion Control - Terraced Hillside - Cost: $25,000 - Vegetative Covered Hillside - Cost: $27,000 Parking Lot Medians - Vegetative Filter Strip w/ Rain Garden - $350,000 - Coconut Mat - $30,000 Project Cost Summary McMillan Road Swale - Grassy Swale - Cost: $6,100 - Riprap Swale - Cost: $11,000 - Check Dams - Cost: $15,000 End of Pipe - Detention Pond - $20,000 - Submerged Gravel Wetland - $30,000 Total Cost of All Designs = $92,000 ~ $415,000
  • 65. 3 Questions Answered User - Clemson University 1. Is this going to limit where people can park on campus? 2. How much maintenance is required? What does this entail? 3. Will the design be aesthetically pleasing? Client - Clemson University Facilities, Subcontractor/Developer 1. Can the design system elements be implemented at different times? 2. What is the approximate cost of the design and installation of the project? 3. What is the expected lifetime of the structures and systems being proposed? Designer - Stormwater Project Team 1. What regulations must we work within? 2. Is the design system resilient? 3. What funding is available for this project?
  • 67. References Jurries, Dennis, P.E. “Biofilters For Storm Water Discharge Pollution Removal”. Department of Environmental Quality. State of Oregon. 2003. PDF. <.http://www.deq.state.or.us/wq/stormwater/docs/nwr/biofilters.pdf> Accessed 7 August 2015. Mey, Gerald Vander. et. al. “Riparian Corridor Master Plan”. Campus Planning Services. Clemson University. December 2006. PDF. <http://www.clemson.edu/public/hunnicutt/documents/riparian_corridor_master_plan.pdf> Google Maps. Accessed 13 August 2015. Ruhlman, Melanie. President, Save Our Saluda. Personal communication. 12 August 2015. Murphree, Brian Frank, P.E. et. al. MS 4 Outfall Inspections and Evaluation, Clemson University. Project No. 1505. Design South Professionals, Inc. July 2015. Dorren, Luuk, and Freddy Rey. "A Review of the Effect of Terracing on Erosion." SCAPE: Soil Conseveration and Protection for Europe (n.d.): 97-108. Web. 15 Oct. 2015. Watershed Hydrology and Small Catchments, BE3220. Owino, T, PhD. Clemson University. Spring 2015. http://www.erosionpollution.com/support-files/coir_geotextiles_specification.pdf
  • 68. References http://water.epa.gov/scitech/wastetech/upload/2002_06_28_mtb_wetdtnpn.pdf http://www.unh.edu/unhsc/sites/unh.edu.unhsc/files/pubs_specs_info/unhsc_gravel_wetland_specs_6_09.pdf http://www.unh.edu/unhsc/sites/unh.edu.unhsc/files/presentations/NJASLA%20subsurface%20gravel%20wetland.pdf http://sfrc.ifas.ufl.edu/urbanforestry/Resources/PDF%20downloads/Rushton_2001.pdf State Water Resources Control Board: EPA, California. Attachment D: Sediment Basin Sizing. Draft, 18 March 2008. Online. PDF. Accessed 11 November 2015. <http://www.swrcb.ca.gov/water_issues/programs/stormwater/docs/constpermits/draft/draftconst_att_d_sed_basin.pdf > Jones. Tom. Personal Interview. Fall 2015. Widomski, Marcin K. "Terracing as a Measure of Soil Erosion Control and Its Effect on Improvement of Infiltration in Eroded Environment." Ed. Danilo Godone. Soil Erosion Issues in Agriculture (2011): 315-34. InTech. Web. 15 Oct. 2015. <http://www.intechopen.com/books/soil-erosion-issues-inagriculture/ terracing-as-a-measure-of-soil-erosion- control-and-its-effect-on-improvement-of-infiltration-in-erod>.
  • 69. References Pitt, R. Detention Pond Design and Analysis. CE 378 Water Resources Engineering. University of Alabama. April 2004. <http://rpitt.eng.ua.edu/Class/Water%20Resources%20Engineering/M9c2%20WinTR55%20ponds%20docs.pdf> Northern Concrete Pipe, Inc. Price List: Reinforced Concrete Pipe. Online. Accessed 18 November 2015. <http://www.ncp-inc.com/price1.html> TigerDroppings. Thread: “Price per cubic yard for concrete?”. Louisiana State University-community discussion forum. Online. Accessed 18 November 2015. <http://www.tigerdroppings.com/rant/outdoor/price-per-cubic-yard-for- concrete/40127861/> http://www.energy.ca.gov/sitingcases/sangabriel/documents/applicant/afc-cd/AFC_Volume-2/G%20- %20Preliminary%20Detention%20Basin%20Calculations.pdf Jarrett, A.R. Water Management. Kendall/Hunt Publishing. 1995. http://nurcar.com/wholesale_catalog.pdf http://www.homewyse.com/services/cost_to_install_sod.html Sheng, T. Bench Terrace Design Made SImple. Department of Earth Resources. Colorado State University. 2002.
  • 70. Acknowledgements We would like to thank the following for all their help, guidance, patience, and contribution to literature: ● Dr. Caye Drapcho ● Dr. Tom Owino ● Barrett Anderson ● Tom Jones ● Tony Putnam ● John Gambrel ● Dr. Cal Sawyer ● Dr. Ellen Vincent ● Dr. Paul Russell ● Melanie Rhulman ● Dr. Abdul Khan ● University of New Hampshire Stormwater Center

Editor's Notes

  1. Conor Here is an overview of the Clemson University watershed. Everything inside the PURPLE LINE drains into Hunnicutt Creek, and from there gets pumped into Lake Hartwell. Our project focused on the Kite Hill area which can be seen right here (point out our area)
  2. Conor Here you can see two maps of our area of interest. The map on the left illustrates subsurface storm drain pipes in red. As you can see, each flow route eventually ends up in Hunnicutt creek at the end of this pipe
  3. Conor The stormwater runoff results in heavy peak flows due to the high percentage of impervious surface area This means that nearly all of the rain that falls gets quickly transported straight into Hunnicutt Creek. This massive influx of water produces considerable erosion of the creek bed. It is also responsible for pollution transportation from the Kite Hill parking lot, which leads to destruction within the downstream ecology
  4. These two pictures are taken towards the top of our area of interest, looking towards Kite Hill This shows heavy runoff and sedimentation transportation coming off of Kite Hill and running down MacMillan Rd.
  5. This drain is supposed to be catching the runoff show in the previous slide, but as you can see, most of the water flows across the road and into the storm drain located behind the cars seen here
  6. Here is the end of the pipe network from the Kite Hill parking lot which shows the heavy volume of water and sediment The water flows from this pipe, down this stream...
  7. And into this massive crater that was created by erosion. To give some sense of scale, this is about 20 - 25 feet deep and about 50 feet across. Obviously this goes beyond the concern of stream health and into the realm of human safety
  8. We defined our problem as having a lack of infiltration with heavy pollution runoff, which leads to damage downstream in Hunnicutt Creek. Our goals of the project are both biological and structural. Our biological goals entail biologically remediating the pollution runoff. Our structural goals entail reducing peak flows for a 10 year, 24 hr storm event
  9. Conor The constraints for our project include designing around a busy existing infrastructure with high demand on space, such as traffic and parking on game day This must be taken into account when selecting locations and materials We must also be mindful of future planned construction projects that would compete for space For considerations, safety is our top priority. The area needs to not only be safe for maintenance, but for local traffic, motor or pedestrian, as well The design needs to strive for sustainability, with minimal energy and resource input for maintenance, as well as be long-lasting It needs to be aesthetically pleasing, as well as functional And as always, we want to be mindful of cost during design
  10. Conor
  11. C The image above shows the four different areas of interest for this project. Jeannie will talk to you about erosion control on Kite Hill. Ashleigh will speak about the parking lot medians and the Best Management Practices, or BMPs, associated with that Ray will propose options on different swale designs in the areas highlighted in blue, And Jeremiah and I will speak to BMPs located at the end of pipes
  12. So as for erosion control off Kite Hill,
  13. We first needed to define our area of interest. This extends from the edge of the recycling facility down to MacMillan Rd. A ridge boundary line was chosen based on the topography and likelihood of flow direction. Because an erosion analysis was dependent upon slope, the area of interest was divided into 16 segments of like conditions. Goals: Reduce Erosion from Kite Hill by 75% per yr Safe Driving Option: Gameday parking Reduce Runoff Rate by 25 % for a 25 yr- 24 hr storm
  14. real runoff 842 m3 = 29736 ft3 Using the Revised Universal Soil Loss Equation, we determined an estimated soil loss of about 23 tons per year. Using the soil-cover complex method, we estimated a runoff volume of 774 cubic meters for a 25 year, 24 hour storm.
  15. 12.64 cfs 0.357 m3 The existing peak runoff rate was determined to be about a third of a cubic meter per second for a 25 year, 24 hour storm.
  16. Spacing for Liropie is 18” Two effective means of reducing erosion are terracing and utilizing a vegetative cover better suited to reduce flows. These measures were developed with the intent that visitors would not drive over them. Our design involved two benches and three risers, with a grass covering on the benches, and liriope and pine straw cover on the risers. This design is able to reduce the overall erosion from the entire area by 92 %, as well as reduce the runoff volume over the hillside portion by 14 %, and the total area by 3.4 % Terracing is also able to reduce the overall flow rate by 25 %
  17. An alternative design would involve altering the vegetative cover only. In this design, woody-shrubbing plants such as juniper are planted not only to reduce erosion by dissipating the rainfall intensity upon the soil and reducing the runoff velocity, but also as a vegetative fence, preventing automotive traffic in certain areas that could otherwise be disturbed by the traffic. This design is able to reduce the overall erosion over the hillside area by 89%, and a 27% reduction across the entire area The runoff volume over the hillside portion could be reduced by 54%, with a reduction of 13% over the entire area Vegetative cover is also able to reduce the overall flow rate by 61 %
  18. By eliminating the hillside as an option for commuting on and off of Kite Hill, the current gate around the Recycling facility would need to be changed Currently they close the entrance gate when at the end of the work day, We would propose to realign the fences so that the business can be closed, but the driveway can remain open for commuting on and off the hill. This would require about 500 ft of new fencing and the removal of about 55 ft of fencing As another driving option, a semi-driveway can be implemented on Hwy 76, located about 400 ft from the intersection with Perimeter Road As people drive over the curb anyway, it would be better managed to have a directed access point. This drive would be 1600 sq. ft.
  19. After completing the budget for the hillside designs, it was determined that the Terraced Hillside will cost approximately $25 grand to install, which includes an additional 15 % for contingency The Vegetative Cover installation Cost is approximately $28 grand which also includes a 15% contingency
  20. The estimated budget for the fencing installation at the Recycling Center is about $8 grand, and the installation of a semi- driveway would be around $7 grand
  21. changing the manning’s n - between short and tall vegetation changing the depth of the channel from 1 foot to 6 inches . The ponding depth of the rain garden ranges between 6 and 12 inches, and the side slopes should be gently sloping (3 feet horizontal to 1 foot vertical). Side slopes that exceed this recommendation require mechanical compaction, which will ruin the infiltration capacity of the amended soil in this area and also make it much more difficult to establish plantings. 70% of the total suspended solids from 80 to 90% of the average annual runoff phosphorus removal rate to be 25 to 50%; nitrogen removal rate was estimated at 40 to 60%
  22. Made from a natural and biodegradable coconut fiber, these mats work to increase soil stabilization, effectively decreasing erosion and allowing vegetation to effectively take root (vegetation is optional). These mats are recommended for steep slopes such as stream bank erosion. - the top is buried about 6 inches underneath the top of the slope - should have seeding before mat is installed - 4 to 6 years will biodegrade naturally live stakes are dormant plant material - as they grow they will help anchor the mat - some type of tall iscantus no till - can use horticulture crops or hay and pasture overland flow - sheet flow (before mat) gives enough time for the grass to establish
  23. Hey Ash: http://www.clemson.edu/extension/hgic/plants/landscape/groundcovers/hgic1108.html http://nurcar.com/wholesale_catalog.pdf (~$4/gal) space 16” apart on center in moderate to low flooding areas. space 12” apart in extremely high overflow area. coverage area: pi*8”*8” = ~200 sq in = ~ 1.4 sq ft. Find required area, divide by 1.4 sq ft = # of plants you need * $4/plant. Sugars.
  24. For soil group B reduction TSS = 60% TP = 32% TN = 36%
  25. For low flows, check-dam geometry and swale width are actually more influential on flow than stone size. The average flow length through a check-dam as a function of flow depth can be determined by the following equation:
  26. For low flows, check-dam geometry and swale width are actually more influential on flow than stone size. The average flow length through a check-dam as a function of flow depth can be determined by the following equation:
  27. For low flows, check-dam geometry and swale width are actually more influential on flow than stone size. The average flow length through a check-dam as a function of flow depth can be determined by the following equation:
  28. For low flows, check-dam geometry and swale width are actually more influential on flow than stone size. The average flow length through a check-dam as a function of flow depth can be determined by the following equation:
  29. C So we have all these design solutions upstream of the pipe, but they are not enough to thoroughly remediate pollutants The most common end of pipe BMPs are detention basins and retention basins. A detention basin is dry in between storms, while a retention basin has a permanent pool of water. We focused on a detention basin design, as well as a “hybrid” between the two, called a submerged gravel wetland
  30. C Here we see an example of a detention basin. Detention basins are typically used to manage peak runoff from large storm events While they can remove some sediments in runoff, they remove little to no pollutants The size of the detention basin needed to treat the runoff for our area of interest would be about 200’ x 100’ with a depth of 8’ This size would be large enough to treat a 100 year, 24-hour storm event As one of our original goals was to remove pollutants from the runoff coming off Kite Hill, this design would not be our preferred BMP
  31. J This figure illustrates a model developed by the University of New Hampshire. There is a sedimentation forebay before the first cell. Flow travels from the forebay into the surface region of the next cell. The vertical perforated pipes seen here use an elevation head and hydrostatic pressure to force flow through the subsurface system The subsurface layer is always submerged, creating an anoxic zone where facultative anaerobic microbes can metabolically decompose pollutants While this system typically requires a liner to prevent water infiltration into the soil below, the hydraulic conductivity of the soil in our area of interest is low enough to not require one In the event that flow reduces to zero, the system remains in a stable state, where further pollutant decomposition can occur Our modifications incorporate a concrete-core-reinforced earthen dam between each cell. This system can withstand both extended droughts and peak flows from a large storm event.
