Hot Aisle & Cold Aisle Containment Solutions & Case Studies

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

0 comments

Post a comment

    Post a comment
    Embed Video
    Edit your comment Cancel

    1 Favorite

    Hot Aisle & Cold Aisle Containment Solutions & Case Studies - Presentation Transcript

    1. Hot Aisle and Cold Aisle Containment Strategies & Case Study Presenters: Justin Blumling – Product Manager Steve Lewis – Director of Sales ©2009 42U All rights reserved
    2. Agenda • Introduction • Airflow Management Strategies • Aisle Containment – Cold Aisle & Hot Aisle • Containment Case Study • Q&A ©2009 42U All rights reserved 2
    3. “Data centers worldwide now consume more energy annually than Sweden” -- New York Times ©2009 42U All rights reserved 3
    4. Inefficiency + Demand • Server utilization – 30% are comatose (Uptime Institute) • Overprovision – SLAs • Ownership – IT/Facilities disconnect • Demand for data center services Source: Gartner ©2009 42U All rights reserved 4
    5. Data Center Dilemma Legacy Facility Sluggish Economy “The majority of existing data centers… “Server unit shipments declined 26.5 lack the capacity and operational percent year over year in 1Q09” efficiency to meet the needs of the next 10 years.” - Data Center Knowledge - Gartner Availability Performance Cost Cutting Efficiency Concerns “[T]he current economic environment forced 61 percent of respondents to cut “Forty-seven percent of respondents listed budgets; while 35 percent of respondents energy efficiency as one of their top were forced to delay data center build or facilities and network concerns” expansion projects. - Emerson Liebert Data Center Users’ - Emerson Liebert Data Center Users’ Group Survey Group Survey ©2009 42U All rights reserved 5
    6. Airflow Management Remote Heat Rejection ©2009 42U All rights reserved 6
    7. CFD Analysis ©2009 42U All rights reserved 7
    8. Thermal Imaging Thermal Maps show where there are hot and cold spots within the data center, indicating areas of potential risk. Based on sensors placed at the top, middle and bottom of the instrumented racks. ©2009 42U All rights reserved 8
    9. Thermal Imaging – Baseline Baseline H C H C No Containment High Degree of Air Mixing High Inlet Temperatures ©2009 42U All rights reserved 9
    10. Solution Overview Impact of Aisle Containment ©2009 42U All rights reserved 10
    11. Cold Aisle Containment (CAC) • Cold air directed to server inlet; hot air dispersed into room • Mixing eliminated • Conventional cooling units (CRACs) installed outside the containment area ©2009 42U All rights reserved 11
    12. Cold Aisle Containment Advantages • Focused on air supply to the racks: the only ASHRAE standards exist there (temperature and humidity) • Addresses the prevalence of existing raised floor environments • Capacity and efficiency gains for existing environments ©2009 42U All rights reserved 12
    13. CAC: Existing Data Center After Containment H C H C Cold Aisles Contained No Change to CRAHs Overcooled ©2009 42U All rights reserved 13
    14. Existing Data Center- With Control With Control H C H C Controlled CRAHs with possible higher set points, Lower Fan Speeds and Increased Water Supply Temperatures ASHRAE Inlet Temperatures Increased Return Temperatures ©2009 42U All rights reserved 14
    15. Hot Aisle Containment (HAC) • Seen above with modular CHW InRow air conditioners • Increased return temperature to cooling coil to maximize efficiency • Can be accomplished with false/drop ceilings and “chimney cabinets” ©2009 42U All rights reserved 15
    16. Hot Aisle Containment Advantages • Contains hot aisle; rest of data center akin to server inlet temp • The “room volume” of cold air is available in case of cooling failure • Independent of raised floor variables. • Capture server exhaust air at its hottest point ©2009 42U All rights reserved 16
    17. “Curtain Containment” Cold Aisle Hot Aisle CAC: • “Strip Door” at aisles • roof above HAC: • “Strip Door” at aisles • ceiling return for heat removal ©2009 42U All rights reserved 17
    18. Shared Advantages • Eliminates mixing through airflow management • Allows “tuning” of airflow: CFM supply to match CFM demand • Promotes warmer return temperatures to computer room air conditioners • Provides better supply temperature control – Mid 70s supply temperature – No hotspots ©2009 42U All rights reserved 18
    19. The Wild Card: Your Data Center • Uniformity of racks and aisles? • Rack manufacturer offer containment solution? • Ceiling plenum for hot aisle containment? • Raised floor clear or full of obstructions? ©2009 42U All rights reserved 19
