Rolling Greens/Bald Hill Nursery

An Inventory of Perspectives…a real mess!
Land in Conflict framework
Chapters:
4. Assessing and understanding the
stakeholders, issues and interests
5. Designing a ...
Guiding Process Principles
•
•
•

Engage early
Listen and learn first
Build on interests, not
positions

•

Design and bui...
Chapter 4
Assessing and understanding the stakeholders,
issues and interests
Assessment in North Kingstown
•

CBI Assessment Phase I and II
Phase I – interviews with local stakeholders; interviews an...
Assessment in North Kingstown

•

Town Council ordered 2nd assessment from CBI after
adoption of zoning and closure of Vil...
Chapter 5
Designing a process for collaboration
1. Design the process with, not for the people
2. Undertake an assessment
...
Design of the North Kingstown Process
•Who is included in designing the process? TC said, this is a Planning Department st...
Chapter 6
Facilitating deliberation
Facilitating deliberation:
The Beginning Phase
Clarify How Decisions Will Be Made
• Link with the Intent of the Process
• How much Agreement is needed?
• Determine what ...
Facilitating the Beginning Phase
in North Kingstown

•
•
•
•
•
•

Ground-rules – how, when, and conduct;
What is consensus...
Facilitating deliberation: The Middle Phase
Trust
Strategies for Dealing with Difficult People

•
•
•
•
•
•
•
•

Enforce the Groundrules
Acknowledge concerns
Talk Privately...
Facilitating the Middle Phase
in North Kingstown

•
•
•
•
•
•
•
•
•
•

TRUST!!!!!! Building it was challenging and for som...
Build out
Facilitating deliberation: The End Phase
Facilitating the End Phase
in North Kingstown

•Deadline of Town Council’s last meeting
•VOTING!!!!
•Scenario solutions of...
Chapter 7
Implementing Agreements

•

The Steps of Implementation

1. Incorporate the agreement into a proposal
2. Advise ...
Monitoring Implementation
Recommendations for Effective Implementation

•
•

Discuss implementation early

•
•
•

Clarify roles, responsibilities, a...
Implementation in North Kingstown

•
•
•
•
•
•
•
•

It was never hidden why this deadline was in place; openly
discussed a...
Village
Lessons Learned

•
•
•
•
•
•
•
•
•

We reached consensus, but was that successful?
Needed more time, maybe would not have ...
Lessons Learned
continued…

•
•
•
•
•
•
•

Avoid the pitfalls, what where they at each phase?
Great consultants and design...
Rolling Greens/Bald Hill Nursery
Rural
Gateway/Emerging
Growth Center
Recommendation
from South County
Design Manual
RIDEM...
Questions???
•
•

Stacie Smith
Consensus Building Institute

•
•

Jonathan J. Reiner, AICP
North Kingstown Planning Depart...
SNEAPA 2013 Thursday a2 9_15_mutual gains
SNEAPA 2013 Thursday a2 9_15_mutual gains
SNEAPA 2013 Thursday a2 9_15_mutual gains
Upcoming SlideShare
Loading in...5
×

SNEAPA 2013 Thursday a2 9_15_mutual gains

301

Published on

Land in Conflict. Managing and Resolving Land Use Disputes

Published in: Real Estate, Technology
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
301
On Slideshare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
2
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide
  • Another example of the possibilities of Conservation Development shows an existing rural landscape before development.
  • SNEAPA 2013 Thursday a2 9_15_mutual gains

    1. 1. Rolling Greens/Bald Hill Nursery An Inventory of Perspectives…a real mess!
    2. 2. Land in Conflict framework Chapters: 4. Assessing and understanding the stakeholders, issues and interests 5. Designing a process for collaboration 6. Facilitating deliberation 7. Implementing agreements
    3. 3. Guiding Process Principles • • • Engage early Listen and learn first Build on interests, not positions • Design and build an effective process • Involve many, not just a few • • • Learn jointly • • Be transparent Use a skilled facilitator Build relationships for the long-term Be responsive
    4. 4. Chapter 4 Assessing and understanding the stakeholders, issues and interests
    5. 5. Assessment in North Kingstown • CBI Assessment Phase I and II Phase I – interviews with local stakeholders; interviews and feedback would dictate the process Planning Commission shot down CBI project after 1st assessment PC felt that assessment was redundant, they already knew background and resident concerns… Application for new zoning district, tied to this intersection, moved on….Public feels disconnected Took over 1 year to adopt an ordinance that should have taken a few months; public fought new mixed use ordinance for fear of how it would apply at intersection • • • • •
    6. 6. Assessment in North Kingstown • Town Council ordered 2nd assessment from CBI after adoption of zoning and closure of Village Project reports I, II, III Process and results oriented; Consultant team selection Had a strict mission – determine a vision and mix of uses; complete process in 4 months Spoke to original stakeholders and got other names of people to speak with further in the process It was never hidden why this deadline was in place; openly discussed and debated numerous times Had people on both sides objecting that this has already taken too long, why even have this process…. • • • • •
    7. 7. Chapter 5 Designing a process for collaboration 1. Design the process with, not for the people 2. Undertake an assessment 3. Select the participants carefully 4. Link collaborative processes explicitly to formal decision-making 5. Provide multiple forms of participation to ensure full engagement 6. Ensure that technical support is professional, credible and publicly legitimate 7. Set specific timeframes and deliverables
    8. 8. Design of the North Kingstown Process •Who is included in designing the process? TC said, this is a Planning Department study – Planning, figure it out; Planning Dept and CBI – designed process Stakeholder group – who is on; are elected officials or those running for office; TC appointed group, and said take recommendations into consideration; no guarantee that TC would agree; Voting and non-voting members; Set timeframe – wanted decision prior to the election; TC felt that they had been dealing with this issue for over 2 years! Stakeholder meetings; neighborhood focus meetings; open public meetings; Simultaneously while Rolling Greens application was pending; What are the constraints and opportunities for the future of this intersection? What does the future of this intersection look like? What is that vision? What can we agree upon to narrow down the issues? Planning Commission and Town Council need direction from this group and the residents on the proper type and intensity of development at this intersection. • • • • • • • • • •
    9. 9. Chapter 6 Facilitating deliberation
    10. 10. Facilitating deliberation: The Beginning Phase
    11. 11. Clarify How Decisions Will Be Made • Link with the Intent of the Process • How much Agreement is needed? • Determine what happens if decision threshold cannot be met. • Clarify responsibilities of approval (e.g., not blocking later) • Possible decision rules: • Majority • Super-Majority (i.e., 2/3s, 3/4s, 90%) • By Interest/Stakeholder Group • No blockers • Unanimity
    12. 12. Facilitating the Beginning Phase in North Kingstown • • • • • • Ground-rules – how, when, and conduct; What is consensus; defining consensus – 2 meetings to complete/figure out; Non-voting members/voting members; Involvement of abutting municipality as 2 nonvoting members; Meetings every 3 weeks; tight timeframe; What information (technical) was needed to make a decision: aquifer, traffic, environment, stormwater, and open space.
    13. 13. Facilitating deliberation: The Middle Phase
    14. 14. Trust
    15. 15. Strategies for Dealing with Difficult People • • • • • • • • Enforce the Groundrules Acknowledge concerns Talk Privately Account for Emotional Intensity Separate the gripe from the griper Analyze and name the problem Use different process techniques Engage broader constituencies
    16. 16. Facilitating the Middle Phase in North Kingstown • • • • • • • • • • TRUST!!!!!! Building it was challenging and for some was never achieved (but did occur for others) Work Plan was based upon existing zoning and issues Zone change and Master plan for Rolling Greens was submitting and on hold/slowly moving forward….. Address technical questions on: aquifer, traffic, environment, stormwater, open space, NIMBY Smoke and mirrors; hidden agendas Bickering No innovative ideas that came out of this process Design scenario options Ability to rely on past meeting summaries What can go there today?
    17. 17. Build out
    18. 18. Facilitating deliberation: The End Phase
    19. 19. Facilitating the End Phase in North Kingstown •Deadline of Town Council’s last meeting •VOTING!!!! •Scenario solutions of different options for development; broke down into elements – i.e. bike paths and sidewalks; open space; per property uses and densities; roundabout. Tradeoffs and negotiating at the table Developing a package of a preferred overall solution In between the highway and the new zoning district, those residential neighborhoods surrounding this intersection will not change Goal to reinforce the southern rural farmland, and to protect what is not protected • • • •
    20. 20. Chapter 7 Implementing Agreements • The Steps of Implementation 1. Incorporate the agreement into a proposal 2. Advise the decision makers during the required process 3. Monitor implementation
    21. 21. Monitoring Implementation
    22. 22. Recommendations for Effective Implementation • • Discuss implementation early • • • Clarify roles, responsibilities, and timelines Keep lives of communication open throughout implementation Decide on timelines Decide on Consequences
    23. 23. Implementation in North Kingstown • • • • • • • • It was never hidden why this deadline was in place; openly discussed and debated numerous times Adoption by PC and TC process A hectic November, especially the last full week Mismatched ads – hurdles with that adoption Hurt feelings 2 lawsuits pending; objections at SWP x2 Appeal decision through SWP and abutting municipalities PC now reviewing the Preliminary plan
    24. 24. Village
    25. 25. Lessons Learned • • • • • • • • • We reached consensus, but was that successful? Needed more time, maybe would not have had the residual lawsuits Some of the details got lost, and details are important Trust – people should trust, or we need to get public to trust us, planners and consultants Where did we go wrong? What happens if you get outvoted? Would there have been any outcome, other than NO CHANGE, that would have prevented the town from getting sued by abutters? As soon as the abutters/stakeholders felt invalidated, they tried to undermine the process! Buy in from our Planning Commission – they didn’t get it; SOUR APPLES – they were undermining the process during the process and spreading misinformation;
    26. 26. Lessons Learned continued… • • • • • • • Avoid the pitfalls, what where they at each phase? Great consultants and designed scenarios, but public did not believe what existing zoning would allow or that it could be built Take some pictures to document this process Solution is MUCH better than what was allowed under previous zoning Process is about getting to solutions, not making everyone happy May develop some allies and enemies through this process It is taking too long to do nothing!
    27. 27. Rolling Greens/Bald Hill Nursery Rural Gateway/Emerging Growth Center Recommendation from South County Design Manual RIDEM, 2001
    28. 28. Questions??? • • Stacie Smith Consensus Building Institute • • Jonathan J. Reiner, AICP North Kingstown Planning Department • • Nathan Kelly, AICP Horsley Witten Group