  32. Using parameters we found from From the California EPA State Water Resources Control Board We started looking into calculating the settling velocity using a classic form of Stokes law, but found too much variability. We later came across a simplified version of Stokes law in an SCDOT Stormwater manual that that fell under the same parameters we were working under. We calculated the settling velocity, the discharge for a 2 yr, 24 hour storm, and the effective surface area, length, and width for 90% sediment removal. SCDOT Stormwater Manual Reports Cecil as d15 = 0.0066 ~ 0.0043 mm If d15 < 0.01 mm, use simplified Stokes, where, d = particle diameter in mm Vs = settling velocity in ft/s Designing the channel as parabolic ensures uniform velocity along any cross-sectional slice normal to the channel length regardless of position within the cross-section (Assoc. Prof R.J. Keller, CIV3264, Dokuz Eylül University, Turkey)
  33. J From our literature review, we found that nearly all surface pollutants are washed off in the first fifth of an inch of rain. This first flush became a necessary parameter to accommodate in our design. We also needed to allow enough residence time for the microbes to decompose the pollutants. We therefore sized the submerged zone within our gravel wetland to accommodate both this first flush plus our water quality volume of 1 in over the entire 4.15 acres, as well as the necessary hydraulic retention time needed to obtain the same results as the Univ. of New Hampshire study. This design size also reduces the peak flow of of a 10 year, 24 hr storm by ~90%
  34. Here we see a representative diagram of how we are proposing to lay out this design. A maintenance crew could access the basin from a proposed service road which would run alongside the forebay. (if asked: A crew with shovels, or potentially a bobcat could dredge out the wetland cells.)
  35. J This hydrograph illustrates roughly a 90% reduction in peak flow from the University of New Hampshire study. To get a similar influent peak flow in Clemson, SC would require a 5-yr, 24hr storm (NOAA data). This design would reduce a 5 year peak flow from about 300 GPM to about 30 GPM.
  36. J This figure illustrates the percent reduction of pollutants in this study. TSS, TPH-D, DIN, and heavy metals such as ZN are all reduced by more than 90%. The performance in P removal was much less than the other pollutants in this study. However there was still more than 50% removal. (DIN has a similar performance in the warmer months, but considering this study was conducted in New Hampshire, our warmer climate in SC will allow for greater microbiological activity, likely improving the performance in colder months.) TSS - Total Suspended Solids TPH-D - Total Petroleum Hydrocarbons as Diesel DIN - Dissolved Inorganic Nitrogen (sum of nitrate and ammonia) Zn - Zinc TP - Total Phosphorous
  37. J Here we see a checklist for maintenance to be performed about every 6 months which would include dredging and checking for plant health (if asked: from our literature review, we found a common round estimate of $1500/yr in maintenance)
  38. J We performed a rough itemized cost estimate for the gravel wetland. Our rate values came from interviews and web references. A more accurate estimation would come from the R.S. Means Building Construction costs, but purchasing access to this alone would have exceeded our design budget. Our price for a detention pond was referenced from a published estimation by a professor at the Univ. of Alabama. Adjusting for contingency, our cost estimation for installation of the gravel wetland was under $30,000. The cost estimation for the detention pond was about $20,000.
  39. Conor Sustainability measures for this project include economic sustainability - we want it be economically feasible both in the installation and maintenance phases Ecological sustainability is obvious - we want to improve the health of Hunnicutt Creek There is also a measure of social sustainability as we want to do our best to preserve the natural resources that we have for future generations Ethical consid
  40. In summary, we saw a significant improvement from existing conditions with each individual measure. With the added benefit of breaking our analysis into modules, each element can be implemented individually, collectively, or sequentially as per the User’s preference. The cost range from our lowest collective cost options to the highest collective cost options ranges from $92,000 to $415,000.
  41. So when we started this project, we asked three questions each likely asked by the end user, the client, and the designer 1. No 2. Depending on the designs chosen, maintenance will vary, but in general, the designs are mostly low maintenance. 3. While aesthetics are of course subjective, the designs presented all take aesthetics into account 1. The overall drainage design was made to allow the different system elements to be implemented at different times 2. Depending on the designs chosen, the total cost for the projects range from $70,000 to $400,000 3. Given proper maintenance, the structures should last be able to last indefinitely, or at least until the next major project in the area 1. Must work within the EPA stormwater regulations, Clemson University design standards, “Waters of the US” under the Clean Water Act 2. Given proper maintenance, the structures are resilient and are able to withstand large storms 3. Clemson University has set aside about $150,000 for this area
  42. R
  43. Boo jah
  44. Boo jah
  45. Boo jah