    20. HAC Curtain Case Study INTRODUCTION • An electronics manufacturer, with an extensive IT portfolio, wanted to optimize a lab environment • Labs contained a variety of IT equipment: blades, 1U servers, switches – Arranged in hot aisle/cold aisle but not all uniform – Everything overhead: cold air supply and hot air return • Plagued by airflow challenges – Supplemental exhaust fans installed on top of cabinets – Rear door air removal unit used to channel higher density exhaust directly into the plenum – Portable AC units throughout the floor Turned to 42U to explore cooling optimization and containment solutions ©2009 42U All rights reserved 20
    21. Containment Installation ©2009 42U All rights reserved 21
    22. Containment Installation Cold Air Supply Exhaust Fans Containment attached to ceiling with fuseable link ©2009 42U All rights reserved 22
    23. Installation Continued Containment Curtains Supplemental Rack Air Movement Portable AC ©2009 42U All rights reserved 23
    24. Following Installation ENERGY SAVINGS • (21) rack “air removal units” turned down to their minimum CFM (400): decrease in 33,600 CFM • Exhaust fans (used to force heat out of the room) completely turned off • (4) portable air conditioners simply moving air; no compressor activity RELIABILITY • Inlet temperature stabilization; hotspots eliminated COMFORT COOLING • Without air mixing, lab working environment is much more comfortable NOISE CONTROL • Offices, which surround the lab perimeter, aren’t subjected to the maximum CFM from the air removal units ©2009 42U All rights reserved 24
    25. CAC: New Build Conventional Approach CAC New Build New Build Scenario: 306 kW load installed using Cold Modeling CAC vs traditional install approach Aisle Containment design Scenario: 306 kW load installed using traditional design Qty(18) 17kW racks, Load = 306kW room area: 896 Sq Ft (32’ x 28’) Qty (102) 3kW racks, Load = 306kW room area: 3000 Sq Ft (60’ x 50’) 24” raised floor 10’ from floor to ceiling 24” raised floor 10’ from floor to ceiling Source: EDS ©2009 42U All rights reserved 25
    26. Containment: Next Steps Cold Aisle Containment Cold Aisle Containment with InRow Cooling with Overhead Cooling Cold aisle containment ©2009 42U All rights reserved 26
    27. Containment: Next Steps Close Coupled Cooling • Dual containment within the same rack footprint- • Chilled water or refrigerant based cooling • High density, high efficiency •Hot air has no choice but to pass through HEx Front of cabinets and Rear of cabinets and cooling unit cooling unit ©2009 42U All rights reserved 27
    28. Data Center Dilemma Legacy Facility Sluggish Economy “The majority of existing data centers… “Server unit shipments declined 26.5 lack the capacity and operational percent year over year in 1Q09” efficiency to meet the needs of the next 10 years.” - Data Center Knowledge - Gartner Availability Performance Cost Cutting Efficiency Concerns “[T]he current economic environment forced 61 percent of respondents to cut “Forty-seven percent of respondents listed budgets; while 35 percent of respondents energy efficiency as one of their top were forced to delay data center build or facilities and network concerns” expansion projects. - Emerson Liebert Data Center Users’ - Emerson Liebert Data Center Users’ Group Survey Group Survey ©2009 42U All rights reserved 28
    29. An Efficiency Study Process Data Center Survey Best practices & ROI Potential rebates Plan Executive managerial buy-in Establish efficiency team & goals Determine methodology Install instrumentation & software Benchmark Perform energy utilization audit Calculate current benchmark Data Collection Environmental Measure Monitoring Analysis Recommendations Reconfiguration plan Remediate Efficiency improvements Facilities Data Infrastructure Data Report IT Equipment Data Environmental Conditions Design and limitations Efficiency improvements ©2009 42U All rights reserved 29
    30. • Steel containment is more The Reality aesthetic but better suited for What can I do today? new builds. • Hot Aisle Containment can require extensive rework to deploy in existing cabinet rows. • Curtain solutions, though not beautiful, offer flexibility ©2009 42U All rights reserved 30
    31. Q&A For a copy of today’s presentation please email rebecca.mccue@42U.com For additional information on 42U’s products and services, please visit: http://www.42U.com ©2009 42U All rights reserved 31
    32. Thank You! ©2009 42U All rights reserved 32
    SlideShare Zeitgeist 2009

    + 42U42U Nominate

    custom

    475 views, 1 favs, 0 embeds more stats

    The segmentation of data centers into alternating h more

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 475
      • 475 on SlideShare
      • 0 from embeds
    • Comments 0
    • Favorites 1
    • Downloads 15
    Most viewed embeds

    more

    All embeds

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories